Building a house in Islamabad starts with a plan CDA has approved, and the rules for getting one changed in August 2023. This guide follows the regulation itself, the ICT Building Control Regulations 2020 as amended by S.R.O. 1074(I)/2023, published in the Gazette of Pakistan on 16 August 2023. It covers who must prepare the drawings, what goes in the file, what CDA charges, how long it may take, and what is checked while you build. It is written for plot owners, including owners abroad, and for anyone briefing an architect.
It covers houses. Apartments, commercial buildings and the Design Vetting Committee follow other parts of the same regulation (see commercial plan approval and the DVC), and a shop or office fit-out must also meet the 2016 fire safety provisions.
Which rules apply to your plot
The same regulation applies across Islamabad Capital Territory except the Diplomatic Enclave, but where your plot sits changes what CDA asks for. Rawalpindi plots follow RDA’s process instead.
| Where the plot is | Limits the drawings follow | Extra documents | Notes |
|---|---|---|---|
| A CDA sector | Schedule-I of the regulation | NOC from CDA’s Estate Management (EM-I for houses), allotment or transfer letter, possession certificate | CDA demarcates the plot and issues the possession certificate first (regulation 5.1.1) |
| A private housing scheme or society in Zones 2, 4 or 5 | Schedule-5, written for private schemes | The society’s NOC on CDA’s specimen; allotment and possession letters | CDA approves building plans in private schemes too; see the conditions below |
| An unplanned area of Zones 2, 4 or 5, outside any scheme | Regulation 8.22 and its table | Fard, aks shajra with the site plan on the khasra plan, non-encumbrance certificate from the Tehsildar, site plan showing access from a revenue road, indemnity bond | Street at least 30 feet wide; a sewage and drainage plan is mandatory |
Private schemes. CDA’s specimen NOC has the society certify the owner, that “the plot is not included in the mortgage list of plot with CDA and is clear from all litigations”, that the plot’s use matches CDA’s approved layout plan, and that the society has scrutinised the plan first. On 19 January 2026 CDA’s Directorate of Housing Societies set out four conditions under its 2023 scheme regulation for processing building plans in a private scheme: the plot must agree with the originally approved layout plan (the latest one), even if approval has been withdrawn from the sponsor; the sponsor must have executed the transfer and mortgage deeds in CDA’s favour; the allotment letter must be vetted by CDA’s Director (Planning); and the record maintenance fee must be paid. Check these before the architect starts, because a perfect drawing will not move without them. Our guide to checking a scheme plot against its layout covers the first condition on the ground.
Who prepares and signs the drawings
Regulation 5.2.1 makes it mandatory to hire a CDA-enlisted architect and an enlisted structural engineer, both to prepare the building plans and to supervise the building until it is complete. Regulation 5.3.1 says the plans are prepared by architects and structural engineers registered with PCATP and PEC. CDA keeps the list of enlisted professionals at its One Window Operation and its Directorate of Architecture. The structural engineer designs the frame for Islamabad’s seismic zone, Zone 2B in the Building Code of Pakistan.
The supervision part is easy to miss. The architect and engineer give CDA notice on Form A-2 that they have taken on the work, and sign a certificate on Form B-2 when it is done (regulation 3.3). If either stops before completion, work must stop until a new appointment is made, and the owner has 15 days to make it.
Regulation 3.6.1(c) has one exception: where a design approved by CDA itself is adopted, no architect’s signature is needed on the plans.
What the drawings must show
Regulation 3.4.2 lists what the six sets of drawings (plus one copy on CD) must cover. Sheets are A0, A1 or A2, at scales of 1/8, 1/16 or 1/32 inch to a foot.
- Plans, elevations, sections, and a site or key plan with north and the road width.
- External dimensions of the building and internal dimensions of every room.
- Total height of the building measured from the front road, with plinth, driveway and any split levels.
- Roof plan with overhead and underground water tanks, sewerage and drainage lines.
- Rainwater harvesting tanks where they apply.
- Plumbing, with separate sewerage and drainage systems.
- Ramps, the drainage grating at the gate, driveway and plinth, all against the front road level.
- Foundation and structural design, fire safety drawings, a schedule of covered areas, a schedule of doors and windows, covered area calculations and a perspective view.
- The signatures of the owner, the architect and the engineer.
Notice how much of the list is about levels against the front road. Plinth height, ramp height and basement exposure (see our house basement rules) are all limited relative to the road, so the drawings need real levels. That is why we start every house design from a measured plot, not from the plot’s nominal size.
The file: folder I and folder II
Regulation 5.3 sets out the file. The owner signs Form A-1, the architect and structural engineer sign Form A-2, and the file goes to CDA’s One Window Operation in two folders.
| Folder I (for Estate Management) | Folder II (for the Building Control Section) |
|---|---|
| Form A-1, original | Form A-2, original |
| Form A-2, attested copy | Form A-1, attested copy |
| Allotment or transfer letter, attested copy | Proposed building plans, six original sets |
| Possession certificate, attested copy | Allotment or transfer letter, attested copy |
| Sub-division letter, if any | Possession certificate, attested copy |
| CDA’s letter accepting an attorney, if any | Contour plan, if applicable |
| Owner’s or attorney’s CNIC, attested copy | Sub-division letter and attorney letter, if any |
| Pay order of the scrutiny fee, original | Owner’s or attorney’s CNIC; soil investigation report if applicable; copy of the fee pay order |
Estate Management issues its NOC and forwards it to the Building Control Section, which scrutinises the plans and writes to the architect and the owner.
Fees
Annexure-A of the regulation sets the scrutiny fee, and Annexure-B the fines. These are CDA’s charges, paid to CDA, separate from any professional fees.
| Item | Amount for a house | Where it is set |
|---|---|---|
| Scrutiny fee for approval | Rs 6 per sq ft of covered area, or Rs 10,000, whichever is higher; basement area counts | Annexure-A (A)(ii) and note 1 |
| Completion scrutiny fee | Same as the approval fee | Annexure-A (B); regulation 3.11.1(v) |
| Revalidation of an unchanged plan | 10% of the normal approval fee, minimum Rs 2,000 | Annexure-A (C) |
| Revised approval | Fee on the proposed covered area only | Annexure-A note 3 |
| Completed building differs by more than 15% | Double the approval fee, on top of the completion fee | Annexure-A note 5; regulation 3.11.1(iii) |
| NOC processing fee, residential | Rs 10,000 lump sum | Annexure-B (7)(ii) |
| Starting construction without approval | Rs 20,000 compounding plus Rs 100 per sq ft | Annexure-B (5) |
| Additions up to 10% without a revised plan | Rs 50 per sq ft | Annexure-B (6) |
So a house with 4,000 square feet of covered area, basement included, pays a scrutiny fee of Rs 24,000 at approval and the same again at completion. A house of 1,500 square feet pays the Rs 10,000 minimum each time. Our free map approval fee calculator does this sum for any covered area, with the minimum, completion and revalidation.
How long CDA takes, and how long approval lasts
The 2023 amendment rewrote both time clauses. Regulation 2.2.6 and regulation 3.7.1 now say that where plans are submitted through an architect in line with the regulations, CDA shall tell the owner and the architect of the approval, or give the reasons for non-approval in writing, within 10 working days of submission. The 2019 text gave 21 days (three weeks, or six weeks for buildings over 10,000 square feet), which is the figure most news reports and guides still repeat.
Approval lasts five years from the date of approval (regulation 3.12.2), or for the construction period in the plot’s allotment terms (regulation 2.2.5). After that, revalidation or a revised approval is mandatory. If an application is rejected, regulation 4.1.22 allows an appeal to the CDA Board within 15 days of the order, with no fee.
During construction: Form-D and the inspection stages
Approval is not the last time CDA looks at the plot. Two checks run alongside the build.
Form-D (regulation 5.5). When the foundations reach plinth level and the boundary wall is up at least at the corners, the owner submits Form-D through the architect, who certifies the plinth, the plot size and the building lines and issues a provisional certificate. Work may continue once that is filed, and CDA’s Land Survey Division verifies the plot lines, plinth level, plot size and building lines within 15 days. Discrepancies must be corrected, or the owner may be penalised and the violating part demolished. Form-D is filed again at every slab level, before the concrete is poured. Getting it wrong at plinth stage costs Rs 20,000 plus Rs 20 per square foot of plinth area; not getting it verified costs Rs 4 per square foot (Annexure-B).
Architect’s inspections (regulation 3.12.8). The architect inspects at set stages and reports to the One Window Operation within seven days of each:
| Stage | Inspected |
|---|---|
| Before digging | Ground demarcation of the area to be dug |
| Basement (if any) | Foundation of the basement; basement roof before the slab is poured |
| Plinth | Ground floor at damp proof course level, with the boundary wall |
| Ground floor | At roof height, before the roof slab is poured |
| First and upper floors | At roof height of each floor |
| Roof | Water tank and stair tower (mumty) |
| Completion | All remaining requirements |
Limits your drawings are checked against
Schedule-I sets the main limits for houses in CDA sectors. Every house type there allows two storeys and 30 feet in height. There is no ground coverage percentage: the house “may cover a block, leaving compulsory setbacks”, so the setbacks decide the footprint. The plot’s type is decided by both its size and its frontage.
| Type (Schedule-I) | Plot size, sq yd | Frontage, ft | Front / side / side / rear setback, ft | Max plinth |
|---|---|---|---|---|
| A, terraced | up to 150 | 20 to 29 | 5 / none / none / 5 | 3 ft 6 in |
| A, terraced | 201 to 300 | 30 to 35 | 10 / none / none / 8 | 3 ft 6 in |
| B, semi-detached | 300 to 625 | 40 to 49 | 10 / none / 5 / 10 | 3 ft 6 in |
| C, detached | 400 to 1000 | 50 to 59 | 15 / 5 / 5 / 10 | 5 ft |
| D, detached | 700 to 1670 | 70 to 79 | 20 / 10 / 10 / 10 | 5 ft |
| D, detached | 1770 to 2720 | 100 and over | 40 / 15 / 15 / 10 | 5 ft |
These are selected rows; the full schedule has eleven. Private schemes follow Schedule-5, whose setbacks differ: a detached house on a 50 to 59 foot frontage, for example, keeps a 13 foot front and an 8 foot rear setback instead of 15 and 10. Other rules that shape a house design include a 14 foot maximum floor height, a ramp no more than 12 inches above the road at the gate, a boundary wall between 3 and 7 feet high, mandatory rainwater harvesting on plots of 400 square yards and above, and no septic tanks in sectors. Any covered area beyond the limits is liable to demolition (regulation 2.4.1), and a deviation of up to 5 percent can be compounded only with CDA’s approval in advance (2.4.2).
Completion and occupation
Within one month of finishing, the owner files a notice of completion on Form B-1 with the architect’s certificate on Form B-2 and six sets of completion (as-built) drawings, again in two folders (regulations 3.12.10 and 5.6). CDA inspects the plinth level, ramp height, gate grating, sewer and storm water connections, setbacks, covered area and rainwater tanks before issuing the completion certificate.
No one may occupy the house before the completion certificate. Regulation 2.8.1 requires it within three months after the initial construction period ends, and sets a fine of Rs 5,000 a month for a residential building occupied without one, for the first year, doubled after that. The completion drawings must show what was actually built, which is what an as-built survey records. A house already built without approval follows a different route, set out in our guide to CDA regularisation of unauthorised construction.
We prepare house designs and the drawings CDA asks for, starting from a survey of the plot, through our architecture service, and can follow the build through project supervision. Send us your plot’s location and papers through the contact page and we will tell you which part of the regulation applies to it.