Housing schemes

Housing scheme approval documents: the checklist by authority (LDA, RDA, CDA, local government)

Updated · 16 min read · RN Tech Associates · in Housing schemes

Short answer

There is no single list. Inside a Punjab development authority's area (RDA, FDA, GDA and others), the application needs the eleven items in rule 6(2) of the Punjab Development Authorities Private Housing Schemes Rules 2021. Outside those limits, rule 6(3) of the Punjab Private Housing Schemes Rules 2022 lists fifteen. LDA uses a checklist split by department, and CDA asks for land documents under clause 8-B and ten planning documents under clause 8-C of its 2023 regulation. More documents fall due after the layout plan is cleared.

Housing scheme approval documents: the checklist by authority (LDA, RDA, CDA, local government)

Key points

  • The list depends on where the land is: the 2021 rules for development authority areas, the 2022 rules for local government land, LDA's own checklist, CDA's 2023 regulation in Islamabad.
  • Both Punjab rule books refuse a power of attorney as proof of ownership; the 2022 rules also refuse an agreement.
  • The 2022 rules ask for more at the start: revenue papers countersigned by the Collector, an Irrigation Department NOC, a PEC-registered soil consultant for 100 kanal and above, and five copies of the layout with an AutoCAD file.
  • The file grows after technical approval: transfer deed, mortgage deed, services designs, environment NOC and fees, all before the sanction letter.
  • Checklists still online follow the repealed 2010 rules; check the date and rule book of any list you are handed.

Which list applies to your land

The documents for housing scheme approval are set by the rule book that governs the land, so the first job is to find out which one that is. Four lists are in use around Rawalpindi, Islamabad and Lahore, and they do not match.

Where the land is Instrument Where the document list is
Punjab, inside a development authority’s notified area (RDA, FDA, GDA, MDA and others) Punjab Development Authorities Private Housing Schemes Rules 2021 Rule 6(2), items (a) to (k); later documents in rules 24 and 26; Form-H checklist
Punjab, outside development authority limits Punjab Private Housing Schemes Rules 2022 Rule 6(3), items (a) to (o) and “any other information”; later documents in rule 21
Lahore, LDA’s area LDA’s own procedure (whether the 2021 rules now apply in LDA’s area is unconfirmed) A checklist split by LDA department and agency, and by stage
Islamabad Capital Territory, zones 2, 4 and 5 CDA regulation of 2023 (gazette notified 7 July 2023) Clause 8-B (land documents) and clause 8-C (planning documents)

Rule 4 of the 2021 rules says no local government shall approve a scheme inside a development authority’s notified area, so a file built for the wrong office is not a file at all. How to tell which office your land falls under, and the stages each rule book runs through, are in our guide to private housing scheme approval in Punjab. From an office in Rawalpindi we see all four lists in use: RDA land, local government land beyond RDA’s limits and CDA land in Islamabad can lie a few kilometres apart.

Before the application: the land status request

The first paper you file is a short request for the land’s status in the master plan, and it needs only three things. Under rule 5 of both Punjab rule books you send:

  • a valid CNIC (computerised national identity card);
  • a document showing the khasra numbers (the numbered revenue fields) marked on a satellite image;
  • proof of the Rs 1,000 processing fee.

The 2022 rules add one condition: the satellite image must be certified by the Assistant Commissioner. The reply is valid for six months at most, and under the 2021 rules it is not a commitment that the land use will not change. Under the 2022 rules the local government replies within two weeks. Use those six months to assemble the full file. For land in RDA’s area, what Rawalpindi’s land use maps cover explains why the written reply, not a map, is what counts.

The application file side by side

The main application is where the lists differ most. The table puts each document against the rule or clause that asks for it. A dash means the document is not on that list; it does not mean the authority will never ask for it.

Document Punjab DA Rules 2021, rule 6(2) Punjab LG Rules 2022, rule 6(3) LDA checklist CDA 2023, clauses 8-B and 8-C
Application with postal and email address Rule 6(2) opening words (b) complete mailing address Signed by all owners, with contact numbers Not in the clauses quoted
Sponsor’s CNIC (a) certified copy (a) certified copy Copies for all owners Not in the clauses quoted
Proof of residence (b) last-paid utility bill (c) utility bill or tenancy agreement Utility bill Not in the clauses quoted
Company, firm or society registration (c) company or cooperative society, if applicable; a cooperative also needs the Cooperatives Department NOC (amended 2026) (d) if applicable If applicable Not in the clauses quoted
Title documents (e) registered sale deed, mutation, fard; no power of attorney (g) the same; no power of attorney or agreement Fard, mutations and registered deeds (revenue list) 8-B(i) fresh fard attested by Tehsildar ICT
Khasra list and plan on a satellite image, site on the master plan (f) signed by town planner and sponsor (h) the same Khasra list with areas; plan on satellite image; site on master plan 8-C(i) site plan at 1:10,000 with the zone’s land use plan
Khasra plan or aks shajra (g) three copies, certified by the revenue officer (i) three copies, certified and countersigned by the Collector of the Tehsil Copy of aks shajra 8-B(ii) certified by the Tehsildar, with an ownership and possession statement
Non-encumbrance certificate (i) three copies, from the competent authority (k) three copies, Revenue Officer, countersigned by the Collector; also confirms no acquisition notice Not listed 8-B(iii) from Tehsildar, Registrar, Sub-registrar or Naib Tehsildar
Khasra girdawari - - Copy (revenue list) 8-B(iv) for shamlat (common) land
Soil investigation report (h) by a consultant engaged by the sponsor (j) by a PEC-registered consultant, 100 kanal and above Boreholes drilled in the presence of LDA staff Not in 8-C; a water resistivity survey report is 8-C(viii)
Flooding Checked under rule 7(2); no NOC in the list (l) Irrigation Department NOC Not listed 8-C(ix) flood study within 500 m of a main stream
Location plan (d) three copies, signed by town planner and sponsor (e) three copies, signed, with total area Signed by owners and town planner 8-C(i) site plan
Topographic survey (j) three copies, 1,000 ft around the scheme (m) three copies, 1,000 ft around the scheme Three copies 8-C(ii) three copies of the survey plan
Layout plan on the khasra plan (k) three copies, signed by town planner and sponsor (f), and (n) five hard copies plus an AutoCAD file Three copies plus AutoCAD, signed by all owners and the town planner 8-C(iii), (iv), (vi): three copies, signed by a PCATP-registered planner enlisted with CDA, and laid on the topography plan
Geo-referenced soft copy Later, once the layout is cleared (rule 24(1)(b)(ii)) (o) with the application At the final transparency stage Not in 8-C
Concept report and planner’s certificate - - - 8-C(vii) concept report; 8-C(x) certificate on Rs 100 stamp paper
Other (f) “any other information, if required” “Any other information, if required” Army or DHA and NHA clearance if applicable; consent of the sponsor of an adjoining approved scheme whose access or services you use -

Count them and the difference is plain: eleven items under the 2021 rules, fifteen plus “any other information” under the 2022 rules. The CDA column comes from a CDA letter of 6 March 2026 that quotes clauses 8-B and 8-C for one scheme’s file; we could not find the full regulation text online, so treat that column as the minimum. The stages that follow the first approval are in our guide to the CDA layout plan and NOC process.

Ownership and revenue papers

Most returned files fail on ownership, and both Punjab rule books are strict about it. These are the revenue terms you will meet:

  • Fard (fard malkiat, or Register Haqdaran-e-Zameen in Islamabad): the record of rights, showing who owns which share of a khasra.
  • Mutation (intiqal): the entry that records a transfer in the revenue record.
  • Aks shajra: a copy of the revenue map of the village fields, on which the scheme boundary is drawn. Our guide to reading the khasra plan and aks shajra shows how it becomes the boundary.
  • Khasra girdawari: the record of the crop inspection of each field, which CDA asks for where shamlat (village common) land is involved.
  • Non-encumbrance certificate (NEC): confirmation that the land carries no charge, such as a mortgage or attachment.

Three rules shape the ownership papers. First, a power of attorney is not proof of title (2021 rule 6(2)(e)); the 2022 rules also refuse an agreement. Second, under rule 6(4) of the 2021 rules, the sponsor must show 100% ownership before the layout plan is technically approved. Third, with more than five owners, the application comes from a company, firm or cooperative society under rule 6(2) of the 2022 rules; under rule 6(1) of the 2021 rules, as amended on 8 July 2026, only a company or cooperative society, with no more than five applicants in a joint venture and no joint venture with a cooperative (rule 6(1d)). Who certifies each paper also differs: a revenue officer in the 2021 rules, a revenue officer countersigned by the Collector of the Tehsil in the 2022 rules, the Tehsildar of ICT for CDA. A copy certified by the wrong officer is a common reason for a file to come back.

Drawings and technical reports

The drawings carry the scheme, and each list fixes copies, signatures and formats. In both Punjab rule books the location plan and the layout plan are signed by a town planner and the sponsor; rule 2(1)(dd) of the 2021 rules defines a town planner as one registered with the Pakistan Council of Architects and Town Planners (PCATP). Rule 9 sets the scales: the scheme plan at 1:1200 to 1:2400 and the location plan at 1:4800. The layout itself is drawn on our housing scheme layout plan service.

The topographic survey is three copies and reaches 1,000 feet beyond the scheme in Punjab; a land sub-division under the 2021 rules is surveyed to its own boundary. What the survey sheets must show for each authority is set out in our guide to the topographic survey your approval file needs.

The soil report is where the lists split. The 2021 rules ask only for a report by a consultant the sponsor engages. The 2022 rules want a PEC-registered consultant for 100 kanal and above. LDA’s checklist asks for a PEC-registered geotechnical firm with five years’ experience, tests to ASTM and AASHTO methods, and states “for the scheme area up to 1000 K, 20 boreholes and 20 test pits” (one of each per 50 kanal), drilled with LDA’s engineering staff present. Where a borehole or test pit falls near a road or an existing settlement, a short clearance check for buried gas, water and power lines first is worth the time; our guide to utility survey quality levels shows how to scope one.

CDA’s clause 8-C is the longest technical list. Beyond the site plan, survey plan and layout plan, it asks for the aks shajra on the contour plan, the layout on the topography plan, a layout plan concept report (“Without these documents no scheme shall be proceeded for its approval”), a water resistivity survey report showing enough underground water, a flood study near a main stream vetted by a PEC-registered hydrologist enlisted with CDA, and the town planner’s certificate on Rs 100 stamp paper. The heading of clause 8-C says these documents are signed and stamped by a PCATP-registered town planner enlisted with CDA and by the sponsors.

Agency NOCs and clearances

Other agencies check the file too, and the lists differ on whether you bring their papers or the authority asks for them. Under rule 8 of the 2021 rules, as substituted on 8 July 2026, the Water and Sanitation Agency issues a no objection certificate (NOC) on the waste water disposal route and treatment, the site of any waste water treatment plant, the overhead reservoirs and the timeline for sewerage trunk charges; the old seven and ten day limits are gone. Under the 2022 rules the sponsor brings the Irrigation Department’s NOC, and the local government sends it for verification.

LDA’s checklist makes most of this the sponsor’s work. Its WASA list asks for a water quality test of the water source by a laboratory accredited to ISO 17025:2017 (PCRWR, PCSIR and Punjab University are named), a plan of the ultimate sewage disposal to a nearby drain, nallah or sewer, and clearances from whoever owns the path of the force main and the drain it discharges into. Its TEPA (traffic engineering) list asks for cross sections and the total right of way of the roads abutting the scheme, with a per-kanal fee paid by pay order; check the current rate with TEPA.

The environment NOC comes at different points. Under the 2021 rules as amended on 8 July 2026, where the Environmental Protection Agency already issued an NOC for the master plan or land use plan, the sponsor follows its mitigation measures (rule 26(3)); elsewhere the EPA’s NOC is due within six months of sanction, if applicable (rule 26(4)). The 2022 rules want the Environment Protection Department’s NOC with the services designs, within six months of technical clearance (rule 8(7)). LDA’s checklist asks for an Initial Environmental Examination (IEE) report for the EPA NOC at the services design stage.

Documents due after technical approval

The application is only the first part of the file. Once the layout plan is cleared, a second set of documents falls due before the letter of sanction or approval is issued. What the fees add up to, and what else a sponsor pays, is worked through in housing scheme approval costs in Punjab. The fee amounts for each rule book are compared in our approval guide’s table of fees, mortgage and deadlines.

Document Punjab DA Rules 2021 Punjab LG Rules 2022 LDA checklist
Transparency of the layout marking the mortgaged plots Rule 24(1)(b)(i); none under 40 kanal Mortgaged and transferred plots shown on the layout at application, 6(3)(n) Final transparency signed by all owners and the town planner
Geo-referenced soft copy of the layout Rule 24(1)(b)(ii) With the application, 6(3)(o) At the final transparency stage
Transfer deed for roads, open spaces and public land Form B, B1, B2 (rule 24(1)(b)(iii)), executed at the Sub-Registrar (rule 26(1)(d)) Form-B, B1, B2 (rule 21(1)(d)) Draft signed by all owners, then final on stamp paper
Mortgage deed Form C, C1, C2, 20% of plots; none under 40 kanal (rules 24(1)(b)(iv), 26(1)(e)) Form-C, C1, 20% of saleable area, 10% of saleable plots in a farm scheme (rule 21(1)(e)) Draft signed by all owners, then final on stamp paper
Performance bond Form D, D1, with an unconditional bank guarantee equal to the cost of the development works (rule 26(1)(f)); the mortgage deed or the bond releases the layout plan Not in rule 21(1) Not listed
Services designs Water supply, sewerage and drainage, roads, horticulture and electrification, approved by the agencies (rule 26(1)(g)); soft copies of the approved designs (rule 25(e)) Water, sewerage, drainage, road and electricity designs approved by the agencies, in hard and soft form, with landscape and solid waste plans; verified before approval (rule 21(1)(g)) Designs plus horticulture and solid waste plans, approved by the electricity company, WASA, LDA’s engineering wing, PHA and the waste management company
Fees Approval fee, land use conversion fee and public notice fee (rule 26(1)(a) to (c)) The same three (rule 21(1)(a) to (c)) Sanction fee, any penalty and the public notice fee
Revenue record Deeds and scheme entered in the revenue record (rule 26(2)) Deeds mutated and scheme entered (rule 21(2)) -
Letter issued Letter of sanction, Form E (rule 27) Letter of approval, Form-D (rule 22(1)) -

Under the 2022 rules the water, road and electricity designs are prepared by engineers registered with the Pakistan Engineering Council. Check the number of sets with the local government: the general rule on submission asks for three sets of approved designs in hard and soft form, while the water and road rules each say four sets. The sponsor also deposits gas charges within one year of approval, or produces a certificate from Sui Northern Gas Pipeline Company that gas is not available nearby.

Old checklists and online filing

Many checklists still in circulation follow the Punjab Private Housing Scheme and Land Sub-division Rules 2010, which the 2022 rules repealed. The checklist published by the Municipal Committee Daska, uploaded in March 2023, opens with “Submission of application for preliminary planning permission”, a stage the current local government rules no longer have, and lists that stage’s fees. Even the 2021 rules carry traces of the old system: their Form-H sanction checklist still asks whether “planning permission was issued to the sponsor”, and rule 32(1) still calls the Rs 1,000 per kanal application fee a “preliminary planning permission fee”. Read the rule text, not an old form, when you build the file. The same goes for the layout: the Daska checklist also prints the 2010 planning standards, such as a “fixed” 5% commercial area, which the 2022 rules replaced with a table banded by scheme size, set out in our guide to which planning standards bind a new scheme.

The way the file is filed has changed. The amendment of 8 July 2026 (Punjab Gazette Extraordinary, 15 July 2026) adds rule 6(1a): an application for a new scheme or a revision of an approved one is submitted by all landowners through the centralised digital approval system. A cooperative society now also needs a No Objection Certificate from the Cooperatives Department (rule 6(2)(c)); the rest of the rule 6(2) list is unchanged. On 23 July 2026 APP reported from Rawalpindi that amendments to the Punjab Development Authorities Private Housing Schemes Rules had been notified, and that all applications for approval, extension, renewal or other permission must go through the Housing Scheme Management System (HSMS), with applicants told to “upload complete and accurate documents”. On 1 September 2026 APP reported that RDA had launched the system and asked sponsors to file fresh applications and revisions there instead of on paper. No source we found gives the portal address. More on the 2026 changes is in our guide to what changed in 2026.

Before you file: a completeness check

Both Punjab rule books say an incomplete application is not entertained (rule 7(1) in each), so a short check before filing saves a round trip. These are the checks we run on a file before it goes in:

  1. The right list. The rule book matches the land’s location, and no item comes from a 2010-style checklist.
  2. Every owner accounted for. More than five owners means a company, firm or cooperative applies under the 2022 rules, and a company or cooperative under the amended 2021 rules, with its registration certificate; a 2021 application goes in from all landowners.
  3. Title, not authority. Registered deeds, mutations and fards for every khasra; no power of attorney or agreement.
  4. The right certifying officer. Revenue officer, Collector’s countersignature or Tehsildar, as the list requires.
  5. Copies counted. Three of most items; five hard copies of the layout under the 2022 rules; three of each CDA planning document.
  6. Signatures. Location and layout plans signed by the town planner and the sponsor (all owners, on LDA’s list).
  7. Survey to the right extent. 1,000 feet around the scheme in Punjab, with the khasra boundary laid on it.
  8. Soft copies ready. The layout as an AutoCAD file and geo-referenced on real coordinates, and every drawing as a PDF for online upload.
  9. Names checked. The scheme name is not already on record; “Phase-II” or “Extension” may be added only by the same sponsor (rule 6(3) of the 2021 rules); phasing a large scheme explains the three ways a next phase comes in.
  10. Later documents planned. Transfer and mortgage deeds, services designs and the environment NOC have owners and dates before the layout is cleared.

We prepare the survey, the layout plan and the approval file together, and follow up the technical comments; authority fees are paid by the sponsor. The housing scheme survey is drawn to the authority’s specification, a consultancy check of land status and title can come first, and our housing scheme approval page sets out what we deliver. The whole sequence, from land check to demarcation, is on our scheme development page. To start, send the location and khasra numbers through our contact page or on WhatsApp, and we will tell you which list applies and what your file is missing.

Want RN Tech Associates to handle this for your site?

Send the location and what the work is for. We reply with the questions that decide scope and price.

Questions

Common questions

01What documents are required for approval of a private housing scheme?

Under the Punjab 2021 rules: the sponsor's CNIC, a utility bill, any company or society registration, a location plan, title documents, the khasra list and plan on a satellite image, a certified aks shajra, a soil report, a non-encumbrance certificate, the topographic survey and the layout plan on the khasra plan (rule 6(2)). The 2022 local government rules add a mailing address, an Irrigation Department NOC and soft copies of the layout. LDA and CDA have their own lists.

02Is a power of attorney accepted as proof of ownership for a housing scheme?

No. Rule 6(2)(e) of the 2021 rules says no special or general power of attorney shall be accepted as proof of ownership, and the 2022 rules say the same of a power of attorney or an agreement. Title is shown by a registered sale deed, a mutation or the fard. Under rule 6(4) of the 2021 rules, the sponsor must show 100% ownership before the layout plan is technically approved.

03What is a non-encumbrance certificate for a housing scheme?

It is a certificate from the revenue side that the land is free of charges such as mortgages or attachments. The 2021 rules ask for three copies from the competent authority. The 2022 rules want it from the Revenue Officer, countersigned by the Collector of the Tehsil, and also certifying that the land is not notified for acquisition. In Islamabad, CDA accepts it from the Tehsildar, Registrar, Sub-registrar or Naib Tehsildar.

04Who prepares the soil investigation report?

Under the 2021 rules, a consultant engaged by the sponsor. The 2022 rules require a consultant registered with the Pakistan Engineering Council for schemes of 100 kanal and above. LDA's checklist asks for a PEC-registered geotechnical firm, with boreholes drilled in the presence of LDA's engineering staff.

05Do all landowners have to sign the application?

Where the land has more than five owners, the 2022 rules say the application comes from a company, firm or cooperative society, with its registration certificate (rule 6). Under the 2021 rules as amended on 8 July 2026, it is a company or cooperative society (a firm no longer qualifies), the application goes in from all landowners through the online system, a joint venture may have at most five applicants, and a cooperative also needs the Cooperatives Department's NOC (rule 6(1) to (1d) and 6(2)(c)). LDA's checklist asks for the application and the layout plan to be signed by all owners. The location and layout plans are also signed by the town planner.

06Can the documents be submitted online?

For development authority areas, yes. Rule 6(1a) of the 2021 rules, added on 8 July 2026, says an application for a new scheme or a revision is submitted by all landowners through the centralised digital approval system, and APP reported in September 2026 that RDA had launched it. Keep every document as a scan and every drawing as a PDF and a DWG. No source we found gives the portal address.

Sources

  1. Punjab Development Authorities Private Housing Schemes Rules 2021, Punjab Gazette (Extraordinary), 7 December 2021, rules 5, 6, 24, 26 and Form-H (copy hosted by FDA)
  2. Amendments to the Punjab Development Authorities Private Housing Schemes Rules 2021, Notification No. SO(H-II)2-5/2015 of 8 July 2026, rules 6, 8 and 26 (Punjab Gazette Extraordinary, 15 July 2026, RDA copy)
  3. Punjab Private Housing Schemes Rules 2022, Notification No. SOR(LG)8-5/2022, rules 5 to 8 and the services design chapter (LG&CDD compendium)
  4. Approval process under the Punjab Private Housing Schemes Rules 2022, documents 6(3)(a) to (o) and sanction requirements 21(1) (Municipal Committee Khanpur abstract)
  5. Approval of Private Housing Scheme, Development Authorities: checklist of documents by LDA department (undated copy hosted by FDA)
  6. CDA letter No. CDA/PLW/HS(700)/2003/Vol-III quoting clauses 8-B and 8-C of the 2023 ICT regulation (6 March 2026)
  7. Municipal Committee Daska: checklist for private housing scheme approval, still set out as preliminary planning permission (uploaded March 2023)
  8. APP: Commissioner directs strict implementation of amended housing scheme rules (news report, Rawalpindi, 23 July 2026)
  9. APP: RDA launches digital HSMS for private schemes (news report, 1 September 2026)

Rules and fees change. Check the current notification with the authority before you file; we do this on every job.

→Request a survey

Tell us about the site

Location, rough size and what you need it for. We reply with the questions that decide the scope and the price.

Town, area or a Google Maps link.

Rough size, purpose, deadline. Drawings can follow by email or WhatsApp.