What a level is measured from
A benchmark level survey gives every point on a site a height measured from one starting point of known height, the benchmark. The height of a point above the chosen reference is its reduced level (RL). The reference itself is the datum. Three kinds of datum turn up on Pakistani sites:
- Mean sea level (MSL). Heights tied, through a chain of levelling, to the national reference. A level of 512.346 m on this datum means 512.346 m above mean sea level.
- A transferred datum. Heights carried from a bench mark whose level is known only from an earlier survey, a scheme’s own control, or a government drawing. It is as good as that bench mark and the record of where its value came from.
- An assumed datum. The surveyor gives a solid point on site a round value, usually 100.000 m, and measures everything from it. Perfectly sound for one site, as long as every drawing says “assumed”.
A bench mark set on site for the job is a temporary bench mark (TBM): a nail in a kerb, a mark on a culvert, a steel pin set in concrete. “Temporary” refers to its purpose, not its build. It must survive the whole job, which is why our engineering survey protects its bench marks for the life of the work. Set more than one: when one is knocked by a roller, the others prove which is wrong.
Mean sea level in Pakistan and who holds it
Pakistan’s national height reference is mean sea level by law. The Surveying and Mapping Act 2014 defines the vertical datum as “the surface to which all vertical measurements are referred and mean sea level is taken as vertical datum of a country” (section 2). Survey of Pakistan must “determine and update vertical datum” using sea level data along the coast (section 6(c)), “provide geodetic control, heights and geographical positions all over Pakistan” (section 6(e)), and see that its datum is adopted “in all national activities of surveying and mapping” (section 10(1)).
Getting an official height onto a private site is possible, but it is not routine. Survey of Pakistan’s “Site Coordinates Request” page offers “official site coordinates with ASML height verification” (ASML: above mean sea level) and lists rates of Rs. 30,000 per point for the coordinates of a Survey Bench Mark (SBM) and Rs. 10,000 per SBM for its height. The application (Form I) asks for the number of points, their purpose, CNIC copies, the allotment letter and site plan and the fee receipt, and coordinates are issued “subject to provision of transport by the indentor”.
The undertaking that goes with it (Form II) is the part most people miss. The applicant affirms that the coordinates and elevation “shall be treated as classified information/document”, kept “in lock and key”, handled only by a security cleared Pakistani national, and “used only for issue of NOC by the concerned agency”. In other words, official heights are issued for an approval that needs them, not as a general service for design and construction.
Two practical results follow. First, most private surveys in Pakistan are on an assumed or transferred datum, and an honest drawing says so instead of printing “MSL” on levels that never touched a national bench mark. Second, a project that does need true sea level heights (for a height clearance, a flood level comparison or a link to a government network) should plan for the official route early.
The national network is also being rebuilt. In its August 2021 report to the UN Committee of Experts on Global Geospatial Information Management, Survey of Pakistan described a new datum project that includes a long-term tide gauge, a levelling origin “at Gwadar Port or Karachi”, about 12,000 km of high-order levelling and a national geoid model, so that “the geospatial industry will be able to use GNSS for precision leveling”. We could not confirm on 4 November 2026 whether those parts have been completed.
GNSS heights are not heights above sea level
A GNSS receiver measures height above the WGS 84 ellipsoid, a smooth mathematical shape. Sea level follows the geoid, a lumpy surface shaped by gravity. In Pakistan the two are far apart. We looked up the geoid height at three cities on 4 November 2026 with GeographicLib’s GeoidEval tool:
| City | EGM2008 geoid height | EGM96 geoid height | Difference between models |
|---|---|---|---|
| Islamabad (33.70°N, 73.04°E) | -47.02 m | -46.14 m | 0.88 m |
| Lahore (31.55°N, 74.34°E) | -45.72 m | -44.50 m | 1.22 m |
| Karachi (24.86°N, 67.01°E) | -44.18 m | -43.49 m | 0.69 m |
A negative geoid height means the ellipsoid lies above the geoid there. So a GNSS ellipsoid height in Islamabad reads about 47 m lower than the height above sea level. Add the geoid height back (subtract the negative number) and you are close to sea level height.
Close, not exact. The two global models, EGM96 and EGM2008, differ by 0.7 m to 1.2 m at these cities, so two surveyors using different models will disagree by about a metre before either makes a mistake. Neither model is the same thing as Pakistan’s levelling network either, which is why Survey of Pakistan planned a national geoid. For a site, the safe practice is to occupy a known bench mark with the receiver, compare, and apply that local difference to the whole site, then state it on the drawing.
Why two surveys of one site disagree
When two level surveys of the same site differ, the cause is nearly always in the starting surface, not in the instrument. The size of the difference is the best clue.
| Size of difference | Usual cause | How to check |
|---|---|---|
| Hundreds of metres | One survey is on an assumed datum (100.000 or 1000.000), the other on MSL or a transferred datum | Read the datum note; an assumed datum gives round numbers near the first bench mark |
| About 44 to 47 m | GNSS ellipsoid heights mixed with heights above sea level | Compare one point measured both ways |
| 0.5 m to 1.5 m, the same everywhere | Different geoid models (EGM96 vs EGM2008), or two bench marks with values from different sources | The difference is constant across the site |
| A constant few centimetres to a metre | A bench mark disturbed, rebuilt or mis-identified | Re-level between the two bench marks |
| Growing with distance from the start | Level run not closed, or an instrument out of adjustment read with unequal sight lengths | Check the misclosure and the instrument’s last collimation (two-peg) test |
| Exactly the plinth or floor height | One set is relative to ±0.00 at finished floor, the other to the road or natural ground | Read the drawing’s level reference |
| A factor of about 3.28 | Feet on one drawing, metres on the other | CDA allows contours at “0.5 meters or 2 feet”, so both still appear |
A constant offset is good news: both surveys are probably sound, and one number converts between them. A difference that grows across the site means one of the surveys has an error and needs re-checking.
Architect, contractor and surveyor: one site datum
Most level disputes on building sites come from three zeros. The architect draws the finished ground floor as ±0.00. The contractor takes a level from the road or a manhole cover. The surveyor’s topographic survey is on an assumed 100.000 or on a GNSS height. Each set of numbers is internally right, and nobody has written down how they relate.
The cure is a short site datum statement, agreed before any level is set out and printed on every drawing:
- The bench marks: where each one is, a description, and its value.
- Where the values came from: assumed, transferred from a named survey, or from a Survey of Pakistan bench mark.
- The relationship to the architect’s zero, for example “±0.00 finished ground floor = RL 101.450”.
- The road crown or invert level the design depends on, measured from the same bench marks.
- Who checks the bench marks, and how often.
With that in place, a column base, a drain invert and a road level all come from one surface. Our engineering survey delivers it as the “level and bench-mark records” listed among its deliverables.
How a level run is checked
A level run is only trusted once it closes. The surveyor starts on a bench mark and either returns to it (a loop) or finishes on a second bench mark of known value. The difference between the measured and known value at the end is the misclosure, and it is compared with an allowance that grows with distance.
One widely used published set of limits is in the US Federal Geodetic Control Committee’s 1984 standards. For geodetic leveling:
| Order and class | Section misclosure (mm) | Loop misclosure (mm) |
|---|---|---|
| First order, class I | 3 √E | 4 √F |
| First order, class II | 4 √E | 5 √F |
| Second order, class I | 6 √E | 6 √F |
| Second order, class II | 8 √E | 8 √F |
| Third order | 12 √E | 12 √F |
E is the shortest one-way length of the section and F the length of the loop, both in kilometres. A 2 km loop of third-order levelling should therefore close within 12 × √2 ≈ 17 mm. Some study notes give the same formula with K as the number of instrument set-ups; in this standard it is a distance in kilometres.
Three habits keep a run inside its allowance. Backsight and foresight distances are kept roughly equal, so a small tilt in the instrument’s line of sight cancels out. The instrument’s line of sight is tested regularly with a two-peg test. And the misclosure is shown in the level book or report, not just “checked”. A survey report that does not state its misclosure has not shown that it closed.
Levels in an approval file
Approval rules ask for levels without naming a datum. CDA’s 2023 regulation for private schemes in Islamabad asks for a survey plan at not more than 1:1200 showing khasra numbers, “the spot level and physical features”, with contours at “0.5 meters or 2 feet interval” (clause 8-C(ii), as quoted in CDA’s letter of 6 March 2026; how to choose an interval is in our guide to contour surveys). The same clause asks for a flood study if the scheme falls within 500 m of a main water stream. A flood level from a hydrologist and a site level from a surveyor can only be compared if both are on the same datum, so that is one case where the datum statement decides the result. What else the approval survey must show is covered in our guide to the topographic survey a housing scheme file needs.
Levels also travel with coordinates. A drawing that states its horizontal system but not its height datum is only half described; the horizontal side, including the zone and the older Kalianpur 1962 grids, is in our guide to UTM zones and coordinate systems in Pakistan.
What to ask for before levels are set
Whether you are a client, an architect or a contractor, five requests prevent almost every level dispute:
- A datum note on every drawing: MSL from a named bench mark, transferred from a named survey, or assumed.
- At least two bench marks on or near the site, described and photographed, with their values and source.
- The misclosure of each level run, with the allowance it was checked against.
- For GNSS heights, the geoid model used and the check against a levelled bench mark.
- The architect’s ±0.00 written as an RL on the same datum.
For a tender, the same points belong in the survey scope; how to word them is in our guide to specifying an engineering survey for a tender. On a long road, canal or pipeline the same rule needs bench marks spaced all along the strip, as the guide to route surveys explains.
Our topographic survey reports state the datum, instruments and method, as our standards page sets out, and our engineering survey keeps the bench marks and level records for the life of the job. If you have two sets of levels that do not agree, send both drawings and the site location through our contact page. We will tell you which surface each was measured from and how to bring them onto one datum.