The seismic zone of Islamabad and Rawalpindi, from the code itself
The seismic zone of Islamabad is 2B, and so is Rawalpindi. Both come from Table 2.2 of the Building Code of Pakistan, Seismic Provisions 2007 (BCP SP-2007), which lists the zone of every tehsil in the country. The code divides Pakistan into five zones by peak ground acceleration (PGA), the strongest horizontal shaking the ground is expected to reach. It designs buildings for shaking with a 10% chance of being exceeded in 50 years, a return period of about 475 years (section 2.2 and Appendix A).
| Zone | Peak ground acceleration (Table 2.1) | Zone factor Z (Table 5.9) | Examples from Table 2.2 |
|---|---|---|---|
| 1 | 0.05g to 0.08g | 0.075 | Fort Abbas |
| 2A | 0.08g to 0.16g | 0.15 | Lahore City, Multan City, Faisalabad City |
| 2B | 0.16g to 0.24g | 0.20 | Islamabad, Rawalpindi, Taxila, Kahuta, Gujar Khan, Attock, Jhelum, Chakwal, Haripur, Peshawar |
| 3 | 0.24g to 0.32g | 0.30 | Murree, Kotli Sattian, Abbottabad, Mansehra, Quetta |
| 4 | more than 0.32g | 0.40 | Muzaffarabad, Bagh, Balakot |
“g” is the acceleration due to gravity, so 0.20g is a fifth of it. For the twin cities and the country around them, these are the rows that matter:
| Tehsil (Table 2.2) | Zone | Tehsil (Table 2.2) | Zone |
|---|---|---|---|
| Islamabad (Federal Area) | 2B | Murree | 3 |
| Rawalpindi | 2B | Kotli Sattian | 3 |
| Taxila | 2B | Attock, Hassanabdal, Fateh Jang | 2B |
| Kahuta | 2B | Jhelum, Dina, Sohawa | 2B |
| Gujar Khan | 2B | Haripur | 2B |
| Chakwal | 2B | Abbottabad | 3 |
Two notes from reading the table. It uses the tehsil names of 2007, so a tehsil created later is not listed; use the zoning map (Figures 2.1 and 2.2) or the tehsil it was carved from, and ask your engineer to confirm. And a site-specific hazard analysis, where one is done for a large project, supersedes the map (section 2.4). Nobody does one for a house.
Is it zone 3? Where the confusion comes from
Search for the seismic zone of Islamabad and you will find “zone 3” in news reports, and research papers giving site hazard values above 0.3g for parts of the twin cities. Neither is the zone the code assigns for design. The news reports date from before or just after the 2005 earthquake, when the zoning was being redrawn. The research values come from different methods and return periods; they are useful for planners, but the design zone is the one in Table 2.2, and that is 2B.
The practical error runs the other way too. Because Lahore is 2A and the twin cities are 2B, a structural design copied from a Lahore house is not automatically right for a plot in Islamabad or Rawalpindi. The zone factor rises from 0.15 to 0.20, and the hills a few kilometres north are Zone 3.
What the code is, and who it binds
BCP SP-2007 was written after the October 2005 earthquake by NESPAK for the Ministry of Housing and Works, vetted by the Pakistan Engineering Council (PEC) and based on the US Uniform Building Code 1997 and ACI 318-05 (its preface). According to PEC, the federal cabinet approved it on 9 August 2007.
Three instruments give it force:
- S.R.O. 971(I)/2008 of 8 September 2008 added bye-law 10 to PEC’s bye-laws for consulting engineers: the Seismic Provisions “shall apply for engineering design of buildings, building like structures and related components”, and construction in violation of the code is a violation of professional engineering work under the PEC Act. The same S.R.O. says the code is to be revised every five years or earlier.
- In Islamabad, clause 4.1.17 of CDA’s Building Control Regulations 2020, as amended by S.R.O. 1074(I)/2023, reads in full: “Provisions of PAKISTAN BUILDING CODE shall be followed.” The next clause, 4.1.18, does the same for the 2016 Fire Safety Provisions, explained for shops and offices in our guide to fire safety for commercial fit-outs. The structural drawings go in with the house plan, as set out in our guide to CDA building plan approval for a house.
- In Rawalpindi, we have not found an equivalent clause in a regulation we could read today. The PEC bye-law still binds the engineer who designs the house, wherever it stands.
The newer code is a separate question. PEC has published the Building Code of Pakistan 2021 (BCP 2021), based on the 2021 International Building Code. It replaces zones with mapped spectral accelerations at a 2% chance of exceedance in 50 years, and assigns buildings a Seismic Design Category. On PEC’s own site it is filed as a final draft dated 26 October 2021, and we have found no gazette notification of it. CDA’s clause names no edition. So the honest position is: the 2007 provisions are the notified edition, BCP 2021 exists, and your engineer should state on the structural drawings which one the design follows.
What Zone 2B changes in a concrete frame house
Most new houses in Islamabad and Rawalpindi have a reinforced concrete frame with brick infill. For these, Zone 2B sets three things.
A house is not exempt. Section 5.29.1 lets one and two family dwellings skip the earthquake design section only in Seismic Zone 1. A house is a “standard occupancy” structure (Occupancy Category 4, importance factor 1.0 in Table 5.10), and for buildings of not more than two storeys above the basement (in Islamabad, regulation 2.6 of the CDA rules decides what counts as a house basement) the code allows a simplified static method (section 5.29.8.2). Simplified does not mean skipped.
The frame must be at least intermediate. Under section 5.33.2.7, concrete frames that resist earthquake forces must be special moment-resisting frames in Zones 3 and 4, and “as a minimum, intermediate moment-resisting frames” in Zone 2. Chapter 7 (7.3.1.3) says the same for Zones 2A and 2B and allows structural walls instead. An intermediate frame is a detailing standard: how closely column and beam ties are spaced, how bars are lapped, how beams join columns. It shows on the structural drawings, and on site before concrete is poured.
Soil changes the force. The design force depends on the zone and on the ground. With Z = 0.20, the code’s seismic coefficients are:
| Soil profile (Table 4.1) | What it is | Ca (Table 5.16) | Cv (Table 5.17) |
|---|---|---|---|
| SA | Hard rock | 0.16 | 0.16 |
| SB | Rock | 0.20 | 0.20 |
| SC | Very dense soil and soft rock | 0.24 | 0.32 |
| SD | Stiff soil | 0.28 | 0.40 |
| SE | Soft soil | 0.34 | 0.64 |
On soft soil the longer-period coefficient Cv is four times the hard rock value. Where the soil is not known in enough detail, section 5.29.3 tells the engineer to assume SD, unless SE is suspected or found. Filled plots, old nullah beds and made ground on the edges of the twin cities are where that assumption is most likely to be wrong, and where a soil investigation earns its cost.
Load-bearing brick houses: Category C
Some houses, boundary structures and outbuildings are still built with brick walls carrying the roof. Chapter 9 of the code puts these in a building category by zone and importance (Table 9.25). A house (importance 1.0) is Category C in Zone 2B and Category D in Zone 3. The main Category C rules:
| Rule | Category C (Zone 2B house) | Category D (Zone 3 house, e.g. Murree) |
|---|---|---|
| Mortar (Table 9.26) | Cement-sand 1:6, or cement-lime-sand 1:2:9, or richer | Cement-sand 1:4, or cement-lime-sand 1:1:6, or richer |
| Nearest opening to an inside corner (Table 9.27) | At least 230 mm | At least 450 mm |
| Total opening width as a share of wall length | 0.55 one storey, 0.46 two storeys, 0.37 three or four | 0.50, 0.42, 0.33 |
| Pier between two openings | At least 450 mm | At least 560 mm |
| Vertical steel at corners (Table 9.30) | None for one or two storeys; 10 to 12 mm bars for three | 10 mm from one storey; 10 and 12 mm for two |
| Steel in a 5 m band (Table 9.29) | 2 bars of 8 mm | 2 bars of 8 mm |
Bands are continuous reinforced concrete strips through the walls: at plinth where the soil is soft or uneven, at lintel level, and under the roof. They are the full wall width, at least 75 mm deep, in M15 (1:2:4) concrete, with longer spans needing heavier bars (Table 9.29). Table 9.28 lists the strengthening for Category C of one or two storeys as “a, c, c, f, g”, an evident misprint in which the lintel band (b) or roof band (c) is doubled; we read it as requiring both and would specify both. Bearing-wall buildings are limited to four storeys or 15 m (9.9.17.5.1), bricks must crush at not less than 3.5 MPa (9.9.17.3), and arches over openings are to be avoided (9.9.17.7.6).
Building in the hills around the twin cities
Murree, Kotli Sattian and Abbottabad are Zone 3, and the code’s site chapter matters more there. Before placing a building on or beside sloping ground in hilly terrain, the slope’s stability must be examined, and the building’s position must meet the setbacks in Figure 3.1 unless special slope measures are taken (section 3.4). In Zones 3 and 4 the foundation rules of section 4.5 also apply, and concrete frames must be special moment-resisting frames.
That examination starts with a plan of the ground: levels, the slope above and below the plot, cuts, retaining walls and drainage. Our topographic survey gives the engineer exactly that, in the same coordinates the engineering survey later uses to set the building out.
What to ask your engineer and builder
A house in Zone 2B is only as safe as its drawings and the work that follows them. Before you sign with a builder, ask for these, in writing, and attach them to the construction contract:
- The zone and code edition on the structural drawings: “BCP SP-2007, Zone 2B, Z = 0.20”, or the BCP 2021 parameters if that edition is used.
- The soil profile assumed, and whether it came from a soil investigation or the code’s default SD.
- The frame type: intermediate or special moment-resisting, with the tie spacing and lap details drawn, not left to the site.
- For bearing walls: the mortar mix, band positions and bar sizes from Tables 9.26 to 9.30.
- Inspection before every pour, so ties, laps and cover are checked while they can still be seen. Our house construction supervision checklist lists what to check at each stage.
Our construction team builds to the structural drawings, with setting out and levels checked by our own surveyors and each stage inspected before it is covered. The house itself starts with architecture that keeps the plan regular and the openings within limits, and owners who build with another contractor can add project supervision for those pre-pour checks. When the house is finished, as-built drawings record what was actually built, which is what any future engineer will need. To discuss a plot in Islamabad, Rawalpindi or the hills, send its location and size through our contact page, or book a short consultancy visit if you need a second opinion on drawings you already have.