Short answer

After the layout plan is cleared, a Punjab housing scheme needs approved designs for water supply, sewerage and drainage, roads, electricity and street lights, plus landscape and solid waste plans, filed within six months. Engineers registered with the Pakistan Engineering Council prepare them and the agencies concerned approve them. Without them the scheme cannot be sanctioned, and the mortgaged plots come back only as the designed works are completed.

Service designs for a Punjab housing scheme: water, sewerage, drainage, roads and power under rules 11 to 20

Key points

  • Services designs are due within six months of the layout plan's technical approval or clearance, in both rule books.
  • 2021 rules: the authority forwards the designs to the agencies. 2022 rules: the sponsor brings agency-approved designs and the local government verifies them.
  • Water, road and electrical designs are prepared by engineers registered with the Pakistan Engineering Council.
  • Design fees: Rs 1,000 per kanal each for water and roads under the 2021 rules, Rs 500 under the 2022 rules; electricity at the agency's rate.
  • Mortgaged plots come back by weight: 25% each for water, roads and electricity, 10% gas, 10% horticulture, 5% solid waste.
  • Schemes and sub-divisions under 40 kanal are excused, but must still provide internal services and septic tanks.

What service designs are, and when they fall due

Service designs are the engineering designs for a housing scheme’s infrastructure: water supply, sewerage and drainage; the road network; electricity and street lights; plus a landscape plan and a solid waste management plan. They come after the layout plan is cleared and before the scheme can be sanctioned or approved, and in both Punjab rule books the clock is six months.

  • 2021 rules (land inside RDA, FDA, GDA, MDA and other development authority areas): the sponsor submits the services designs within six months of the technical approval of the layout plan, rule 24(2)(d). The letter of sanction is not issued until the designs for water supply, sewerage and drainage, roads, horticulture and electrification are approved by the agencies, rule 26(1)(g).
  • 2022 rules (local government land): the sponsor submits the designs with the Environment Protection Department’s NOC within six months of the layout plan’s technical clearance, rule 8(7). The local government verifies the approved designs before it approves the scheme, rule 21(1)(g).

Our housing scheme approval documents checklist lists these among the post-clearance papers. This page goes inside them: what each rule asks for, who prepares it, who clears it and what it costs.

Two routes: the authority forwards, or the sponsor brings approvals

The two rule books run the designs in opposite directions, and a sponsor who expects one route and meets the other loses months.

Step 2021 rules (development authority) 2022 rules (local government)
What is filed Four sets of designs, with the location plan, topographic survey plan, land use analysis and a soil test report from an approved laboratory (rule 11) Three sets of designs already approved by the agencies, in hard and soft form, with the EPD NOC (rule 11)
Who sends designs to the agencies The authority’s Director, within 7 days (rule 25(a)) The sponsor, before filing; the local government then forwards them for verification within 4 working days (rule 20)
Agency’s time Objections within 20 days; decision within 15 days of resubmission (rule 25(b) to (d)) Verification or refusal within 5 working days; resubmission if refused (rule 20)
End of the step Soft copies of the approved designs and of the approved infrastructure layout (rule 25(e)) Written notice within 5 working days of all verifications, then a soft and hard copy (rule 20)

The 2022 water and road rules each still say “four sets” of drawings, while the general rule says three; check the number with the local government before printing. The agencies differ by place: the water and sanitation agency or the public health engineering department for water and sewers, the road-owning department, the electricity distribution company (the 2022 approval letter says “WAPDA or other agency designated for it”), Sui Northern Gas Pipeline Company and the solid waste company or local government.

Design by design: what rules 12 to 19 ask for

Rules 12 to 19 carry the same numbers and nearly the same words in both rule books. Where the 2022 version adds something, the table says so.

Rule Design Prepared by, per the rule What it must cover
12 Water supply, sewerage and drainage Qualified public health and structural engineer, registered with the Pakistan Engineering Council Detailed designs and specifications (2022: with a water quality testing arrangement); tube wells with capacity, chamber design, bore hole, logs (strata chart) and machinery; overhead tanks with capacity, design and structural calculations; the design for ultimate disposal of sewage; septic or soakage wells where there is no disposal (2021 rules since July 2026: a wastewater treatment plant is added to the designs and the septic or soakage well item is deleted). Lines on both sides of every road, or connections laid under the road before it is paved
13 Road network (2022: and parking) Qualified civil or structural engineer, registered with the Pakistan Engineering Council Road, bridge and footpath designs (2022: underpasses and parking too); geometric design of roads and junctions; appurtenances and structures; road drainage; landscape design for the roads; street furniture; traffic control devices. Footpaths on both sides of major roads; a service road on both sides of any road with a right of way over 80 feet
14 Electricity and street lights Electrical engineer, registered with the Pakistan Engineering Council Electricity and street lighting designs using the most energy efficient lights the approving agency specifies, approved by the electricity agency (2021 rules since July 2026: an agency or company holding a NEPRA distribution licence for the area)
15 Landscape plan Not specified Parks and open spaces (2022: playgrounds and sports facilities), with tree planting on both sides of roads
16 Solid waste management plan Not specified Dust bins, storage places, collection and disposal (2022: plus an agreement with a waste management company, or the local government, with the payment method)
17 Gas Not a design Gas charges deposited with Sui Northern Gas within one year of sanction or approval, or its certificate that gas is not available nearby
18 Telephone Not a design Telephone facilities available within three years of the scheme’s development
19 Underground services Not a design Water, sewerage, gas and cable lines laid underground (2022: before roads are built); exemption where the topography does not allow it

Rule 10(1)(b) adds layout items that the designs must fit: sites for tube wells, overhead reservoirs and pumping or disposal stations where the water agency asks for them, and fire hydrants on the main water line in open spaces, the commercial centre and at intervals along roads.

Small schemes: the exemption and its limits

Small schemes are excused from the design approvals but not from the services. Under rule 20 of the 2021 rules the whole services chapter does not apply to a land sub-division under 40 kanal; under rule 10(1)(b) of the 2022 rules, a housing scheme under 40 kanal does not need design approval from the agencies. In both, the sponsor must provide internal infrastructure and services, and a septic tank in each plot where there is no public sewerage system. An apartment scheme under 40 kanal is a separate type in the 2022 rules, so do not assume the same relief; our guide to apartment housing schemes in Punjab sets out that question.

Fees for the designs

Design fees are charged per kanal of the total scheme area, not of the plots, so a measured boundary matters.

Design 2021 rules, rule 32(2) 2022 rules, fee rule 200 kanal, 2021 200 kanal, 2022
Water supply, sewerage and drainage Rs 1,000 per kanal Rs 500 per kanal Rs 200,000 Rs 100,000
Roads, bridges, footpaths (2022: underpasses) Rs 1,000 per kanal Rs 500 per kanal Rs 200,000 Rs 100,000
Electricity and street lighting Rate fixed by the agency Rate fixed by the agency (also gas, telephone, NOCs) Agency rate Agency rate
Revised design 50% (rule 33) 50% Half the above Half the above

These are authority fees only. The engineers’ design fees, the soil and water tests and the agencies’ own charges are separate and are not set by the rules. All the scheme’s fees together are worked through in housing scheme approval costs in Punjab.

What the designs need from the survey and the layout

Every design is drawn on two documents the rules put first: the layout plan and the topographic survey. Rule 11 of the 2021 rules lists the topographic survey plan among the papers filed with the designs, and the survey reaches 1,000 feet beyond the scheme, which is where the outfall, the nearest sewer or drain and the road connections usually are. Sewers and drains run by gravity, so the levels on that survey decide whether a sewer can reach its disposal point or needs a pumping station; our guide to the topographic survey your approval file needs covers what it must record.

The checklist that LDA, its water agency and its traffic agency use, hosted by FDA, shows what the agencies ask for before they will look at a scheme:

  • Water and sanitation agency: a water quality test of the scheme’s water source from a laboratory accredited to ISO 17025:2017 (it names PCRWR, PCSIR and Punjab University as examples); a plan of the ultimate sewage disposal route to a nearby drain, nallah or sewer; and clearances from the Railway, Highway, Revenue department or private owners for the force main’s path, and from whoever owns the receiving drain.
  • Traffic engineering agency: the cross section and full right of way of the roads abutting the scheme.
  • Environment: an Initial Environmental Examination report for the EPA NOC.

A further requirement was reported in October 2025: ProPakistani reported a Punjab directive to all development authorities not to approve new schemes without dedicated water treatment plants, with the Director General Environment saying a detailed treatment plant design is now mandatory for environmental clearance. Inside development authority areas it is now in the rules. The amendment of 8 July 2026 (Punjab Gazette, 15 July 2026) substituted rule 8, so the water and sanitation agency’s no objection certificate now covers the wastewater disposal mechanism (disposal point and route, treatment and rainwater harvesting), the area and location of the treatment plant, overhead tanks and the timeline for sewerage trunk charges; it added the treatment plant to the rule 10 planning table (it may sit outside the scheme boundary with the agency’s NOC) and to the rule 12 designs; and where the agency builds works as deposit work, the sponsor pays it within one year of sanction (rule 12(3)). On local government land it remains a directive we have not seen in the 2022 rules, so ask the local government whether your designs must include one and leave room for it on the layout.

The layout decides much of the design’s cost: roads wide enough for lines on both sides, service roads beside roads over 80 feet, footpaths on major roads, and sites for tube wells, tanks and disposal works placed where the levels suit them. We place those on the housing scheme layout plan from the start, so the engineers inherit a layout that their designs can serve.

From designs to works, and the mortgaged plots

Approved designs are what the scheme is built and inspected against. Works start only after the designs are approved; under the 2021 rules the sponsor also tells the water agency which factory makes the pipes, rule 49(c). Before starting, the sponsor informs the approving agency in writing and engages engineers registered with the Pakistan Engineering Council for quality control. The agency visits without notice, runs hydraulic tests on sewer and water lines, and tests before trenches are backfilled and roads paved (the moment to also record each line as it is laid), all at the sponsor’s cost (rule 50 in the 2021 rules; the monitoring rule in 2022).

The designs then decide when the mortgaged plots come back. Both rule books weight the release the same way:

Completed work Share of mortgaged plots released
Water supply, sewerage and drainage 25%
Roads 25%
Electricity and street lights 25%
Sui gas, or the certificate that it is not available 10%
Horticulture 10%
Solid waste management 5%

The 2022 mortgage deed (Form C) prints a slightly different split, 15% for gas and 10% for horticulture and solid waste together, so read the deed you sign against the rule. The 2021 rules add a schedule: up to 24% of the mortgaged plots on 25% completion, more at every 10% stage, and the last 4% only when the scheme’s maintenance is taken on or handed to the residents’ association (rule 52(3)); the bank guarantee is reduced in the same 24% steps (rule 53). How the mortgage limits what can be sold before that is shown in our guide to saleable area in a Punjab housing scheme.

A change to the road pattern after approval usually means revised designs as well as a revised layout; our guide to revising an approved layout plan covers that route. RN Tech Associates prepares the survey and the layout plan the designs are drawn on; the engineering designs themselves are prepared by the engineers the rules name. Send the location and area through our contact page, and we will tell you what the survey and layout need to carry for your agencies.

Want RN Tech Associates to handle this for your site?

Send the location and what the work is for. We reply with the questions that decide scope and price.

Questions

Common questions

01What are service designs in a housing scheme?

They are the engineering designs for the scheme's infrastructure: water supply, sewerage and drainage; roads, bridges and footpaths; electricity and street lights; plus a landscape plan and a solid waste management plan. Rules 11 to 20 of the Punjab housing scheme rules set what each must contain. The agencies responsible for each service approve them before the scheme is sanctioned.

02Who prepares the service designs for a housing scheme?

The rules name the engineers. Water supply, sewerage and drainage are designed by a qualified public health and structural engineer, roads by a qualified civil or structural engineer, and electricity by an electrical engineer, each registered with the Pakistan Engineering Council. The designs are built on the scheme's layout plan and topographic survey.

03When must service designs be submitted?

Within six months. Under the 2021 rules the sponsor submits them within six months of the technical approval of the layout plan. Under the 2022 rules the sponsor submits them with the Environment Protection Department's NOC within six months of the layout plan's technical clearance.

04What is the fee for services design approval in Punjab?

Under the 2021 rules, Rs 1,000 per kanal of the total scheme area for water supply, sewerage and drainage, and the same again for roads, bridges and footpaths. Under the 2022 rules each is Rs 500 per kanal. Electricity, gas, telephone and street lighting are charged at the rate the agency fixes, and a revised design costs half the fee.

05What happens if gas is not available near the scheme?

The sponsor provides a certificate from Sui Northern Gas Pipeline Company that gas is not available in the vicinity. Where gas is available, the sponsor deposits the charges within one year of sanction or approval. The same certificate is accepted when the gas share of the mortgaged plots is released.

06Do small housing schemes need service designs?

Not the full set. Under rule 20 of the 2021 rules the services chapter does not apply to a land sub-division under 40 kanal, and under the 2022 rules a housing scheme under 40 kanal is excused from design approval. In both cases the sponsor must provide internal infrastructure and services, and a septic tank in each plot where there is no public sewer.

Sources

  1. Punjab Development Authorities Private Housing Schemes Rules 2021, rules 10, 11 to 20, 24 to 26, 32, 33 and 49 to 53 (Punjab Gazette Extraordinary, 7 December 2021, pp. 2741 to 2765, FDA copy, read from the kept copy fetched 2 November 2026)
  2. Amendments to the Punjab Development Authorities Private Housing Schemes Rules 2021, Notification No. SO(H-II)2-5/2015 of 8 July 2026, Punjab Gazette (Extraordinary), 15 July 2026: rules 8, 10, 12 and 14 (copy in RDA downloads)
  3. Punjab Private Housing Schemes Rules 2022, Notification No. SOR(LG)8-5/2022: rules 8, 10, 11 to 20 and 21, the rules headed Fee and Release of mortgaged plots, Forms C and D (LG&CDD compendium, read 4 November 2026)
  4. Approval of private housing scheme by development authorities: LDA, WASA and TEPA documents checklist (copy hosted by FDA)
  5. ProPakistani: Punjab imposes strict new requirement for housing societies (news report on water treatment plants, 17 October 2025)

Rules and fees change. Check the current notification with the authority before you file; we do this on every job.

→Request a survey

Tell us about the site

Location, rough size and what you need it for. We reply with the questions that decide the scope and the price.

Town, area or a Google Maps link.

Rough size, purpose, deadline. Drawings can follow by email or WhatsApp.