Two rule books, two fee schedules
Before any figure means anything, find out which rule book governs your land. Inside the notified area of a development authority (RDA, FDA, GDA, MDA and others), the authority approves the scheme under the Punjab Development Authorities Private Housing Schemes Rules 2021. Outside those limits, the local government approves it under the Punjab Private Housing Schemes Rules 2022. Our guide to private housing scheme approval in Punjab explains how to tell which applies. Lahore (LDA) and Islamabad (CDA) have their own rules and are not covered by the numbers below.
All fees are charged per kanal. A kanal is 20 marla, and the area that counts is the total scheme area on the survey, not just the saleable plots. That is why a measured boundary matters before you budget.
The 2022 rules (local government): the fees
These come from the 2022 rules as published on the Local Government department’s compendium. The page’s extracted text does not print every rule number, so the numbers below follow the rules’ own cross-references (for example, the pre-requisites cite the conversion fee “under rule 28”). Check them against the gazette copy the authority holds.
| What you pay for | Amount | Basis |
|---|---|---|
| Land status request (before the application) | Rs 1,000 processing fee | Rule 5(3) |
| Approval of the housing scheme | Rs 1,000 per kanal of the total scheme area | Rule 25 |
| Services design: water supply, sewerage, drainage | Rs 500 per kanal | Rule 25 |
| Services design: roads, bridges, underpasses, footpaths | Rs 500 per kanal | Rule 25 |
| Electricity, gas, telephone, street lighting, NOCs | Set by the agency concerned | Rule 25 |
| Revised layout plan or services design | 50% of the rule 25 fee | Rule 26 |
| Transfer, renaming or amalgamation of a scheme | 25% of the prevailing approval fee | Rule 27 |
| Change of land use (conversion) | A fee under rule 28; no amount is printed on the page | Rule 28 |
| Extension of the development period | Rs 10,000 per kanal per year | Extension in time |
A worked example
For a 100 kanal scheme the arithmetic is: approval Rs 100,000, plus Rs 50,000 for the water, sewerage and drainage design, plus Rs 50,000 for the roads design. That is Rs 200,000 in authority fees, before conversion, notice and other agencies. This is our arithmetic from the published rates, not a quotation from an authority.
The 2021 rules (development authorities): the fees
The 2021 rules put the money earlier and make sanction the big item. Rule 32 sets these amounts:
| What you pay for | Amount |
|---|---|
| Preliminary planning permission, with the application | Rs 1,000 per kanal |
| Sanction of the scheme | Rs 15,000 per kanal |
| Water, sewerage and drainage design | Rs 1,000 per kanal |
| Roads, bridges and footpaths design | Rs 1,000 per kanal |
| Conversion of land use (rule 36) | 5% of the residential value, from the valuation table or the 12-month average sale price |
On the same 100 kanal, that is Rs 100,000 with the application, Rs 1,500,000 for sanction and Rs 100,000 for each design: Rs 1,800,000 in authority fees. The gap with the 2022 total is nine times, which is why quoting one rule book’s number for the other land is the commonest error in what is published. We read the 2021 rules from a kept copy of the gazette scan, so confirm the current schedule with the authority.
Penalties and late costs
Fees are the cost of doing it right. The rules also price doing it late or not at all, and what may happen before approval is in housing scheme penalties in Punjab.
- Building without approval (2021 rules, rule 37): a daily fine of Rs 5,000 for schemes up to 300 kanal, Rs 10,000 from 300 to 500, Rs 15,000 from 500 to 1,000 and Rs 20,000 above 1,000 kanal, for as long as the default continues. The same fine applies to a scheme not developed within its period. Since the amendment of 8 July 2026, the fine runs for no longer than the development period of the scheme’s category: two years up to 100 kanal, three years up to 300, five years from 300 to 5,000 and seven years above 5,000 kanal (rule 49(a)).
- Extension (2022 rules): up to two years on payment of Rs 10,000 per kanal per year, with shorter extensions charged for the period asked. For a 100 kanal scheme one year costs Rs 1,000,000, ten times the approval fee.
- Late possession (2022 rules): a sponsor who does not hand over on time owes the allottee 2% per month of the amount paid. If the allottee defaults and the agreement is cancelled, ten percent of the paid price is deducted.
- Cancelling an approved scheme (2022 rules): fifty percent of the value of the public building areas transferred to the local government, plus dues and fines.
- Marketing too early: the 2021 rules bar marketing until the approval fee, any penalty, the deeds and the revenue record entry are done, and an advertisement needs prior approval (rule 46). Under the 2022 rules marketing starts after the approval fee and any penalty are paid.
The costs the rules do not set a price on
Most of a sponsor’s cash goes to things with no authority fee schedule. They are still on the critical path of the file.
The survey
Both rule books ask for a topographic survey in three copies that extends 1,000 feet around the scheme (rule 6(2)(j) of the 2021 rules, rule 6(3) of the 2022 rules). The band is mostly other people’s land, so the survey is bigger than the scheme. See the topographic survey your approval file needs and drone survey vs total station vs GNSS for how to choose a method. The brief goes through our housing scheme survey service, and a good survey saves money later because a wrong boundary reaches every plot.
The layout plan and services designs
Both rule books require the location plan and layout plan to be signed by a town planner and the sponsor. The fee above pays for the authority to scrutinise the services designs; it does not pay for drawing them. Drawing them is the work of a housing scheme layout plan and the designs the rules require within six months of technical clearance (2022 rules, rule 8(7)). Revisions after scrutiny are the main reason cost and time grow, which is why the planning standards in housing scheme planning standards in Punjab are worth reading first.
Title and revenue documents
Ownership documents, the aks shajra and a khasra boundary that matches the satellite image must be in the file. A mismatch triggers a return, not a fee. See reading a khasra plan and aks shajra.
The mortgage and the bond
The mortgage is not a fee, but it ties up stock until the mortgaged plots are released as the works are completed. The 2022 rules require a mortgage deed over twenty percent of the saleable area (ten percent for farm housing). Under the 2021 rules the mortgage is over 20% of the plots, with none for schemes under 40 kanal, and the sponsor may instead give a performance bond backed by an unconditional bank guarantee equal to the cost of the development works (rule 26). A bank guarantee has a cost from your bank; the rules do not say how much.
Notice, inspection and the works themselves
The public notice is published at the sponsor’s cost and the amount is not stated in the rules. Under the 2022 rules testing and inspections by the approving agency during development are at the sponsor’s cost. And the development works (roads, water, sewerage, drainage, electricity) are the largest figure of all. If they are not completed, the 2022 rules let the authority recover the shortfall from the sponsor as arrears of land revenue.
What the 2026 amendments may have changed
For the 2021 rules we have read the amendment of 8 July 2026 (Punjab Gazette Extraordinary, 15 July 2026). It leaves the fees in rules 30 and 32 to 36 as they were; it caps the rule 37 fine at the development period, lengthens that period to seven years above 5,000 kanal, and moves applications to a centralised digital approval system. Amendments to the 2022 rules were reported in June 2026, but we have not seen them in the gazette, so we cannot say whether any 2022 fee changed. Treat the tables as the published rules as we could read them, and ask the authority’s housing scheme section for the current fee schedule in writing before you commit a budget.
How to budget a scheme
- Confirm the rule book from the land’s location: development authority limits or local government.
- Measure the total area from a surveyed boundary and convert to kanal.
- Multiply the schedule for that rule book and add conversion if the land use changes. Our free approval fee calculator does the multiplication with the rule on every line.
- Add what the rules leave open: survey, planning, notice, bank guarantee, inspections and the development works.
- Hold a reserve for time: an extension costs more than the approval itself.