Housing schemes

After approval: development periods, monitoring and release of mortgaged plots in Punjab

Published · 9 min read · RN Tech Associates · in Housing schemes

Short answer

In Punjab, mortgaged plots are released in proportion to the development works, on the completion report of the agency that approved each design: 25% of the mortgaged plots for water, sewerage and drainage, 25% for roads, 25% for electricity and street lights, 10% for gas, 10% for horticulture and 5% for solid waste. Inside development authority areas, 4% is held until the scheme's maintenance is taken over. Works must finish in 2, 3, 5 or 7 years by scheme size.

After approval: development periods, monitoring and release of mortgaged plots in Punjab

Key points

  • Approval comes with security: 20% of the plots (or saleable area) are mortgaged to the authority, and none of them may be sold until redeemed.
  • Both rule books release the mortgage by work type, on the approving agency's completion report, not when the whole scheme is finished.
  • Under the 2021 rules, up to 24% of the mortgaged plots come back at 25% completion, more with each 10% stage, and the last 4% after maintenance is arranged.
  • The 2022 mortgage deed (Form C) prints a different split from the 2022 release rule; settle which applies before you sign.
  • Since July 2026, schemes above 5,000 kanal in development authority areas get seven years; others get two, three or five.
  • Late works cost Rs 10,000 per kanal per year on the whole scheme for an extension of up to two years, and the authority can take over the works.

What the mortgage is, and why it matters

Approval of a private housing scheme in Punjab comes with security for the works, and the usual security is a mortgage of plots. Release of mortgaged plots is how the sponsor gets that security back, in stages, as roads, sewers, power and the rest are built and checked.

Under rule 24(1)(b)(iv) of the 2021 rules (development authority areas), the sponsor mortgages “twenty percent plots of the housing scheme” to the authority by a deed in Form C, C1 and C2; no mortgage is required for a land sub-division under 40 kanal. Rule 21(1)(e) of the 2022 rules (local governments) takes 20% of the saleable area, or 10% of the saleable plots in a farm housing scheme. In both, the mortgage is entered in the revenue record before approval, the mortgaged plots are marked on the layout plan (hatched red under the 2022 rules), and a public notice lists them by number (Form F under the 2021 rules, Form E under the 2022 rules).

The rule that matters most to buyers is short. The sponsor “shall not market or sell any mortgaged residential plot unless it has been redeemed” and released by a redemption deed (2021 rule 27; 2022 rule 22(3)). The 2022 approval letter, Form D, goes further: “Sale or commitment of mortgaged plots shall be an offence.” On our scheme development page this period, from approval to completed works, is the construction stage, and it is where most of a sponsor’s cash and time go.

How long you have to develop

The clock is set by the scheme’s area, and the July 2026 amendment changed it for large schemes in development authority areas.

Scheme area 2021 rules, rule 49 (development authority areas), as amended 8 July 2026 2022 rules, rule 34 (local governments)
Land sub-division, or up to 100 kanal 2 years 2 years
101 to 300 kanal (2022: over 100 up to 300) 3 years 3 years
300 to 5,000 kanal 5 years 5 years (above 300 kanal)
Above 5,000 kanal 7 years 5 years

Under the 2022 rules the period runs from the date of the approval letter. Works may start only after approval and, under the 2021 rules, only after the designs and specifications are approved by the agencies concerned (rule 49(b)), covered in our guide to service designs for a Punjab housing scheme; for water, sewerage and drainage works the sponsor must also tell the agency that approved those designs which factory is making the pipes (rule 49(c)). Gas charges are due to Sui Northern Gas Pipelines within one year of approval (rule 17 in each rule book), and under the 2022 rules water, sewerage, gas and cable lines go underground before roads are built (rule 19). The amendment does not say whether the seven-year period applies to schemes sanctioned before 8 July 2026, so ask the authority in writing if yours is one.

Monitoring while you build

The authority does not wait for the end to look. Rule 50 of the 2021 rules and rule 35 of the 2022 rules give the authority, or the agency that approved a design, the power to:

  1. visit the site without notice to check work against the approved designs and specifications;
  2. carry out hydraulic tests on sewer and water supply lines;
  3. choose the testing laboratory and the type and number of tests;
  4. complete testing and inspection before trenches are backfilled and roads are paved;
  5. tell the sponsor to put right any deviation, and act against violations.

The sponsor, for its part, must tell the approving agency in writing before starting works, and engage public health, structural and electrical engineers on the Pakistan Engineering Council’s register to control quality. Testing and inspection are at the sponsor’s cost. Point 4 is the one that costs money when missed: a sewer covered before it is inspected may have to be dug up again before the agency will sign anything.

How mortgaged plots are released

Mortgaged plots are released by work type, on reports from the agencies that approved the designs. Both rule books use the same weights, but the 2021 rules add a schedule and a holdback, and the 2022 deed form says something different from the 2022 rule.

Work completed 2021 rule 52(1) weight 2022 rule 37(1) release 2022 Form C (mortgage deed)
Water supply, sewerage and drainage 25% 25% 25%, on 100% completion
Roads 25% 25% 25% (roads, bridges and footpaths), on 100% completion
Electricity and street lights 25% 25% 25%, on 100% completion
Sui gas, or SNGPL certificate that gas is not available 10% 10% 15%, on 100% payment of gas charges
Horticulture 10% 10% 10%, horticulture and solid waste together
Solid waste management 5% 5% (included above)

The trigger is the agency’s report. Under 2021 rule 52(2) and 2022 rule 37(2), the authority releases plots after reports of the completed works from the agency that approved the design; for electricity and gas, the reports are of payment of charges (2021) or completion (2022).

Inside development authority areas, rule 52(3) adds a schedule. On completion of 25% of the development works, up to 24% of the mortgaged plots are released; further plots are released in proportion to every 10% stage; 4% stay attached to the scheme’s management and maintenance, and come back only when the sponsor submits a written request for maintenance or hands the scheme over. Rule 52(4) bars any release application if the mortgage or transfer deeds were never executed, and allows individual allottees to apply with the sponsor’s recommendation once they were.

A worked example shows the difference. Suppose 100 plots are mortgaged and the water, sewerage and drainage works are finished and reported:

  • 2022 rule 37: 25 plots can be released.
  • 2021 rule 52: the finished works carry 25% weight, so up to 24 plots come back; the rest follow at each 10% stage, and 4 plots wait for the maintenance arrangement.
  • 2022 Form C: 25 plots, but gas would later carry 15 plots and horticulture with solid waste 10, against 10, 10 and 5 in the rule.

When a deed and a rule disagree, the sponsor is the one exposed, because the deed is what was signed. Ask the local government in writing which split it will apply, before the mortgage deed is executed.

The bank guarantee route

Inside development authority areas, a sponsor can offer a performance bond instead of mortgaged plots. Rule 26(1)(f) of the 2021 rules describes a performance agreement with an unconditional bank guarantee “equivalent to the total cost of development works”, and its Explanation lets the sponsor fulfil either the mortgage (clause (e)) or the bond (clause (f)) to have the layout plan released. Rule 53 then reduces the guarantee as works are completed: 24% at 25% completion, a further 24% at 50%, 24% at 75%, 24% on completion of all works, and the last 4% after the maintenance request or handover.

For schemes approved earlier where no mortgage deed was ever executed, the July 2026 amendment added rule 26(2)(e): the authority may assess the work done from the department’s report and take a fresh mortgage deed “on a proportionate basis corresponding to the remaining development work”.

When works run late

Missing the development period costs money on the whole scheme, not just the unfinished part.

  • Extension (2021 rule 51; 2022 rule 36). For reasons beyond the sponsor’s control, the authority may extend the period by up to two years on a penalty of Rs 10,000 per kanal per year for the total area of the scheme; the 2021 rules add “or part of it”. A shorter extension costs proportionately. No further extension is allowed.
  • Daily fines (2021 rule 37). A development authority fines a sponsor who fails to develop within the period Rs 5,000 a day up to 300 kanal, Rs 10,000 up to 500, Rs 15,000 up to 1,000 and Rs 20,000 above. Since July 2026, the penalty cannot run for longer than the development period of that category.
  • Takeover (2021 rule 54; 2022 rule 30). The authority may take over the works and pay for them from the sale of the mortgaged plots or by cashing the bank guarantee, and recover any extra cost from the sponsor as arrears of land revenue.

A revised layout plan does not buy time either: both rule books say the sponsor gets no extra time for executing a revised scheme, except for added land. That rule, and what can and cannot move in a revision, is in our guide to revising an approved layout plan. For a 300 kanal scheme, one year of extension is Rs 3 million in penalty before a single extra metre of road is laid, which is why the development period deserves as much planning as the layout itself.

Handover and the last plots

The end of the works is not the end of the sponsor’s duties. Under the 2022 rules (rule 38), once works are complete and plots handed over, an association of plot owners or residents, incorporated under the Cooperative Societies Act 1925, manages and maintains the roads, sewers, parks, street lights and graveyard until a public body takes them over.

Inside development authority areas, rule 55 was replaced in July 2026. The sponsor stays responsible for management and maintenance after handover. Once half the scheme is lived in, the Director General may, with the consent of most resident owners, direct a management committee or company: seven members for three years, four nominated by the sponsor and three community members nominated by the Director General, working on a no profit, no loss basis, with fees kept in a separate bank account audited every year. The sponsor pays its share of maintenance for plots and buildings it still holds. Form H, the authority’s sanction checklist, also asks whether guide maps are installed in the scheme and whether an association or administrator for maintenance is functioning.

Records that speed up release

Release turns on the agency’s completion report, so the sponsor’s job is to make that report easy to write. No rule asks for an as-built survey for release; what helps is evidence the inspector can check quickly:

  • approved designs with every change recorded and approved;
  • test results for each sewer and water line, dated before backfilling, together with as-laid records of where each line was put;
  • a measured record of what was built: road widths and levels, manhole positions and invert levels, pipe runs and sizes;
  • the SNGPL payment receipt or its certificate that gas is not available.

During the works, our engineering survey team sets out roads and services from the approved drawings and checks levels as they are built. At the end, an as-built survey records what is actually in the ground, which the residents’ association will need long after the mortgage is gone. If you are still choosing land, start with checking land before you buy it; the stages before sanction are in private housing scheme approval in Punjab, and the fees in housing scheme approval costs.

Want RN Tech Associates to handle this for your site?

Send the location and what the work is for. We reply with the questions that decide scope and price.

Questions

Common questions

01What is a mortgaged plot in a housing society?

It is a plot the sponsor has mortgaged to the approving authority, by a registered deed, as security that the roads, sewers, power and other works will be built. Both Punjab rule books take 20% of the plots or saleable area (10% of saleable plots in a 2022-rules farm scheme), and the plots are listed in a public notice after approval. A mortgaged plot cannot be sold until the authority releases it by a redemption deed.

02When are mortgaged plots released?

In proportion to the works completed, on the completion report of the agency that approved each design. Both rule books weight the release as 25% for water, sewerage and drainage, 25% for roads, 25% for electricity and street lights, 10% for gas, 10% for horticulture and 5% for solid waste. In development authority areas the 2021 rules also release up to 24% at 25% completion and hold the last 4% until the scheme's maintenance is taken over.

03Can I buy a mortgaged plot in a housing society?

Not until it is redeemed. The rules forbid the sponsor to market or sell a mortgaged plot until the authority releases it, and the approval letter under the 2022 rules calls sale or commitment of mortgaged plots an offence. Check the plot number against the mortgaged list in the public notice and ask the authority whether it has been released.

04How long does a developer have to complete a housing scheme in Punjab?

Under the 2022 rules: two years up to 100 kanal, three years from 100 to 300 kanal and five years above 300 kanal. Inside development authority areas, the July 2026 amendment to rule 49 keeps two and three years for the smaller bands, sets five years from 300 to 5,000 kanal and seven years above 5,000 kanal.

05What happens if a housing scheme is not developed on time?

The authority may extend the period once, for up to two years, on a penalty of Rs 10,000 per kanal per year for the total scheme area; no further extension is allowed. Development authorities can also fine the sponsor daily under rule 37 and take over the works, paying for them from the sale of the mortgaged plots or the bank guarantee and recovering any shortfall from the sponsor as arrears of land revenue.

06Who maintains a housing scheme after development is complete?

Under the 2022 rules, an association of plot owners or residents, incorporated under the Cooperative Societies Act 1925, takes over management and maintenance. Inside development authority areas, the rule substituted in July 2026 keeps the sponsor responsible, and once half the scheme is lived in the Director General may direct a seven-member management committee for three years.

→Request a survey

Tell us about the site

Location, rough size and what you need it for. We reply with the questions that decide the scope and the price.

Town, area or a Google Maps link.

Rough size, purpose, deadline. Drawings can follow by email or WhatsApp.