A plan that works on the ground
A layout plan has two audiences. The authority checks it against the rules: percentages, road widths, plot sizes, scale and format. The ground checks it too, less politely: roads that climb the wrong way, plots in a water channel, drains with no fall. We plan for both, which is why every layout starts from the topographic survey.
What the rules fix
The Punjab rules for development-authority areas set the scale of the scheme plan (1:1200 to 1:2400) and the location plan (1:4800), the way plots are numbered, corner chamfers (5 × 5 ft for plots up to one kanal, 10 × 10 ft above), and a standards table for land use. For a private housing scheme, at least 7% is open space and at least 2% graveyard; commercial use is capped at 5% (10% above 500 kanal); public buildings take 2% to 10%. The access road must be a carpeted or metalled road, or a revenue path at least 20 ft wide in the revenue record; where it is narrower than 50 ft, the scheme leaves a setback along it so the effective width reaches 50 ft (rule 7(2)(a)(i), as substituted by the amendment of 8 July 2026). Before that amendment the rule asked for 50 ft from 301 kanal, 40 ft up to 300 kanal and 25 ft for a land sub-division. Land outside the development authorities’ limits follows the 2022 local-government rules instead, whose table changes with the scheme’s size band; every row, with a worked area statement, is in our guide to planning standards for housing schemes in Punjab. The same guide now carries the full 2021 table for development authority areas, every size band and the major road widths up to 150 ft.
Islamabad’s CDA regulation adds a Layout Plan Concept Report covering population, water source, rainwater harvesting, traffic, solid waste, sewage and emergency planning. Without it, CDA does not process the scheme. What happens after the layout is cleared is in our guide to CDA layout plan and NOC approval.
In Punjab the layout plan is checked at its own stage, after the ownership check and the public notice, and the authority’s technical approval of it starts the six months the sponsor has to submit the services designs. Where that stage sits, rule by rule, is shown in our guide to private housing scheme approval in Punjab.
The area statement
The area statement is where most layouts are tested. Every land use is measured and expressed as a percentage of the scheme, and those numbers must sit inside the limits; what they leave is the saleable area a sponsor can sell. An apartment scheme has its own minimum area, open space and parking limits, set out in our guide to apartment housing schemes in Punjab. We build the layout and the area statement together, so a change to one updates the other. To test a draft area statement against the Punjab shares before it reaches us, try our free housing scheme land use checker, which marks each planned figure against its rule.
Drawn for submission
The final set includes the layout plan, the location plan, the area statement and plot schedule, the layout superimposed on the khasra plan and the survey (our guide to reading the khasra plan and aks shajra shows how the overlay is built), and AutoCAD and geo-referenced soft copies, the formats the 2022 Punjab rules ask for. How many copies each authority wants, and who signs them, is compared in our guide to the drawings and reports in an approval file. A plot schedule that gives each plot’s sides and its area in square feet also serves later, when the scheme’s plot records go into PLRA’s HSMS, as our guide to the Lahore Property Certificate and HSMS explains.
Before and after the layout
The layout is only as good as the ground it is drawn on, which is why it starts from a housing scheme survey to the authority’s specification, or a topographic survey for smaller sites. What that specification is in Punjab and in Islamabad is explained in our guide to which rules your scheme survey follows. Once drawn, it goes into the approval file. For land developed in phases, each layout follows the master plan. The whole sequence, from land check to demarcation, is set out under scheme development. The full range is under our town planning services. Share your survey or land details on our contact page to begin.