Why record services while the trench is open
The only time a buried service can be measured directly and cheaply is while it lies in an open trench. After backfilling, finding it again means records, detection instruments and trial holes, and even a careful survey then gives a less certain result. Recording utilities as they are laid is the difference between a scheme that knows where its pipes are and one that has to search for them every time a road is cut.
The design drawing is not that record. Crews move a line around a tree root, a boulder or an older pipe; a valve shifts by two metres; a sewer is laid flatter or deeper than drawn; a house connection is added on site. The UK Health and Safety Executive’s guidance HSG47 puts it in one line: “The plans for new services should show how they have been laid, not how they were designed.”
For housing schemes in Punjab there is a further reason. The Punjab Private Housing Schemes Rules 2022 say, in rule 19(1), that “a sponsor shall ensure that utility services such as water supply, sewerage, sui gas and cable lines are laid underground” before the construction of roads, unless the local government grants an exemption where the topography does not allow it. Once the roads go down over them, those services are out of sight for good. The same rules release mortgaged plots on “reports regarding completion of works from the concerned agency under the approved design and specifications”. A surveyed as-laid record, compared with the approved services design, is the clearest evidence a sponsor can put in front of that agency; how the release itself works is in our guide to development periods and the release of mortgaged plots.
ASCE 75-22 in brief
ASCE/UESI/CI 75-22, the “Standard Guideline for Recording and Exchanging Utility Infrastructure Data”, was published by the American Society of Civil Engineers in July 2022 as the companion to ASCE 38-22. Where ASCE 38-22 deals with investigating utilities that already exist (the QL-D to QL-A quality levels explained in our quality levels guide), 75-22 deals with recording utilities as they are installed or moved.
ASCE’s announcement describes it as the result of “recurring discussion among various agencies going back 30 years” and as the basis for “a utility ‘As-Constructed’ or ‘As-Built’ standard”, meant “to ensure that new utilities added to a project, or relocated during a project, have accurate and useable records”. It was written as a project standard but, ASCE says, can also serve utility owners as a records development standard, and it addresses security concerns as well as the needs of engineers, utility owners and right of way owners.
The standard’s detailed requirements are in its paid text, which we do not quote. What follows is our own practical list for Pakistani schemes and projects, consistent with that aim.
What to record for each service
For every pipe, cable and duct laid, the record should let someone find it, identify it and understand it without digging.
| Item | What to record | Why |
|---|---|---|
| Position | Coordinates at every bend, change of level, fitting, valve, tee, reducer, chamber and end, and at regular intervals on straight runs | Lines rarely run perfectly straight between drawn points |
| Level | Level of the top of the pipe or duct on the site datum, and of the ground above at the same points | Depth can be recomputed when ground levels change |
| Gravity lines | Invert levels at each manhole or chamber, and pipe gradient | Sewers and drains work by fall |
| Type and owner | Water, sewer, drain, gas, power, telecom; which body will own it | Tells the next digger whom to call |
| Material and size | For example uPVC, HDPE, ductile iron, RCC; diameter; pressure class or voltage | Decides how it can be detected and how dangerous it is |
| Ducts | Number of ducts, which are occupied, draw ropes | Spare ducts look like services on radar |
| House connections | Tee position on the main and route to the plot boundary | The most often missed item, and the most often struck |
| Crossings | Where the line crosses another service, with both levels | Clearances can be checked later without digging |
| Tracing aids | Tracer wire route and test points, marker tape, RFID markers | Lets plastic lines be found again |
| Evidence | Date, crew or contractor, photographs with a scale and the chainage or point number | Settles later questions about what went in |
| Check | Who surveyed it, from which control, and who checked | Gives the record its standing |
Levels and coordinates, not depths and offsets
Most as-laid records fail in the same way: they say “1.2 m deep, 2.5 m from the kerb”. Both numbers depend on things that change. HSG47 lists the reasons old plans mislead: “the position of reference points (eg the kerb line) may have changed since the plans were drawn” and “re-grading of the surface may mean that the depths shown are now incorrect”.
| Recorded as | What goes wrong later | Record instead |
|---|---|---|
| Depth below ground | A road gets a new carpet or a plot is filled, and the pipe is now deeper than recorded; or a road is lowered and it is shallower | Top-of-pipe level on the site datum, plus ground level on the same date |
| Offset from kerb, wall or pole | Kerbs are rebuilt, walls demolished, poles moved | Coordinates in the project system |
| Chainage along a road | The road is realigned or renumbered | Coordinates, with chainage as an extra label |
| “As per design” | Nobody knows where it differs | Surveyed positions, with differences from design marked |
That only works if the scheme has one coordinate system and one height datum from the first survey to the last. A record in a local grid or on an assumed level that nobody wrote down is nearly as hard to use as no record. How to set both up is covered in our guides to coordinate systems in Pakistan and to site levels and bench marks.
Making plastic lines findable
Plastic gas and water pipes are, in HSG47’s words, “the non-metallic services most likely to be encountered”, and a plastic pipe gives an electromagnetic locator nothing to detect. HSG47 notes that locators do not find plastic pipes unless a metallic tracer wire has been laid with them, a transmitter is pushed along inside, or markers have been fixed to them. Radar may see them, depending on the ground; the trade-offs are in our comparison of GPR and electromagnetic locators.
Three habits keep a plastic line findable for its whole life:
- Lay a tracer wire and test it. HSG47 warns that a tracer wire “may not be continuous due to being damaged or not properly laid”, so test continuity before backfill and record the test points where a signal can be connected.
- Use markers where the line matters. RFID markers, which HSG47 describes as “programmed with information about the particular service and its depth”, can be placed at valves, tees and crossings and read later with a matching detector.
- Do not rely on tape or tiles alone. Warning tape and cover tiles help a digger, but HSG47 cautions that such protection “may have been disturbed and moved”. The coordinate record is the primary evidence.
The order of work on a housing scheme
On a scheme, the record has to be built into the construction sequence rather than added at the end:
- Approved services design in the same coordinates as the approved layout plan (what the Punjab rules ask for in those designs is in our guide to service designs for a housing scheme).
- Set out each line from the scheme’s control, so the as-laid survey can be compared with the design on one drawing; our engineering survey handles setting out and control.
- Lay and survey section by section. After bedding and before backfill, survey the pipe, its fittings and house connection tees; photograph them; test any tracer wire. For a long pipeline, chainage and sections along the run work as they do in a route survey.
- Survey chambers and manholes when built: cover levels and invert levels.
- Check crossings between services where two networks meet, with both levels recorded.
- Compile the as-laid drawings per network, with differences from the design marked.
- Then build the roads, as rule 19 requires, knowing the record is complete.
If part of a network was laid without a record, the gap can still be narrowed: an underground utility survey can detect and trace what is there and expose it at key points, and the result is labelled with the quality level actually reached, which will be lower than a direct record. It is always cheaper to record than to rediscover.
The hand-over package
A record nobody can find in ten years has the same value as none. Hand over, to the sponsor, the scheme management and each utility taking over a network:
- Drawings in AutoCAD DWG and PDF, one layer per service, in the project coordinate system, with the datum and coordinate system stated on every sheet.
- A point schedule: coordinates and levels of every surveyed point, with its description.
- Chamber and manhole schedules with cover and invert levels.
- Attribute tables for each line: type, owner, material, size, date laid.
- Tracer wire and marker records: routes, test points, marker positions.
- Photographs indexed to point numbers.
- A short report: control used, survey method, who checked, and any section that could not be surveyed before backfill.
HSG47 adds a duty that applies after hand-over too: if later work finds a service away from its recorded position, or changes its path or depth, tell the owner, “preferably before the excavation is backfilled”, so the record is corrected.
Our as-built survey records services before they are buried and delivers them on the same control as the design, with differences marked; where existing services must be found first, our underground utility survey does that and states how each line was found. To plan the records for a scheme or project, send the services design, the layout plan and the construction programme through our contact page.
