Checked before it is covered
Most construction defects are hidden within days: reinforcement disappears into concrete, drains into backfill, wiring behind plaster. Supervision works by inspecting each stage before it is covered, when a correction costs minutes rather than a demolition; our house construction supervision checklist lists the checks stage by stage.
Measured, not eyeballed
Because we are surveyors, setting out and levels are checked with instruments, not by eye. A column grid a few centimetres out, or a floor level wrong by a step, is found on the day it happens, not when CDA measures the plinth for a completion certificate in Islamabad.
A record you can rely on
Every visit produces a short written report with photographs: what was inspected, what was wrong and what was put right. For owners abroad, it is the next best thing to being on site.
Where we stop the work and look
An inspection point is a stage the builder may not pass until it has been checked. We agree the list with you before work starts, because the right points depend on the building. For a typical house or small block they fall here:
| Stage | What is checked before work continues |
|---|---|
| Setting out | Corners, grid lines and the datum level against the drawings, measured with instruments |
| Excavation | Depth and width of footings, the founding layer and any water or buried services found |
| Reinforcement | Bar size, spacing, laps, cover blocks and the fixing of starter bars, against the structural drawings |
| Formwork | Alignment, plumb, level, bracing and cleanliness before concrete is placed |
| Concreting | Mix delivered against the specification, placing, compaction, curing and the test samples taken |
| Services and drainage | Pipe falls, joints, sleeves and chases, tested before they are buried or plastered over |
| Finishes | Levels, slopes to drains in wet areas, waterproofing and workmanship against the specification |
Some checks come with a test: the water test on a drain, the slump and cube samples on concrete. We record who took the sample, which pour it came from and where it was sent, so the result can be tied to a part of the building later.
What a non-conformance note says
When work does not match the drawing or specification, we write it down the same day: what was found, where, which drawing or clause it departs from, a photograph, and what must be done before work continues. The builder signs the correction when it is made, and we re-inspect. A defect is closed only when the re-inspection is recorded, so the file shows the whole story rather than a list of complaints.
Independent of the builder
A builder who inspects their own work has every reason to move on. Supervision is useful because the person checking has no stake in the schedule or the margin. We report to you, not to the contractor, and we say plainly when work passes. If the structural or architectural drawings are unclear, we raise it with the designer before the contractor guesses.
What you hold at hand-over
At completion you should have the inspection reports in order, the closed non-conformance notes, the test results tied to their locations, and an as-built record of what was built. Together they are the evidence for a later extension, a sale, a bank valuation or a completion certificate. Keep them with the title documents.
The measurements behind supervision
Supervision relies on survey: setting out is checked with the methods of our engineering survey, and completed work is recorded in an as-built survey. We supervise work built to our own architecture and interior design, or work by any contractor, including our own construction team, where an owner wants a second check. How we measure and record is described on our standards page. See all our design and build services. Our background is described on the about page.