Which rules apply
A house in Islamabad that was built without approval, or built differently from its approved plan, is dealt with under one set of CDA regulations. They are the Islamabad Residential Sectors Zoning (Building Control) Regulations 2020, notified as S.R.O. 1575(I)/2019 and published in the Gazette of Pakistan on 26 December 2019, and amended by S.R.O. 1074(I)/2023, published on 16 August 2023. Both are on CDA’s laws and regulations page.
Most pages that answer this question are news reports from several years ago, or a CDA notice that quotes a court order. They tell you that CDA “may regularise” buildings. They do not tell you what the regulation lets CDA accept, what it orders demolished, or what a file must contain. This guide works from the regulation text, with rule numbers.
One limit first. We could read the 2023 amendment as page images, and the base text of 2019 as text. Where a number below comes only from the 2019 text, we say so. A fee schedule can change by notification, so the final figure always comes from CDA’s One Window, not from a guide.
What can be compounded and what cannot
The regulations separate three situations, and which one you are in decides everything else.
| Situation | What the regulation says | Regulation |
|---|---|---|
| Extra covered area beyond the Schedule-1 limits | “Shall be demolished” | 2.4.1 |
| A deviation from any rule of up to 5%, approved in advance | “Shall be considered for compounding with charges”, if it does not conflict with any other regulation | 2.4.2 |
| Smaller rooms or sizes than the minimum in Schedule-2 | Some can be relaxed with a penalty, up to a stated percentage | Schedule-2 |
| A wider stair tower (mumty) on a terraced house | Relaxable up to 55% of the width under conditions; any width beyond that is demolishable and “will not be regularized” | 2.4.1 |
Three points are easy to miss.
First, compounding in regulation 2.4.2 is a “where possible and subject to approval of the Authority in advance” power. It is not a right. Work done first and explained later has the weakest position.
Second, the limit is a percentage of the rule being broken, not of the plot. A house whose covered area is over the Schedule-1 figure is in the demolition rule, not the compounding rule, because the regulation names excess covered area directly.
Third, some relaxations stop at a hard percentage. In the 2019 text of Schedule-2 the ventilation well is a case: a reduction of up to 20% is charged per square foot, and a reduction of more than 20% is “not compoundable”. Room sizes, kitchens and bathrooms in the same schedule are relaxable with penalty only up to 10% of the minimum. Roof projections over setbacks, in Schedules 3 and 4, are also “relaxable with fine” only up to a stated excess.
Setbacks, plinth and the things a survey decides
The deviations that cause the most trouble are the ones that are measured: setbacks, covered area, plinth level and plot lines. They decide whether a house falls under compounding at all.
- Covered area. It is the plan outline of each floor compared with the approved plan and the Schedule-1 limit for the plot size. Walls, porches and extensions added later all count.
- Setbacks. The distance from each plot line to the building, measured from the plot corners as laid out by CDA, not from a boundary wall that may itself be misplaced.
- Plinth level. Regulation 4.1.14 limits it to 3 ft 6 in above the mean level of the front road for terraced or attached houses and 5 ft for others. A plinth above the limit is treated as a storey: “that floor will be considered as ground floor”.
- Plot size and lines. Form-D, the plinth verification, is where CDA’s Land Survey Division checks plot lines, plinth level, plot size and building lines. Our completion certificate guide explains it.
None of these can be judged by eye. A deviation of “about 5%” has to be measured as a percentage, on a plan that CDA will accept, against an approved plan. That is the point where a house owner needs a surveyor’s drawing and an enlisted architect’s decision, not a negotiation.
What CDA can do to unauthorised work
Regulation 3.10, “Work carried out without permission”, is the enforcement rule. If building works are commenced or carried out contrary to the regulations, the Authority may:
- require the person doing the work, by written notice, to stop all work;
- require them to show sufficient cause, in writing, why the work or part of it should not be removed or altered to comply; and
- require them to attend in person or through an agent and show cause.
If they fail to show sufficient cause, the Authority may remove or alter the work and the owner pays the expense. Regulation 3.10.1(e) goes further: if works were commenced contrary to the regulations, the Authority “may demolish such unauthorized work with or without notice”.
Regulation 5.7 gives the same warning from the other side. Starting construction without approval is “a serious violation, subject to penalty and/ or removal of unauthorized construction”. For a house that was built and is lived in, regulation 2.8.1 adds the occupation fine: Rs 5,000 a month for a residential building without a completion certificate for the first year, doubled after that, in the 2023 text. A violation on the site also blocks a sale: under regulation 9.4.4 as amended in 2023, CDA’s Building Control Section processes a transfer NOC only where no violation exists at site.
The regularisation file for Zones II, IV and V
Zones II, IV and V of the Islamabad Capital Territory are the unplanned areas, outside the planned sectors. The 2019 text carries a separate “Procedure for regulations of buildings in Zone-II, IV & V (Unplanned development)”, headed “Application regarding regularization of structure / building”. Its documents are:
| Document | What it is |
|---|---|
| CNIC and authority letter | The owner’s identity, and a letter if someone else files |
| Fard | The certified copy of the sanctioned mutation or the register of landowners (Register Haqdaran-e-Zameen) from the tehsildar |
| Aks shajra | The village map from the tehsildar verifying possession against ownership, with the site plan superimposed on the khasra plan |
| Non-encumbrance certificate | From the tehsildar, ICT |
| Site plan | Showing access from an existing revenue road |
| Forms A-I and A-II | Available at CDA’s One Window |
| Indemnity bond | On the specimen attached to the regulations |
| Building plans | Prepared by an architect enlisted with CDA and PCATP |
| Structural drawings, design and stability certificate | By a CDA-enlisted structural engineer |
| Sewage and solid waste plan | How waste is disposed of |
| Undertaking | To pay conversion and development charges when determined and demanded |
The fees listed in the 2019 text are a scrutiny fee of Rs 6 per square foot of covered area and a regularisation fee of Rs 100 per square foot of covered area, plus land conversion charges applicable at the time of approval. We could not confirm from the 2023 amendment whether these were changed, so read them as the first-notified figures and ask CDA for the current schedule. Do not take any single figure from a news report as the fee for your house.
The same procedure sets how the outcome is decided: the regulation says structures falling under the by-laws “will be approved and others will be decided after approval of Revised Master-Plan”. In plain words, a structure that fits the by-laws can be approved, and one that does not is left open. For setbacks it gives two options if the compulsory setbacks are missing or short: bring down the part of the structure in the setback area, or pay a penalty for the missing or reduced setback.
Khasra is the numbered land parcel in the revenue map, and the aks shajra is the village field map. Matching a built house to them is a survey task, which is why the file asks for a site plan superimposed on the khasra plan. Our guide to the khasra plan and aks shajra explains how that overlay is made.
Why the as-built drawing comes first
Whichever route applies, CDA’s first question is what is actually there. A regularisation or compounding case that is filed on drawings that copy the approved plan will fail at the inspection, because the inspector measures the building against the drawings. The same is true of a completion case, where the six sets of completion drawings must show the house as built, not as approved.
A useful record has four parts:
- A measured plan of each floor, with every wall, porch, stair tower and projection drawn to its true outline.
- Setbacks and plot lines measured from the plot corners, with the building lines stated.
- Levels: plinth, each slab and the front road, tied to one benchmark.
- A comparison table: each measurement against the approved plan and the Schedule-1 or Schedule-2 limit, with the difference in feet and as a percentage.
With that table, the decision is no longer an argument. Items inside a compounding band go into the application. Items over a hard limit are known before CDA finds them, and the owner can decide what to alter. The method is in our guide to as-built drawings and record drawings, and it is the work of our as-built survey service. A plan from such a survey is a measured record. It does not replace the enlisted architect, who prepares and signs the building plans CDA asks for.
If the house is not yet built, the cheaper route is the one in our guide to CDA building plan approval: approve the plan before the first slab, and keep Form-D at each stage so that nothing needs to be regularised later.
Steps for a house owner
- Find out which area the house is in. A planned sector falls under regulation 2.4 and Schedule-1. Zones II, IV and V follow the unplanned-development procedure.
- Collect the papers you already hold: allotment or ownership papers, any approved plan, and any completion certificate or Form-D.
- Measure the house and make a comparison table against the approved plan and the schedule limits.
- Sort each difference into three groups: within a compounding band, over a hard limit, or an unapproved addition.
- Take the table to an enlisted architect and decide what needs amended drawings, what needs alteration and what goes into an application.
- Ask CDA’s One Window for the schedule in force and the form list before paying anything.
- Do not wait for a notice. Regulation 2.4.2 favours approval “in advance”, and regulation 3.10 allows demolition with or without notice.
To start with the measured record, send us the plot details and any approved plan through our contact page. A house in Rawalpindi follows RDA’s rules instead, set out in our guide to RDA building plan approval.