“Naksha pass” is the everyday name for getting a building plan approved. In Rawalpindi, for most private plots outside the cantonments, that means the Rawalpindi Development Authority (RDA). This guide sets out what RDA’s own current checklists ask for, what it charges, how long it says it takes, and what happens at completion. It is written for plot owners, including owners abroad, and for anyone briefing an architect for a house.
Everything here comes from RDA’s published checklists and Governing Body minutes, linked below. Where we could not confirm something from an RDA document, we say so.
First: is your plot under RDA?
Before anything is drawn, find out which body approves building plans for the plot. Getting this wrong means a file filed in the wrong office.
RDA’s area was set by a Punjab Government notification of 24 October 1989, which declared the area within the Rawalpindi Municipal Corporation’s limits plus a schedule of revenue estates (mouzas) a “City” under the Punjab Development of Cities Act 1976, for RDA’s jurisdiction. RDA publishes that schedule on its downloads page; several entries are marked “area falling outside Cantt.”, which is the point: the cantonments are outside it.
| Where the plot is | Who to ask about building plans |
|---|---|
| A Rawalpindi Improvement Trust (RIT) scheme | RDA, under its RIT checklist |
| Elsewhere in the RDA controlled area, on land held through the revenue record | RDA, under its controlled area checklist |
| A private housing scheme approved by RDA | RDA, with the society’s NOC |
| Rawalpindi or Chaklala cantonment | The cantonment board |
| DHA, or a large scheme with its own building control | That body; confirm with the scheme office |
| Outside RDA’s scheduled estates | The local government for that area |
If the plot is in a private scheme, check also that the scheme and your plot are on RDA’s approved list before you design anything. Our guide to checking a plot before you buy explains how.
Which regulations RDA applies
RDA’s Governing Body minutes for its 48th meeting, held on 10 July 2020, record that at its 45th meeting the Governing Body “approved the adoption of LDA Building Regulations 2019 with certain amendments”. These are known as the RDA Building and Zoning Regulations 2020, and RDA’s checklists refer applicants to the BR forms “attached in RDA Building Regulation”.
A warning about copies online. The full text of an “RDA Building and Zoning Regulations 2020” that circulates on consultancy and property sites is watermarked “Draft not approved” and “Draft for Governing Body”. It may match the approved text in places, but it is not the approved regulation, and setback or coverage tables taken from it should not be treated as the rule. Ask RDA, or an architect who files with RDA, for the approved text that applies to your plot. We have not published Rawalpindi setback figures for this reason.
The same minutes show RDA using the building plan as a lever on site conduct. At that meeting the Governing Body approved fines for under-construction buildings whose underground tanks and water drums are left uncovered, a dengue risk: Rs 1,000 for a residential building at the first notice and Rs 2,000 at the second, and on continued disobedience “building plan will be cancelled and FIR will be registered against the owner / builder”.
Documents, by where the plot is
RDA’s checklist for residential building plans has three lists. These are the items as RDA publishes them.
| RIT scheme | RDA controlled area | RDA-approved private scheme |
|---|---|---|
| Owner’s CNIC (attested copy) | Owner’s CNIC (attested copy) | Owner’s CNIC (attested copy) |
| Application for verification of ownership and possession from RDA (DLD/DDEM) | Registry (attested copy) | Allotment or transfer letter (society attested copy) |
| Allotment or transfer and possession letter (attested copy) | Fard malkiyat for map (original) | Possession letter (society attested copy) |
| Sub-division letter and approved sub-division plan, if the plot is sub-divided | Intiqal (mutation), original | NOC from the society (original) |
| Mortgage release letter, if applicable; sub-division letter if RDA sub-divided the plot | ||
| BR forms 1, 3, 4, 6, 10, 11 and 17 | BR forms 1, 3, 4, 6, 10, 11 and 17 | BR forms 1, 3, 4, 6, 10, 11 and 17 |
| Undertaking for damages (BR-5) on Rs 1,000 stamp paper | Undertaking for damages (BR-5) on Rs 1,000 stamp paper | Undertaking for damages (BR-5) on Rs 1,000 stamp paper |
| Proposed plans: 4 ammonia prints, 2 cloth mounted | Proposed plans: 4 ammonia prints, 2 cloth mounted, stamped by a registered architect | Proposed plans: 4 ammonia prints, 2 cloth mounted, stamped by a registered architect |
| Certificate from an RDA-registered structural engineer | Certificate from an RDA-registered structural engineer | Certificate from an RDA-registered structural engineer |
Three items catch people out:
- Fard malkiyat for map. In the controlled area the ownership proof is the revenue record: an original fard issued for the purpose, the mutation and the registry. If the plot was carved from a larger khasra, the fard must show the owner’s share clearly enough to match the plot on the plan.
- Mortgage release letter. When RDA approves a private scheme, part of its plots is mortgaged to RDA until the development works are done. A plot still on that list needs a release before RDA will pass its plan. RDA’s scheme list advises buyers to check the mortgaged plot numbers before buying.
- The society’s NOC. It is the society’s confirmation that the plot is yours and is on the approved layout. If the plot on site does not match the layout, the NOC is where the file stops. Our guide to checking a scheme plot against its layout covers that check.
Fees and the 30-day timeline
RDA’s checklists set these charges. They are paid to RDA and are separate from professional fees.
| Item | Amount | Source |
|---|---|---|
| Plan scrutiny fee, residential | Rs 10 per square foot | Residential building plan checklist |
| BR form fee | Rs 500 | Both checklists |
| Completion processing fee, residential | Rs 5,000 | Completion plan checklist |
| Completion processing fee, commercial | Rs 10,000 | Completion plan checklist |
| Timeline, residential building plan | 30 days | Residential checklist: SOPs and timelines of E-Khidmat and One Window Operation centre |
| Timeline, completion | 30 days | Completion plan checklist |
So a house with 3,000 square feet of covered area pays a scrutiny fee of Rs 30,000 at approval, plus the form fee. The checklist does not say whether the area counted includes a basement or the mumty, so confirm the area basis with RDA when the file is assessed. Change of land use has its own RDA checklist and fee. Apartments and commercial buildings are set out next.
Working out the fee: a calculator in three lines
We found no official RDA online calculator. The rates are printed on RDA’s checklists, so the sum is short: covered area in square feet, times the rate for the building type, plus the Rs 500 BR form fee.
| Building type | Plan scrutiny rate | Source |
|---|---|---|
| House (residential) | Rs 10 per square foot | Residential building plan checklist |
| Apartment building | Rs 20 per square foot | Apartment and commercial checklists |
| Commercial building | Rs 30 per square foot | Apartment and commercial checklists |
The same rates appear on the apartment and commercial checklist for RIT schemes and the RDA controlled area, and on the one for RDA-approved private schemes. Both add “BR Form Fee Rs. 500”. The arithmetic below uses made-up areas to show the method, not any real file:
| Example | Covered area | Rate | Scrutiny fee | With the Rs 500 form fee |
|---|---|---|---|---|
| House | 2,500 sq ft | Rs 10 | Rs 25,000 | Rs 25,500 |
| Apartment building | 10,000 sq ft | Rs 20 | Rs 200,000 | Rs 200,500 |
| Commercial building | 6,000 sq ft | Rs 30 | Rs 180,000 | Rs 180,500 |
These are RDA’s scrutiny charges only. They leave out the stamp paper, the professionals’ fees and any other government charge. Two limits: RDA’s sheets are undated, and they do not say how the area is counted (basements, mumty, covered parking). Ask RDA for a written assessment before you pay. Older newspaper figures for RDA scrutiny rates differ from the sheets above, so do not use them.
Extra charges on larger buildings
The apartment and commercial checklists add items a house does not have:
- Extra-height charge above 38 feet: Rs 100 per square foot for an apartment building and Rs 60 per square foot for a commercial building, as printed. The sheet does not say whether it applies to the area above 38 feet or to the whole building, so ask.
- Builder’s agreement with the resident engineer, structural engineer and architect, on Rs 1,200 e-stamp paper. What a builder’s agreement should contain is set out in our guide to the house construction contract.
- Extra reports and drawings: structural drawings (four sets) and a vetting certificate from an RDA-registered vetting engineer for multi-storey buildings, MEP drawings, a soil investigation report signed by a PEC-registered engineer, and a height clearance NOC from CAA or RDA.
- TIA and EIA (traffic and environmental impact assessments) where they apply. The checklist notes the traffic report is required for plots of 4 kanal and above.
For a shop, office or clinic, the layout of exits, doors and finishes inside the building is also governed by the Building Code’s fire provisions; our guide to fire safety for commercial fit-outs sets out what they ask.
Outside RDA: the TMA and other local offices
Searchers also look for a “TMA map approval fee”. A Tehsil Municipal Administration (TMA) is the local government office that approves building plans in areas outside RDA’s scheduled estates. We could not find a TMA rate per square foot that we could confirm, and we do not apply RDA’s rates to it. Ask the TMA building control office for its fee schedule in writing, and which documents it wants.
Who signs: architect and structural engineer
RDA’s checklists ask for two professionals. The plans are stamped by a registered architect, and a structural engineer registered with RDA gives a certificate for the structure. At completion, the completion plan is stamped by both, and the completion certificate is issued through the RDA-registered structural engineer.
RDA publishes a “List of Approved Architects and Structural Engineers” on its downloads page. Check that your architect and engineer are on it before they start, because a plan stamped by someone RDA does not recognise will come back. The engineer’s design also has to answer to the seismic zone of Rawalpindi and Islamabad, which the Building Code of Pakistan sets as Zone 2B.
Step by step
- Confirm jurisdiction and status. Is the plot under RDA, and if in a scheme, is the scheme and the plot on RDA’s approved list and free of mortgage?
- Gather the ownership papers for your list above. For controlled area land, order a fresh fard for map from the land record office.
- Survey the plot. Measure the boundaries, the road width and the levels against the road. RDA’s form fee is small; redrawing a plan because the plot is a foot narrower than its papers is not. This is where a topographic survey of the plot pays for itself, and our guide to surveying a plot before designing a house lists what it should record.
- Design to the approved regulations that apply to the plot type and location, with the structural design alongside.
- Prepare the BR forms and the BR-5 undertaking, and have the prints stamped by the architect and the engineer’s certificate signed.
- File at RDA’s E-Khidmat and One Window centre and pay the scrutiny and form fees.
- Keep the approved plan on site and build to it; changes need a revised approval.
Completion plan and certificate
The completion certificate is RDA’s sign-off that the house was built as approved. RDA publishes its checklist for it, “documents required for approval of a completion plan”, as a one-page Urdu notice titled “COMPLETION certificate”. It has nine items. We read the notice itself (RDA’s downloads page, updated 2 February 2026), not a news report about it. Here it is in English, with what each item is for.
| No. | What RDA lists | What it is for, and how to get ready |
|---|---|---|
| 1 | Owner’s CNIC, attested copy | Proves who is applying. For a plot held by an attorney or heirs, settle the papers before filing. |
| 2 | Allotment letter (attested copy) or fard malkiyat for map (original) | Proof of ownership. A fard is the revenue record of ownership; the notice asks for the original. |
| 3 | Possession certificate or registry (attested copy), or nazri naqsha (original) | Proof that the plot is yours to build on. A nazri naqsha is the revenue-office plan of the plot. |
| 4 | Approved plan or approval letter (attested copy) | What the house is measured against. |
| 5 | Proposed plan, if one was approved (attested copy) | Only if a revised plan was approved during the build. |
| 6 | Completion plan: four ammonia prints and two cloth prints, stamped by an RDA-registered architect and structural engineer | The drawings of the house as built. They carry the professionals’ stamps, not only the owner’s. |
| 7 | Forms BR-08 and BR-15, and BR-09 for a multi-storey building | RDA’s own forms. We could not read their text, so we do not describe what they certify. |
| 8 | Completion certificate issued through an RDA-registered structural engineer | The engineer’s certificate on the structure. |
| 9 | Processing fee | Rs 5,000 for a residential completion plan, Rs 10,000 for a commercial one. A BR form fee of Rs 500 is noted separately. |
The notice carries the same “30 days” badge as RDA’s building plan checklists, tied to the E-Khidmat and One Window Operation Centre’s service standards. It does not say when the 30 days start. A file missing an item is the likeliest reason for the clock not to run, so check all nine before you file.
What the checklist does not say
It is a document list, not the regulation. It does not say how far a completed house may differ from the approved plan, what happens if it differs, whether there is a fine for living in a house with no certificate, or whether RDA inspects the site before it issues the certificate. RDA’s approved Building and Zoning Regulations are the place for those answers, and we could not read them (see the end of this guide). Do not take figures for them from a page that quotes the draft copy circulating online.
How it differs from CDA’s process in Islamabad
Readers often assume the two cities work the same way. On the papers they do not. CDA’s regulations set out nine stage inspections by the architect, Form-D at plinth and before each slab, Forms B-1 and B-2 and six sets of as-built drawings, and spell out the fine for occupying without a certificate: see our guide to the CDA completion certificate for a house. RDA’s published checklist is shorter and names different forms (BR-08, BR-09 and BR-15), and the owner’s side of it is mostly the stamped completion plan and the engineer’s certificate. Neither city’s rules should be used for the other.
Getting the completion plan right
The completion plan has to show what was built, as as-built drawings do, so any difference from the approved plan surfaces here. The difference that bites is usually small: a boundary wall moved, a stair tower enlarged, a floor area changed. Before the architect and engineer stamp the plan:
- Measure the finished house: outline of each floor, distances to the plot boundaries, and the plinth level.
- Lay those measurements over the approved plan and list every difference.
- Decide with the architect which differences need a revised plan before filing, and which are only drawing corrections.
- Draw the completion plan from the measurements, not by copying the approved plan.
An as-built survey gives you step 1 as a measured drawing, and supervision during the build keeps the differences small in the first place.
What we could not confirm
- The approved regulation text. We read RDA’s minute adopting LDA’s 2019 regulations with amendments, but not the approved RDA text itself, so this guide gives no setback, coverage or height figures for Rawalpindi.
- Online filing. News reports in January 2026 said RDA planned online building plan approvals. We have not seen an RDA notice saying the system is live; RDA’s checklists still name the E-Khidmat and One Window centre.
- Areas between authorities. Which office approves building plans in every part of the Metropolitan Corporation and the district’s tehsil councils is not set out in the documents we read. Confirm before filing.
For Islamabad, the process and fees are different: see our guide to CDA building plan approval for a house. We design houses from a measured plot and prepare the drawings and forms an authority asks for through our architecture service. Send us the plot’s location and papers through the contact page and we will tell you which authority and which list apply.