A commercial building in Islamabad is approved in two steps that people often mix up. The first is a design review by CDA’s Design Vetting Committee (DVC). The second is the formal building plan approval, which needs a much longer file. This guide follows the ICT Building Control Regulations 2020 as amended by S.R.O. 1074(I)/2023 (Gazette of Pakistan, 16 August 2023), and CDA’s own August 2026 release on the latest DVC meetings. It is written for plot owners, developers and architects who want to know what to prepare before the first meeting.
It covers commercial buildings, meaning shops and offices with or without flats. For a house, see our guide to CDA building plan approval for a house.
Which commercial buildings go to the DVC
Not every commercial plan is sent to the committee. Under regulation 3.7.1, CDA must either pass an order granting or refusing permission, or ask for more details. For a building with more than 10,000 sq ft of covered area it may take six weeks to respond. A case is referred to the Design Vetting Committee when the building is of an important nature or a public building, when its covered area is more than 10,000 sq ft, or when it is another special type of building.
A smaller commercial building goes through the ordinary approval route instead. In both cases the same list of approval papers applies later (see the file table below).
What the DVC looks at, and what it does not
The regulation is blunt about the committee’s limit. It says the DVC’s scope is to examine the facade and overall design according to modern standards and aesthetics only, and that its minutes do not mean sanction or approval of the building plans. Plans are then examined against the prevailing bye-laws and formal approval is issued after every codal formality is met.
In practice this means an “approved in principle” result is permission to go on to the full file, not permission to build. Starting work on a DVC letter alone is building without approval, which regulation 2.2.3 treats as work liable to removal at the owner’s cost.
Who presents, and what it costs
Section 9.1 says the design architect, or a representative architect, gives the presentation. CDA lists only cases whose Estate Management clearance certificate (A-I and A-II) has been issued, so the plot’s allotment and dues must be in order first.
The fee is a lump sum and is not refundable. It is Rs 250,000 for buildings in the Blue Area or equivalent, and Rs 150,000 for all other types, payable by the allottee or owner before the case is processed. If the project is not approved in principle in two meetings, 50 percent more is charged to the owner of the plot. A second round therefore costs money, which is one reason to arrive with the full presentation the first time.
The presentation pack
Part 1 of section 9.1 sets the minimum. It is a multimedia presentation covering the architectural concept (plans, sections and elevations), 3-D visualisation, firefighting arrangements and a bye-law analysis (FAR, setbacks and the like). The pack includes:
- eight copies of the presentation at A-3 size;
- a key plan showing the site, landmarks and natural features;
- a site plan showing the plot size and dimensions, a north sign, natural features, surrounding buildings, roads, footpaths, links and service connections;
- photographs of the site from all sides, fixed on a sheet and referenced to the site plan;
- a soft copy of the whole presentation on CD, USB or other media, with perspective views.
The ten schematic sheets
Part 2 asks for ten schematic sheets on top of the presentation. Several of them are where cases weaken.
| Sheet | What it shows |
|---|---|
| 1 Plumbing | Ducts and external connection points to the plumbing mains |
| 2 Electrical | Main wire routes and ducts, external connection points, space for meters and panels |
| 3 Firefighting and safety | Firefighting routes and detection points, the proposed system, equipment list, safety and rescue plan |
| 4 Parking | Car spaces by covered area, in-house staff and visitors shown separately, ramp gradients and turning radius |
| 5 Green architecture | The green features to be used |
| 6 Sui-gas (if applicable) | Main routes, ducts and meter spaces |
| 7 HVAC (if applicable) | Space for central plant, mechanical room, air handling units and split-unit outdoor units |
| 8 Landscape (if applicable) | Landscape design to suit the building |
| 9 Special persons | Ramps, washrooms, parking and other facilities for people with disabilities |
| 10 Rain water harvesting | Location of the tank or well |
Sheet 9 links to a fixed rule: regulation 4.1.16 requires ramps from footpath level for every building other than a dwelling house, at least one lift in commercial and public buildings of more than three storeys, and a toilet for special persons on every commercial floor in the major-road categories.
Why cases stall: what CDA’s 2026 release says
CDA’s release says the DVC met on 4 June, 16 June, 30 July and 20 August 2026. Of 40 commercial cases, 8 were withdrawn by architects and sponsors before the meetings “due to incomplete documentation and failure to fulfill the required prerequisites”. That left 32 presented, of which 23 were approved. The release does not give a count of deferred cases, but says the deferred ones failed “to properly present the basic parking requirements and fundamental planning parameters”, and that they return to the DVC once these are completed.
CDA also formed a committee to review deferred cases hit by anomalies and ambiguity in the existing bye-laws, with a detailed look at parking parameters and commercial regulations. For owners it adds two duties: the owner’s and the architect’s or consultant’s names are stated at the final letter stage and displayed at the site during construction, and legal proceedings may follow if approved designs are changed.
Read together with the regulation, three causes are plain:
- An incomplete file. Withdrawals were for missing documents and prerequisites, and the clearance certificate (A-I and A-II) is a precondition for being listed at all.
- A weak parking sheet. Deferrals named parking. Sheet 4 must show the calculation, ramp gradients and turning radius, not only a car count.
- Planning parameters not shown. The bye-law analysis (FAR, setbacks, coverage) must be on the slides for the plot’s own category.
Parking: two ratios in one gazette
Many pages and news items quote a single parking ratio. The gazette itself holds two. Regulations 8.13(B) item 9 (standalone commercial projects on arterial roads) and 8.14 note 3 (commercial buildings on major avenues in private schemes) say one car space for 750 sq ft of covered area, to be accommodated within the plot line including basements. The DVC’s Sheet-4 says one space for each 500 sq ft for commercial buildings and 750 sq ft for other buildings. The first notification in December 2019 gave 1,000 sq ft in the notes to the commercial tables, so older pages may carry that older number.
CDA’s release does not state a new ratio and says parking parameters are under review. We found no CDA notice that changes the figure, so do not design to a ratio quoted in a news story. Ask the Building Control Section which one it will apply to your plot, note the answer, and show the full calculation on Sheet 4. Parking floors on upper levels need a minimum height of 7 feet 6 inches, and ramps and parking floors are not counted in FAR.
The file after the DVC
Section 9.2 lists what is processed after the in-principle design approval. The plan is not sanctioned until this is complete.
| Paper | What the regulation asks |
|---|---|
| Basic papers | Allotment letter, CNIC, auction brochure |
| Architecture | Four A-2 prints, signed and stamped by the owner and the designing or supervising architect, showing bye-law details and the approved parameters and DVC observations |
| Structure | Four A-2 prints with design calculations and a soundness and stability certificate from a CDA-enlisted structural engineer, vetted by a short-listed PEC and CDA vetting consultant with a certificate |
| Soil | Soil investigation report vetted by a Pakistan Engineering Council consultant |
| Stability and indemnity | Engineer’s soundness certificate, vetting consultant’s certificate, and indemnity bonds from the allottee or developer, on CDA’s specimens |
| Services | Four A-2 prints of mechanical, electrical, plumbing and HVAC drawings with certificates |
| Environment | No objection certificate from the Environmental Protection Agency |
| Fire | Four A-2 prints of firefighting drawings and an NOC from a PEC-enlisted consultant on fire prevention and life safety under CDA’s standards, with an indemnity bond and undertaking on stamp paper |
| Site | Possession certificate from the Land Survey Division, CDA |
| Contractor | Name of the excavation contractor and a valid PEC registration certificate |
| Fees and bond | Scrutiny fee and the owner’s indemnity bond |
For plots in the standalone-commercial category of regulation 8.13, the regulation adds a Pak EPA clearance and a traffic impact analysis for projects of four kanals and above, and sets a scrutiny fee of Rs 100,000 per kanal. For commercial plots inside private schemes, CDA’s January 2026 letter adds that the plot must match the originally approved layout plan, the allotment letter must be vetted by the concerned Director (Planning), and the record maintenance fee must be deposited. Read the fire papers against our guide to fire safety for commercial fit-outs, and the basement against the CDA basement rules, which cover houses and show the pattern CDA follows.
Where a survey helps
The DVC slides lean on the site: plot dimensions, surrounding roads, footpaths and service connections, and photographs. A measured topographic survey gives the architect those facts to scale, so the bye-law analysis and the parking layout start from the real plot. After construction, the completion route under section 9.3 needs as-built drawings with the fire drawings, filed with Form B-1 and Form B-2 through the One Window Operation. An as-built survey measures the finished building for those drawings. See also our guide on as-built and record drawings and on CDA completion certificates for houses, whose stages are the same in outline. If a building was started without approval, see CDA unauthorised construction and regularisation.
Before you book a DVC slot
- Confirm the Estate Management clearance certificate (A-I and A-II) is issued.
- Fix the plot’s category in the regulation (8.13, 8.14 or the plot’s own schedule) and write out its FAR, setbacks and coverage.
- Get CDA’s answer in writing on the parking ratio for your plot.
- Prepare all ten schematic sheets, not only the architecture.
- Budget for the fee and for a second meeting, since a second round adds 50 percent.
- Start the structural, soil, fire and EPA papers early, because they follow straight after the DVC.
Our architecture service prepares the plans and presentation for an enlisted architect to sign, and an independent construction supervision check covers the building stage. Send us your plot details through the contact page and we will tell you which route applies. The DVC fee and rules can change, so check the current CDA notice before you pay.