CDA building plan approval for a house in Islamabad: documents, fees and time limits

Published · 11 min read · RN Tech Associates · in Building and approvals

Short answer

CDA approves house plans under the ICT Building Control Regulations 2020, as amended by S.R.O. 1074(I)/2023. Drawings are prepared and signed by a CDA-enlisted architect and structural engineer and filed at CDA's One Window Operation in two folders, with six sets of plans, Forms A-1 and A-2 and a scrutiny fee of Rs 6 per square foot of covered area or Rs 10,000, whichever is higher. CDA must answer within 10 working days. Approval lasts five years, and plinth and slab levels are verified during construction.

CDA building plan approval for a house in Islamabad: documents, fees and time limits

Key points

  • The 2023 amendment cut CDA's decision period for plans filed through an architect to 10 working days. Older pages still quote 21 days.
  • A CDA-enlisted architect and structural engineer must prepare the plans and supervise the building until it is complete.
  • Residential scrutiny fee: Rs 6 per square foot of covered area, basement included, or Rs 10,000, whichever is higher. The completion fee is the same again.
  • Approval is valid for five years. Building before approval costs Rs 20,000 plus Rs 100 per square foot, and the work can be removed.
  • In a private scheme CDA also needs the society's NOC, a plot on the approved layout and, under the 2023 scheme regulation, a CDA-vetted allotment letter.

Building a house in Islamabad starts with a plan CDA has approved, and the rules for getting one changed in August 2023. This guide follows the regulation itself, the ICT Building Control Regulations 2020 as amended by S.R.O. 1074(I)/2023, published in the Gazette of Pakistan on 16 August 2023. It covers who must prepare the drawings, what goes in the file, what CDA charges, how long it may take, and what is checked while you build. It is written for plot owners, including owners abroad, and for anyone briefing an architect.

It covers houses. Apartments, commercial buildings and the Design Vetting Committee follow other parts of the same regulation (see commercial plan approval and the DVC), and a shop or office fit-out must also meet the 2016 fire safety provisions.

Which rules apply to your plot

The same regulation applies across Islamabad Capital Territory except the Diplomatic Enclave, but where your plot sits changes what CDA asks for. Rawalpindi plots follow RDA’s process instead.

Where the plot is Limits the drawings follow Extra documents Notes
A CDA sector Schedule-I of the regulation NOC from CDA’s Estate Management (EM-I for houses), allotment or transfer letter, possession certificate CDA demarcates the plot and issues the possession certificate first (regulation 5.1.1)
A private housing scheme or society in Zones 2, 4 or 5 Schedule-5, written for private schemes The society’s NOC on CDA’s specimen; allotment and possession letters CDA approves building plans in private schemes too; see the conditions below
An unplanned area of Zones 2, 4 or 5, outside any scheme Regulation 8.22 and its table Fard, aks shajra with the site plan on the khasra plan, non-encumbrance certificate from the Tehsildar, site plan showing access from a revenue road, indemnity bond Street at least 30 feet wide; a sewage and drainage plan is mandatory

Private schemes. CDA’s specimen NOC has the society certify the owner, that “the plot is not included in the mortgage list of plot with CDA and is clear from all litigations”, that the plot’s use matches CDA’s approved layout plan, and that the society has scrutinised the plan first. On 19 January 2026 CDA’s Directorate of Housing Societies set out four conditions under its 2023 scheme regulation for processing building plans in a private scheme: the plot must agree with the originally approved layout plan (the latest one), even if approval has been withdrawn from the sponsor; the sponsor must have executed the transfer and mortgage deeds in CDA’s favour; the allotment letter must be vetted by CDA’s Director (Planning); and the record maintenance fee must be paid. Check these before the architect starts, because a perfect drawing will not move without them. Our guide to checking a scheme plot against its layout covers the first condition on the ground.

Who prepares and signs the drawings

Regulation 5.2.1 makes it mandatory to hire a CDA-enlisted architect and an enlisted structural engineer, both to prepare the building plans and to supervise the building until it is complete. Regulation 5.3.1 says the plans are prepared by architects and structural engineers registered with PCATP and PEC. CDA keeps the list of enlisted professionals at its One Window Operation and its Directorate of Architecture. The structural engineer designs the frame for Islamabad’s seismic zone, Zone 2B in the Building Code of Pakistan.

The supervision part is easy to miss. The architect and engineer give CDA notice on Form A-2 that they have taken on the work, and sign a certificate on Form B-2 when it is done (regulation 3.3). If either stops before completion, work must stop until a new appointment is made, and the owner has 15 days to make it.

Regulation 3.6.1(c) has one exception: where a design approved by CDA itself is adopted, no architect’s signature is needed on the plans.

What the drawings must show

Regulation 3.4.2 lists what the six sets of drawings (plus one copy on CD) must cover. Sheets are A0, A1 or A2, at scales of 1/8, 1/16 or 1/32 inch to a foot.

  • Plans, elevations, sections, and a site or key plan with north and the road width.
  • External dimensions of the building and internal dimensions of every room.
  • Total height of the building measured from the front road, with plinth, driveway and any split levels.
  • Roof plan with overhead and underground water tanks, sewerage and drainage lines.
  • Rainwater harvesting tanks where they apply.
  • Plumbing, with separate sewerage and drainage systems.
  • Ramps, the drainage grating at the gate, driveway and plinth, all against the front road level.
  • Foundation and structural design, fire safety drawings, a schedule of covered areas, a schedule of doors and windows, covered area calculations and a perspective view.
  • The signatures of the owner, the architect and the engineer.

Notice how much of the list is about levels against the front road. Plinth height, ramp height and basement exposure (see our house basement rules) are all limited relative to the road, so the drawings need real levels. That is why we start every house design from a measured plot, not from the plot’s nominal size.

The file: folder I and folder II

Regulation 5.3 sets out the file. The owner signs Form A-1, the architect and structural engineer sign Form A-2, and the file goes to CDA’s One Window Operation in two folders.

Folder I (for Estate Management) Folder II (for the Building Control Section)
Form A-1, original Form A-2, original
Form A-2, attested copy Form A-1, attested copy
Allotment or transfer letter, attested copy Proposed building plans, six original sets
Possession certificate, attested copy Allotment or transfer letter, attested copy
Sub-division letter, if any Possession certificate, attested copy
CDA’s letter accepting an attorney, if any Contour plan, if applicable
Owner’s or attorney’s CNIC, attested copy Sub-division letter and attorney letter, if any
Pay order of the scrutiny fee, original Owner’s or attorney’s CNIC; soil investigation report if applicable; copy of the fee pay order

Estate Management issues its NOC and forwards it to the Building Control Section, which scrutinises the plans and writes to the architect and the owner.

Fees

Annexure-A of the regulation sets the scrutiny fee, and Annexure-B the fines. These are CDA’s charges, paid to CDA, separate from any professional fees.

Item Amount for a house Where it is set
Scrutiny fee for approval Rs 6 per sq ft of covered area, or Rs 10,000, whichever is higher; basement area counts Annexure-A (A)(ii) and note 1
Completion scrutiny fee Same as the approval fee Annexure-A (B); regulation 3.11.1(v)
Revalidation of an unchanged plan 10% of the normal approval fee, minimum Rs 2,000 Annexure-A (C)
Revised approval Fee on the proposed covered area only Annexure-A note 3
Completed building differs by more than 15% Double the approval fee, on top of the completion fee Annexure-A note 5; regulation 3.11.1(iii)
NOC processing fee, residential Rs 10,000 lump sum Annexure-B (7)(ii)
Starting construction without approval Rs 20,000 compounding plus Rs 100 per sq ft Annexure-B (5)
Additions up to 10% without a revised plan Rs 50 per sq ft Annexure-B (6)

So a house with 4,000 square feet of covered area, basement included, pays a scrutiny fee of Rs 24,000 at approval and the same again at completion. A house of 1,500 square feet pays the Rs 10,000 minimum each time. Our free map approval fee calculator does this sum for any covered area, with the minimum, completion and revalidation.

How long CDA takes, and how long approval lasts

The 2023 amendment rewrote both time clauses. Regulation 2.2.6 and regulation 3.7.1 now say that where plans are submitted through an architect in line with the regulations, CDA shall tell the owner and the architect of the approval, or give the reasons for non-approval in writing, within 10 working days of submission. The 2019 text gave 21 days (three weeks, or six weeks for buildings over 10,000 square feet), which is the figure most news reports and guides still repeat.

Approval lasts five years from the date of approval (regulation 3.12.2), or for the construction period in the plot’s allotment terms (regulation 2.2.5). After that, revalidation or a revised approval is mandatory. If an application is rejected, regulation 4.1.22 allows an appeal to the CDA Board within 15 days of the order, with no fee.

During construction: Form-D and the inspection stages

Approval is not the last time CDA looks at the plot. Two checks run alongside the build.

Form-D (regulation 5.5). When the foundations reach plinth level and the boundary wall is up at least at the corners, the owner submits Form-D through the architect, who certifies the plinth, the plot size and the building lines and issues a provisional certificate. Work may continue once that is filed, and CDA’s Land Survey Division verifies the plot lines, plinth level, plot size and building lines within 15 days. Discrepancies must be corrected, or the owner may be penalised and the violating part demolished. Form-D is filed again at every slab level, before the concrete is poured. Getting it wrong at plinth stage costs Rs 20,000 plus Rs 20 per square foot of plinth area; not getting it verified costs Rs 4 per square foot (Annexure-B).

Architect’s inspections (regulation 3.12.8). The architect inspects at set stages and reports to the One Window Operation within seven days of each:

Stage Inspected
Before digging Ground demarcation of the area to be dug
Basement (if any) Foundation of the basement; basement roof before the slab is poured
Plinth Ground floor at damp proof course level, with the boundary wall
Ground floor At roof height, before the roof slab is poured
First and upper floors At roof height of each floor
Roof Water tank and stair tower (mumty)
Completion All remaining requirements

Limits your drawings are checked against

Schedule-I sets the main limits for houses in CDA sectors. Every house type there allows two storeys and 30 feet in height. There is no ground coverage percentage: the house “may cover a block, leaving compulsory setbacks”, so the setbacks decide the footprint. The plot’s type is decided by both its size and its frontage.

Type (Schedule-I) Plot size, sq yd Frontage, ft Front / side / side / rear setback, ft Max plinth
A, terraced up to 150 20 to 29 5 / none / none / 5 3 ft 6 in
A, terraced 201 to 300 30 to 35 10 / none / none / 8 3 ft 6 in
B, semi-detached 300 to 625 40 to 49 10 / none / 5 / 10 3 ft 6 in
C, detached 400 to 1000 50 to 59 15 / 5 / 5 / 10 5 ft
D, detached 700 to 1670 70 to 79 20 / 10 / 10 / 10 5 ft
D, detached 1770 to 2720 100 and over 40 / 15 / 15 / 10 5 ft

These are selected rows; the full schedule has eleven. Private schemes follow Schedule-5, whose setbacks differ: a detached house on a 50 to 59 foot frontage, for example, keeps a 13 foot front and an 8 foot rear setback instead of 15 and 10. Other rules that shape a house design include a 14 foot maximum floor height, a ramp no more than 12 inches above the road at the gate, a boundary wall between 3 and 7 feet high, mandatory rainwater harvesting on plots of 400 square yards and above, and no septic tanks in sectors. Any covered area beyond the limits is liable to demolition (regulation 2.4.1), and a deviation of up to 5 percent can be compounded only with CDA’s approval in advance (2.4.2).

Completion and occupation

Within one month of finishing, the owner files a notice of completion on Form B-1 with the architect’s certificate on Form B-2 and six sets of completion (as-built) drawings, again in two folders (regulations 3.12.10 and 5.6). CDA inspects the plinth level, ramp height, gate grating, sewer and storm water connections, setbacks, covered area and rainwater tanks before issuing the completion certificate.

No one may occupy the house before the completion certificate. Regulation 2.8.1 requires it within three months after the initial construction period ends, and sets a fine of Rs 5,000 a month for a residential building occupied without one, for the first year, doubled after that. The completion drawings must show what was actually built, which is what an as-built survey records. A house already built without approval follows a different route, set out in our guide to CDA regularisation of unauthorised construction.

We prepare house designs and the drawings CDA asks for, starting from a survey of the plot, through our architecture service, and can follow the build through project supervision. Send us your plot’s location and papers through the contact page and we will tell you which part of the regulation applies to it.

Want RN Tech Associates to handle this for your site?

Send the location and what the work is for. We reply with the questions that decide scope and price.

Questions

Common questions

01How long does CDA take to approve a house plan?

Under regulations 2.2.6 and 3.7.1 as amended in 2023, CDA must tell the owner and the architect within 10 working days of submission whether the plan is approved, or give the reasons in writing if it is not. The 2019 text said 21 days, which is why older pages still give that figure.

02What is the CDA building plan approval fee for a house?

Annexure-A sets the scrutiny fee for residential buildings at Rs 6 per square foot of covered area or Rs 10,000, whichever is higher, with basement area counted. The completion scrutiny fee is the same amount again. Revalidating an unchanged plan costs 10 percent of the normal approval fee, with a minimum of Rs 2,000.

03Who can prepare and sign building plans for CDA?

Regulation 5.2.1 makes it mandatory to hire a CDA-enlisted architect and an enlisted structural engineer, both to prepare the plans and to supervise the building until it is complete. Regulation 5.3.1 says the plans are prepared by architects and structural engineers registered with PCATP and PEC. CDA keeps the list of enlisted professionals at its One Window Operation and Directorate of Architecture.

04How long is a CDA building plan approval valid?

Five years from the date of approval, or the construction period in the plot's allotment terms (regulations 2.2.5 and 3.12.2). After that the plan must be revalidated or a revised plan approved.

05Do I need CDA approval for a house in a private housing society?

Yes, in Islamabad CDA approves building plans in private schemes too. The society first signs an NOC certifying the owner, that the plot is not on the mortgage list with CDA and that its use matches CDA's approved layout. CDA's January 2026 letter adds that the plot must agree with the originally approved layout and the allotment letter must be vetted by CDA.

06What happens if I start building before the plan is approved?

Regulation 2.2.3 makes the work liable to removal at the owner's cost, and Annexure-B sets compounding charges of Rs 20,000 plus Rs 100 per square foot for residential buildings. Where the work also breaks the regulations, regulation 2.2.4 allows demolition after 15 days' notice.

→Request a survey

Tell us about the site

Location, rough size and what you need it for. We reply with the questions that decide the scope and the price.

Town, area or a Google Maps link.

Rough size, purpose, deadline. Drawings can follow by email or WhatsApp.