Why check stage by stage
Most defects in a house are hidden within days of being built. Reinforcement disappears into concrete, foundations into backfill, pipes into floors and wiring behind plaster. Once covered, a mistake can only be found by breaking something, so a useful construction supervision checklist is organised by stage: each stage is checked against the approved drawings before the next one covers it.
Pakistan’s rules show the same thinking. In Islamabad, CDA’s building regulations (S.R.O. 1575(I)/2019, amended in August 2023 by S.R.O. 1074(I)/2023) make an inspection by the enlisted architect compulsory at nine stages, from marking out the dig to completion, and ask for the report at CDA’s One Window Operation within seven days of each inspection (regulation 3.12.8). Before every slab is poured, a Form-D goes in as well (regulation 5.5). The last of those inspections feeds the notice of completion, and our guide to the CDA completion certificate for a house shows what the inspector checks and the fines for occupying without one.
The national code is less demanding for houses. The Building Code of Pakistan, Seismic Provisions 2007, expects special inspectors for concrete work, but its exceptions cover concrete in dwellings (Group R, Division 3) where the building official finds no special hazard (section 6.1.5). Its “structural observation” rule also leaves out one- and two-storey houses (section 6.2). Outside CDA’s regulations, we have not found a rule that requires anyone to look at a house’s slab steel before the concrete arrives. If you want it checked, you arrange it.
The checklist at a glance
This table is the whole checklist in one place. The sections after it explain the checks that cause most of the trouble.
| Stage | What is about to be covered | Check before it is covered | Keep on record |
|---|---|---|---|
| 1. Setting out | The marks on the ground | Building outline from the plot corners; setbacks; column grid; right angles; a level benchmark | Setting-out sketch with measured offsets |
| 2. Excavation | The bottom of the trench | Width and depth per drawings; firm ground at the base; no loose fill; neighbours’ walls protected | Photos with a tape in shot; depths |
| 3. Foundations | Footing steel and concrete | Footing sizes; steel size and spacing; cover blocks; column starter bars in the right place | Steel check sheet; concrete batch or delivery notes |
| 4. Plinth and damp-proof course | The plinth and backfill | Plinth level against the front road; plinth band where designed; damp-proof course continuous; backfill compacted in layers | Level readings; photos |
| 5. Walls to lintel and roof | Brick courses | Bond and corners; openings away from corners; lintel and roof bands where designed; panel walls tied to frames | Wall check notes |
| 6. Every slab and beam | Steel inside formwork | Formwork level, tight and propped; steel per drawings; laps; cover; sleeves for services; slab level | Pre-pour sign-off; Form-D in Islamabad |
| 7. Concrete placing | The pour itself | Mix or delivery as specified; compaction; no added water on site; test samples where specified | Delivery notes; sample records |
| 8. Services | Pipes and conduits | Routes per drawings; falls on drains; pressure or leak tests; photos and measurements before burial | As-laid sketch with depths and offsets |
| 9. Finishes and completion | Everything | Defects list closed; tanks, grating, ramp and connections done; drawings of what was built | Completion drawings; final report |
Before digging: setting out and plot lines
The first check is the cheapest and the one most often skipped: is the house in the right place? Before the first trench is dug, check the building outline against the plot corners, the setbacks against the approved plan and the column grid against the structural drawings. A grid a few inches out, or a front setback eaten into, is found that day or lived with forever.
In Islamabad this is also a legal step. Regulation 3.12.4 says the architect certifies the plinth, the plot size and the building lines and issues a provisional certificate, after which CDA verifies the building lines within 15 days; regulation 5.5 sends a copy to CDA’s Land Survey Division, and says a portion built wrongly “may be demolished” if not corrected. We check setting out with a total station from the plot corners, using the methods of our engineering survey work, so the architect’s certificate rests on measurement.
Set a benchmark too: one fixed level, tied to the front road, from which every floor level is measured. Without it, levels drift a little at each stage.
Foundations and plinth
Check foundations twice: the open trench before steel goes in, and the steel before concrete goes in. The trench should be the width and depth the drawings show, on firm natural ground, with loose soil removed. Regulation 4.1.13 of CDA’s regulations makes the owner and the supervising engineer or architect responsible for protecting neighbouring buildings during excavation; the same care applies anywhere.
Then the plinth. CDA caps the plinth level of a house at 3 ft 6 in for terraced or attached houses and 5 ft for others, measured from the mean level of the front road (regulation 4.1.14). Above that, “that floor will be considered as ground floor”, which costs you a storey. CDA also limits digging: the front yard not more than 2 ft below natural level, side and rear yards not more than 6 ft (regulation 5.7). If the house has a basement, CDA sets its own limits on area, height, walls and exits, set out in our guide to CDA’s house basement rules, and its foundation and roof are separate inspection stages. Measure the plinth with an instrument against the benchmark before the damp-proof course goes on, because this is the level the inspector checks at completion.
Where the house has load-bearing brick walls on strip footings and the ground is soft or uneven, the Building Code of Pakistan describes a plinth band, a reinforced concrete band on top of the foundation wall that also serves as a damp-proof course (section 9.9.17.8.6).
Brick walls, openings and bands
For brick houses in Rawalpindi and Islamabad, the Building Code of Pakistan gives real numbers to check. Both cities are in seismic zone 2B in the code’s list of places, a house is a standard occupancy with an importance factor of 1.0 (Table 5.10), and that puts a brick house in building category C (Table 9.25). The rules below come from section 9.9.17 and its tables for category C.
| What to check | Category C rule in the code | Code reference |
|---|---|---|
| Bricks or blocks | Crushing strength not less than 3.5 MPa | 9.9.17.3 |
| Mortar | Cement-sand 1:6 or richer (or cement-lime-sand 1:2:9) | Table 9.26 |
| Corners and junctions | Build corners first, up to 600 mm, then the wall between; otherwise toothed joints in lifts of about 450 mm | 9.9.17.6 |
| Opening near a corner | At least 230 mm from the inside corner of an outside wall | Table 9.27 |
| Total openings in a wall | Not more than 0.55 of the wall length in a one-storey house, 0.46 in two storeys | Table 9.27 |
| Pier between openings | At least 450 mm wide | Table 9.27 |
| One opening above another | At least 600 mm apart vertically | Table 9.27 |
| Concrete bands | Full wall width, at least 75 mm deep, concrete not leaner than M15 (1:2:4), clear cover 20 mm | 9.9.17.8.5, Table 9.29 |
| Band steel, span up to 5 m | Two 8 mm deformed bars, held by 6 mm links at 150 mm | Table 9.29 |
| Arches over openings | Avoided, or tied with steel | 9.9.17.7.6 |
Which bands are needed depends on the number of storeys. For category C buildings of three and four storeys, Table 9.28 calls for the full set: mortar, lintel band, roof band, vertical steel at corners, junctions and door and window jambs, roof bracing and a plinth band where needed. For one and two storeys the list is shorter, but the code notes that a lintel band “will improve their stability during severe earthquake” even in partition walls. Ask your structural engineer which bands the drawings call for, then check each one is there before the next course goes on.
Where the house is a concrete frame with brick infill, the code says the panel walls must be bonded to the frame or connected through dowels (9.9.17.6.2). Check that ties or dowels are in place as each panel goes up.
Before each slab is poured
The pre-pour check is the most important hour of the job. Once the concrete truck or mixer starts, the steel is gone from view. Check, in this order:
- Formwork: level and at the right height against the benchmark, tight at the joints so slurry cannot leak, and propped firmly on solid ground or the slab below.
- Steel against the structural drawings: bar sizes, spacing, bends and hooks, extra bars at supports and openings, laps where the drawings allow them.
- Cover: cover blocks under and beside the steel, at the cover the drawings specify, so the bars do not sit on the shuttering.
- Services: sleeves and conduits for plumbing, electrics and drains placed now, not cut through the slab later.
- Openings and levels: stair openings, shafts and slab levels where the drawings change them.
The Building Code of Pakistan allows a special inspector who is not present throughout to inspect the reinforcement “prior to the closing of forms or the delivery of concrete” (section 6.1.5). That is the right moment for any supervisor. In Islamabad, regulation 5.5 adds a Form-D “at all slabs levels (before pouring the concrete)”, and regulation 3.12.8 lists the roof of each floor, the basement roof, the water tank and the stair tower among the compulsory inspection stages.
During the pour, watch for water added on site to make the concrete easier to place, poor compaction around congested steel, and cold joints in the wrong place. Afterwards, curing and the time before props are removed follow the specification; ask for both in writing before the pour.
Services before plaster and floors
Check every pipe and conduit before it is buried in a wall, a floor or the ground. Drains need the right fall and the right connection: CDA wants sewer and storm water lines laid separately and connected to their own mains (regulation 5.7). Water and drain lines should be tested before they are covered, as the specification or the plumber’s standard requires.
Before any excavation for those runs, find out what is already in the ground, as our guide to what to do before you dig explains. Then record them. A photograph with a tape in view, and two measurements from fixed points for each run and each bend, turn a buried line from a guess into a fact. That record is the start of the house’s as-built drawings, which our guide to as-built drawings and record drawings sets out item by item. Lines measured in an open trench are also the most certain kind of utility record, as our guide to utility survey quality levels explains.
Completion and hand-over
At completion, check the items the authority will check. In Islamabad, regulation 5.6.8 tells CDA’s inspector to verify the building against the completion drawings, looking at the Form-D certificates, the maximum plinth level, the ramp height, the drainage grating at the gate, the sewer and storm water connections, the setbacks, the covered area and, where they apply, emergency exits, fire-fighting arrangements and rainwater tanks. A ramp at the gate higher than 12 inches fails for a house (regulation 5.7). In Rawalpindi, RDA’s completion checklist asks for a completion plan and a completion certificate from an RDA-registered structural engineer.
Close every defect on the list, re-check it, and ask for drawings of what was actually built. Our as-built survey records the finished house in the same coordinates as the setting out, so the completion drawings show the building as it stands.
What each visit record should hold
A supervision record is only useful if someone else can read it later and know exactly what was checked. Each visit should produce a short written report, with photographs, holding:
- the date and the stage of work;
- the drawing numbers and revisions checked against;
- each item checked, and the result: accepted, or not;
- each defect, who must correct it, and by when;
- the re-check: the date it was looked at again and found corrected;
- measurements taken (levels, offsets, sizes), not just “OK”.
The rule is simple: no stage is covered until the defects found at that stage are closed. A report that says “work satisfactory” with no measurements is a diary, not a record.
Who checks what
Supervision works best when everyone knows which checks are theirs. The contractor checks his own work as it goes, to the standard the construction contract sets. The architect and structural engineer of record answer for the design and, in Islamabad, for the stage inspections and the completion certificate (CDA’s regulation 5.2.1 makes their supervision mandatory until the building is complete). The authority inspects when it chooses and at completion. An independent supervisor checks for the owner, measures rather than eyeballs, and writes it down.
Our project supervision is that independent check: inspection at agreed points with written reports and photographs, with setting out and levels checked by instrument. It does not replace the architect’s certificates that CDA or RDA asks for. We supervise work by any builder, including our own construction team, and work built to our own architecture. To discuss a house build, send the approved drawings and the stage the work has reached through our contact page.