Why digging blind is expensive in Pakistan
Every trench, foundation, borehole and road widening in a Pakistani town cuts through ground that already holds gas, power, water, sewer and telecom lines. Before you dig, the job is to find them, and in Pakistan that job falls on whoever is digging.
The cost of not doing it is on record. A study of gas losses carried out for the Oil and Gas Regulatory Authority (OGRA) in 2017 found that “third party contractors working nearby natural gas network often cause damages” to the Sui companies’ pipelines, from scraped coating that leaks later to outright ruptures. The two companies reported these third-party damages:
| Year | SSGC | SNGPL |
|---|---|---|
| 2012 | 1,892 | 877 |
| 2013 | 3,013 | 100 |
| 2014 | 3,153 | 13 |
| 2015 | 3,076 | 19 |
| 2016 | 2,697 | 3,342 |
The SNGPL figures jump in 2016, which may reflect better reporting rather than more damage; the study does not say. Either way, thousands of strikes a year were being reported on gas networks alone, before counting power cables, water mains, sewers and fibre. A strike can hurt people, stops a site, and leaves a contractor facing the owner’s repair bill.
No one-call service: who you have to ask
Many countries run a single “call before you dig” service that passes your enquiry to every utility owner. We know of none in Pakistan, national or provincial. So you ask each owner yourself, in writing, with a site plan:
- Gas: SNGPL in Punjab and Khyber Pakhtunkhwa, SSGC in Sindh and Balochistan.
- Electricity: the distribution company for the area (IESCO in Rawalpindi and Islamabad), and NTDC near transmission routes.
- Water and sewerage: WASA in Rawalpindi and Lahore; CDA in Islamabad’s sectors; the municipal body elsewhere.
- Telecom: PTCL and each fibre operator with a route nearby.
- Others: the cantonment board in cantonment areas, and the management of a private scheme for services inside it.
Expect records of mixed quality, and some owners who send nothing. The limits of those records and how they are graded are covered in our guide to utility survey quality levels. The rule from HSE’s guidance HSG47 holds everywhere: “Plans alone are not sufficient to identify and locate services before starting work”, and “the absence of records should never be taken as proof that the area in question is free of underground services”.
Before you dig: the order of work
The safe sequence is the same for a house foundation, a drain or a road. HSG47 sets it out for the UK; it works in Pakistan with one extra step, because nobody collects the records for you.
- Define the work area on a plan: every trench, pit, pile, borehole and the area machines will track over.
- Ask every owner for records and conditions (above). Note who replied and who did not.
- Walk the site and survey what shows on the surface: valve boxes, manhole and chamber covers, meter boxes, marker posts, poles with cables going down, patches of newer road surface along a straight line.
- Detect across the work area with an electromagnetic locator, passive and with a signal generator, and with ground penetrating radar, because each finds what the other misses. What each instrument can and cannot see is set out in our comparison of GPR and electromagnetic locators.
- Mark the lines on the ground with paint or chalk on hard surfaces and wooden pegs on soft ground. HSG47 warns against steel pins or long pegs, which can damage shallow services.
- Dig trial holes by hand where the work comes close to, or crosses, a located service, to confirm its position, depth and what it is.
- Brief the crew with a drawing of what was found, and supervise excavation near services.
- Record what was exposed, with coordinates and levels, so the next team does not start from nothing.
Steps 3 to 6 are an underground utility survey. The Survey Association’s client guide says a well designed detection survey should find around 80% to 95% of utilities and that 100% may not be possible, which is why step 6 is not optional. The survey should be drawn in the same coordinates as the design, so the services and the new work can be checked against each other on one drawing (see our guide to UTM zones and coordinate systems in Pakistan).
Gas mains: plastic, shallower than you think, and service pipes nobody drew
Gas deserves its own section because it is where the worst assumptions are made.
Much of the network is plastic. The 2017 OGRA study records that SNGPL uses polyethylene pipe to the ASTM D2513 standard in its distribution network, medium density up to 4 inches and high density for 6 inches, and that the Sui companies “introduced PE pipelines in the distribution network to reduce its exposure to corrosion”. A plastic pipe gives an electromagnetic locator nothing to detect, and HSG47 notes that few plastic gas and water pipes have been laid with tracer wires. A sweep with a cable locator that “finds nothing” says nothing about a plastic gas main.
Cover depths are a guide, not a dig depth. The same study reports that SNGPL’s distribution mains have between 3.5 and 5 feet of cover, and gives SSGC’s network in bands from 3.5 feet to more than 5 feet. HSG47’s advice applies: “never assume depths”. Roads are lowered and raised, kerbs move, pipes rise at crossings and culverts, and house service pipes run shallower than mains.
Service pipes are rarely on any plan. HSG47 says plans “do not normally show the position of gas service connections and their existence should be assumed”, and suggests estimating the line from the meter position or where the pipe enters the building. In a Pakistani street, assume a service pipe runs from every gas meter to the main, and find it before a machine does.
HSG47 also makes a point about tools that is worth remembering: damaging a gas pipe with an excavator is much more dangerous than damaging it with a hand tool, while for electricity cables the opposite is true.
Digging near a located service
Once a service is located, the digging method changes. These are HSG47’s practical margins:
| Situation | HSG47 guidance |
|---|---|
| Breaking a hard surface with power tools | Where practicable, keep power tools 500 mm or more from the indicated line, then locate the service by careful hand digging beneath the surface |
| Using power tools above a service | Only if it has been exposed and is at least 300 mm below the bottom of the hard surface, or physical protection is in place |
| Approach to the service | Dig alongside rather than directly above it; final exposure by digging sideways, which gives better control |
| Trial holes | Hand tools or vacuum excavation, to confirm position before machines work close by |
| Machine excavation | Plan it; a second person watches the bucket from a safe position and warns the driver |
| Depth guide | Use the locator down the side of the excavation as the dig goes deeper |
| Backfilling | Support and protect exposed services; do not encase them in concrete |
Pakistani sites often add a hazard HSG47 mentions in passing: congested lanes where water, gas, power and telecom lines lie within a metre of each other. There the 500 mm margin may be impossible, and HSG47 allows it to be reduced only where the line has been positively identified and extra precautions are taken.
Boreholes, piling and trenchless crossings
Drilling meets the ground blind, so it needs the most care. A borehole for a soil report, a pile, a ground anchor or a tubewell each needs a clearance survey of the point and a margin around it, at a close search grid, and a hand-dug start where a service is detected nearby. On a housing scheme, the soil investigation that some authorities ask for (see our approval documents checklist) is often the first time a drill goes into the land.
Trenchless methods, such as horizontal directional drilling (HDD) under a road or canal, moling and auger boring, avoid opening the surface but not the risk. HSG47 says to locate existing services “in the same way as for open-cut excavation methods” and plan the bore path around them. As a general guide it gives a minimum clearance between adjacent services of 250 mm or one and a half times the diameter of the pipe being laid, whichever is greater, and about 300 mm for electricity cables, varied for ground conditions, bore size and how accurately the drilling can be steered. Moles can deflect off course and should be tracked. For a crossing, trial holes at the existing services on both sides of the road give measured depths to plan the bore profile against, and the bore’s own centreline and long section are set up as in a route survey for a road, canal or pipeline.
If you hit something
Have the plan agreed before work starts, with each owner’s emergency contact taken from the owner’s own website or office, not from a directory.
- Stop work and keep people well clear, especially for gas, power and high-pressure water.
- If a machine strikes a cable, HSG47 says the driver should stay in the cab; climbing down can be fatal. Nobody approaches the cable or the machine until the owner has made it safe.
- Gas can travel: HSG47 warns that gas from a damaged pipe may run along a service pipe into a building. Warn the occupants nearby.
- Tell the owner immediately, even for minor damage: scraped coating or a dented pipe becomes a leak later.
- Do not backfill a damaged service, and do not repair it yourself.
Record what you found
Every service exposed on a job is information the next digger will need. Before backfilling, record each one: type, owner if known, material, size, depth to top, and position, surveyed in coordinates rather than measured from a wall that may be demolished. For services you lay yourself, the same record made as they go in becomes the as-laid drawing.
Our underground utility survey gathers the records, surveys the surface features, detects with locators and radar, arranges trial holes with the client and the utility’s permission, and delivers a plan that states how each line was found and where nothing could be seen. Our engineering survey then sets out the new work against it. To plan a dig, send the site location, the extent of the work and any records you hold through our contact page.