Building and approvals

CDA completion certificate for a house in Islamabad: stage inspections, forms and fines

Published · 10 min read · RN Tech Associates · in Building and approvals

Short answer

A CDA completion certificate is CDA's permission to occupy a building, and no house in Islamabad may be lived in without one. Under CDA's building regulations, as amended in 2023, the enlisted architect inspects at nine stages, files Form-D at plinth and before every slab, and within a month of completion the owner files Forms B-1 and B-2 with six sets of as-built drawings. CDA then inspects and decides.

CDA completion certificate for a house in Islamabad: stage inspections, forms and fines

Key points

  • The rules are the ICT Residential Sectors Zoning (Building Control) Regulations 2020 (S.R.O. 1575(I)/2019), amended by S.R.O. 1074(I)/2023.
  • Nine stage inspections by the enlisted architect are compulsory; each report goes to CDA's One Window within seven days.
  • Form-D at plinth level puts the plot lines, setbacks and plinth level on record; CDA's Land Survey Division verifies them within 15 days.
  • Notice of completion is due within one month: Form B-1 (owner), Form B-2 (architect) and six sets of completion drawings.
  • More than 15% change from the approved plan, or a main structural change, doubles the scrutiny fee.
  • Since 2023, living in a house without a certificate costs Rs 5,000 a month, under regulation 2.8.1.

Which rules apply

A house in Islamabad gets its completion certificate under one set of CDA regulations, and it has been amended once. The base text is the Islamabad Residential Sectors Zoning (Building Control) Regulations 2020, notified as S.R.O. 1575(I)/2019 on 23 December 2019, published in the Gazette of Pakistan on 26 December 2019 and in force from 1 January 2020. CDA amended it by S.R.O. 1074(I)/2023, notified on 10 August 2023 and published in the Gazette on 16 August 2023. Both are on CDA’s laws and regulations page. The 2023 text is the latest we could read; we found no later notified change to the completion procedure for houses.

The regulations “extend to all private and public land / plots in the Islamabad Capital Territory, except for those in the Diplomatic Enclave” (regulation 1.1.02). Three changes in 2023 matter to a house owner: the architect is now called the “Enlisted Architect” instead of the licensed architect, the fine for living in an uncertified house changed, and a transfer NOC can now be processed while a completion certificate is “in process”.

The completion certificate is also called “permission to occupy”. Regulation 5.6.1 makes it mandatory before any building in the Islamabad Capital Territory is occupied. The Zameen news report that most search results lead to dates from April 2017 and quotes no regulation; this guide works from the regulation itself.

The nine stage inspections

The completion certificate is earned during construction, not at the end. Regulation 3.12.8 makes an inspection by the enlisted architect compulsory at nine stages, and each inspection report must reach CDA’s One Window Operation (OWO) within seven days. Because each stage is inspected, the same stages are a sensible way to tie payments in your contract with the builder to checked work.

No. Stage (regulation 3.12.8) What it puts on record
1 Ground demarcation of the area to be dug The house is in the right place on the plot, with setbacks clear
2 Foundation of basement, if any (rules in our basement guide) Basement footings as designed
3 Roof level of basement, before pouring the slab, if any Basement slab steel and level
4 Ground floor at damp-proof course (DPC) level, including the boundary wall Plinth level, plot lines and building lines (this is also the Form-D stage)
5 Roof height of the ground floor, before the roof slab is poured Ground floor walls, columns and slab steel
6 Roof height of the first floor First floor and its slab
7 Roof height of any further floor Each further floor
8 Roof height of the water tank and stair tower (mumty), if any Rooftop structures within limits
9 Completion of the building and all other requirements Ready for the notice of completion

CDA can also inspect “at any time” without notice, before approval, during the work or after (regulation 3.12.7). If it finds work that does not follow the approved plans, it can order alterations or amended plans, and if the owner does nothing, stop the work or demolish the part that breaks the rules at the owner’s cost (regulation 3.12.9). Our house construction supervision checklist sets out what to check at each of these stages.

Plinth and building-line verification: Form-D

Form-D is the most important form in the whole process, because it fixes the plot lines and the plinth level before the walls go up. Regulation 5.5 says that once the foundations and the ground floor are done to plinth or DPC level, with the compound wall at least at the corners, the owner submits Form-D through the enlisted architect. The architect certifies “the plinth, the plot size and the building lines” and issues a provisional certificate, and work may continue once that is submitted to CDA’s Building Control Section.

A copy goes to CDA’s Land Survey Division, which verifies “Plot lines, Plinth level, Plot size and the building lines” within 15 days and reports to the owner, the architect and the Building Control Section. If it finds a discrepancy, the construction must be corrected before a final certificate is issued; if it is not corrected, “the Owner may be penalized and violated portion may be demolished”. Form-D is then repeated “at all slabs levels (before pouring the concrete)”.

Two limits are measured here and again at completion. The plinth may not be higher than 3 ft 6 in for terraced or attached houses and 5 ft for others, above the mean level of the front road (regulation 4.1.14). The setbacks must be clear. Both are survey measurements. We check plot corners, setbacks and plinth level with a total station before the architect signs, using the methods of our engineering survey work, so the Land Survey Division’s visit confirms the numbers rather than finds them.

Filing the notice of completion

Within one month of finishing the construction, the owner must deliver a notice of completion on Form B-1 to CDA’s OWO, with Form B-2 and the completion drawings, “duly signed by the Enlisted Architect who supervised the construction” (regulation 3.12.10). Regulation 5.6.2 splits the papers into two folders. The scrutiny fee for the completion certificate equals the approval scrutiny fee (regulation 3.11.1(v)).

Folder Goes to What it holds (regulation 5.6.3)
Folder I Estate Management (EM-I for residential buildings) Form B-1 (original); Form B-2 (attested copy); allotment or transfer letter; possession certificate; sub-division letter if any; CDA’s acceptance of attorney if any; owner’s or attorney’s CNIC; pay order of the scrutiny fee
Folder II Building Control Section (BCS) Form B-2 (original); Form B-1 (attested copy); completion drawings (as-built), six original sets; allotment or transfer letter; possession certificate; contour plan if applicable; sub-division letter if any; attorney letter if any; CNIC; all Form-Ds (originals); soil investigation report if applicable; pay order

On CDA’s forms page (the copies posted with the forms for private housing schemes), Form B-1 is the owner’s letter saying the work “has been carried out in accordance with the Building Plans approved” and applying for permission to occupy. Form B-2 is the architect’s and engineer’s certificate that the building was completed under their supervision in line with the approved plans, with an indemnity to CDA. Estate Management forwards its NOC to BCS, and BCS writes to the owner to arrange the site inspection (regulations 5.6.5 and 5.6.7).

The six sets of completion drawings must show the house as built, not as approved. What they should contain, and how to produce them, is in our guide to as-built drawings and record drawings.

What CDA’s inspector checks

The inspector verifies the house “according to the completion plan (As Built Drawings)” and checks eleven items in particular (regulation 5.6.8). Each one can be checked before you file.

Item checked by CDA The rule behind it Check it yourself before filing
Form-D certificates Regulation 5.5 All Form-Ds present, plinth and every slab
Maximum plinth level from the front road (average) level 3 ft 6 in terraced or attached, 5 ft others (4.1.14) Level the plinth against the mean front road level
Height of ramp Not higher than 12 in at the gate for houses (5.7) Measure the ramp at the gate
Drainage grating at gate level Required at the gate (5.7) Grating in place and draining
Sewer connection to CDA mains Separate sewer and storm lines (5.7) Connection made; basement pumping if any
Storm water connection to CDA mains As above Connection made
Mandatory setbacks The approved plan and schedule Measure setbacks from the plot lines
Total covered area The approved plan Measure each floor’s outline
Emergency exits Where applicable Usually not for a house
Fire-fighting arrangements Buildings of more than three storeys Usually not for a house
Extra water tanks for rainwater harvesting or emergency Rainwater harvesting compulsory on plots of 400 sq yd and above (4.1.2) Tanks built as approved

The fire and emergency-exit rows seldom apply to a house, but they do apply if part of the building becomes a shop, office or clinic; the fire safety provisions for commercial fit-outs set what that part needs.

If there is no change from the approved plan, or the house is otherwise within the regulations, and the fee is paid, the Deputy Director of the Building Control Section issues the completion certificate (regulation 5.6.9). The architect’s termite-proofing certificate is also attached to the completion documents (regulation 3.12.6).

When the house differs from the approved plan

Differences do not stop a completion case by themselves, but they cost money and time. If the completion plan shows a change of more than 15% from the approved plan, as determined by the Deputy Director BCS, or there are main structural changes, CDA charges double the scrutiny fee on top of the normal completion scrutiny fee (regulations 3.11.1(iii) and 4.1.4). A change that breaks a rule, such as a setback built over or a plinth above the limit, is a different matter: CDA can require alteration or amended plans under regulation 3.12.9. A plinth above the limit is treated as a storey, because “that floor will be considered as ground floor” (regulation 4.1.14).

The honest order of work is: measure the house, compare it with the approved plan, list every difference, and decide with the architect which need amended plans before filing. Hiding a difference in drawings that copy the approved plan does not work, because the inspector checks the building against those drawings. The approved plan itself is valid for five years from approval (regulation 3.12.2).

Living in the house without a certificate

Regulation 2.8.1 says no building may be occupied or used without a completion certificate obtained from CDA “within three (3) months after the expiry of initial construction period”, and sets a fine for those who occupy without one. The 2020 text fixed it at Rs 50,000 a year for residential buildings and Rs 100,000 a year for other buildings. The 2023 text changed it to Rs 5,000 a month for residential buildings and Rs 10,000 a month for others for the first year, “and would be doubled thereafter”.

The certificate matters when you sell, too. Under regulation 9.4.4, as amended in 2023, CDA’s Building Control Section processes the NOC for a transfer, lease or legal-heir case only for buildings whose completion certificate “were issued by Authority or in process”, and only where no violation exists at site. Before issuing that NOC, BCS carries out a survey measurement of the property’s covered area and plot size (regulation 9.4.3).

Houses in private schemes, and in Rawalpindi

In a private housing scheme inside the Islamabad Capital Territory, the owner files the same Forms B-1 and B-2 at CDA’s One Window. The regulations add a step: the case goes first to CDA’s Directorate of Housing Societies, which checks that the scheme’s layout plan is approved, that the plot is “as per approved LOP” and that it is not on the list of plots mortgaged with CDA, before Building Control-II deals with the completion (regulations 9.3.11 and 9.3.12). The scheme’s own NOC or clearance is part of the file. How a scheme’s layout plan and NOC are approved is in our guide to CDA layout plan approval.

Rawalpindi is a different authority with a different file (see our guide to RDA’s building plan and completion process). RDA’s checklist for approval of a completion plan, updated on its downloads page in February 2026, asks for the owner’s CNIC, ownership and possession papers, the approved plan, a completion plan in four ammonia prints and two cloth prints stamped by an RDA-registered architect and structural engineer, forms BR-08 and BR-15 (BR-09 for multi-storey buildings) and a completion certificate from an RDA-registered structural engineer. Its processing fee is Rs 5,000 for a residential completion plan.

A pre-filing check

Most completion problems were made at the plinth, so the best time to prepare is before Form-D, not after the last coat of paint. A practical sequence:

  1. At setting out, check the building position and setbacks from the plot corners, and fix a benchmark tied to the front road level.
  2. At plinth, measure the plinth level and building lines before the architect signs Form-D.
  3. Before every slab, make sure the Form-D goes in and the steel is checked before the concrete is ordered.
  4. During services, record sewer and storm lines, their connections and the gate grating as they are laid.
  5. Before filing, measure the finished house (setbacks, plinth, ramp, covered area) and compare it with the approved plan.
  6. Prepare the completion drawings from those measurements, list any differences, and settle them with the architect before the folders go in.

Our project supervision covers steps 1 to 4 as an independent check for the owner, with setting out and levels measured by instrument and a written report each visit. It does not replace the enlisted architect, who signs Form-D, Form B-2 and the completion drawings. Steps 5 and 6 are an as-built survey of the finished house. Send your approved plan and the stage the house has reached through our contact page.

Want RN Tech Associates to handle this for your site?

Send the location and what the work is for. We reply with the questions that decide scope and price.

Questions

Common questions

01Is a completion certificate mandatory in Islamabad?

Yes. Regulation 5.6.1 says it is mandatory to obtain a completion certificate, or permission to occupy, before any building in the Islamabad Capital Territory is occupied, and regulation 3.12.11 says no one may occupy a building until it is obtained.

02What are Form B-1 and Form B-2?

Form B-1 is the owner's notice of completion, saying the work was carried out according to the approved building plans and applying for permission to occupy. Form B-2 is the architect's and engineer's certificate that the building was completed under their supervision and in line with the approved plans. Both are on the forms page of CDA's website.

03How many sets of completion drawings does CDA need?

Six sets of completion drawings, which the regulations also call as-built drawings: one each for the office copy, the working copy, Estate Management, the architect, the owner and the Building Control Section's violation section (regulation 5.6.3).

04What is the fine for living in a house without a completion certificate?

In the 2023 text of regulation 2.8.1, Rs 5,000 per month for a residential building and Rs 10,000 per month for other buildings for the first year, doubled after that. The 2020 text had Rs 50,000 a year for residential buildings. The same regulation expects the certificate within three months after the initial construction period ends.

05What happens if my house is different from the approved plan?

CDA can require you to alter the work to match the approved plan, or to get amended plans approved (regulation 3.12.9). If the completion plan differs by more than 15%, or there are main structural changes, CDA charges double the scrutiny fee on top of the normal completion scrutiny fee (regulations 3.11.1 and 4.1.4).

06Can I sell or transfer a house without a completion certificate?

Under regulation 9.4.4, as amended in 2023, CDA's Building Control Section processes the NOC for a transfer only for buildings whose completion certificate has been issued or is in process, and where no violation exists at site.

→Request a survey

Tell us about the site

Location, rough size and what you need it for. We reply with the questions that decide the scope and the price.

Town, area or a Google Maps link.

Rough size, purpose, deadline. Drawings can follow by email or WhatsApp.