Start from PEC’s standard form, not a rate sheet
A house construction contract in Pakistan is usually a page or two: the plot, a rate per square foot for “grey structure”, a completion time and a payment schedule. Most disputes between owners and builders come from what that page leaves out. The better starting point is free and Pakistani: the Pakistan Engineering Council’s Standard Form of Bidding Documents for Procurement of Works (For Smaller Contracts), dated 11 June 2007.
PEC wrote it for public works. Its preface says it is based on the World Bank’s national bidding documents and FIDIC’s Short Form of Contract, was approved by ECNEC on 12 November 2007, and was notified by the Planning Commission on 12 February 2008 as mandatory for engineering organisations and departments at federal, provincial and district level. Its 2007 text says it is for works of not more than Rs. 25 million. None of that makes it binding on a private house owner, and this guide is not legal advice. What makes it useful is that its 16 conditions of contract cover every question an owner and a builder argue about, in plain terms, and its Contract Data page shows which blanks the owner (the “Employer”) has to fill in.
Below, each part of a house contract is set against the PEC clause that covers it.
The documents that make up the contract
A contract is the agreement plus the documents it refers to. PEC’s Contract Data (clause 1.3) lists them in order of priority, so that when two disagree, the higher one wins:
- The contract agreement
- The letter of acceptance
- The completed form of bid
- The contract data
- The conditions of contract
- The completed schedules, including the schedule of prices
- The drawings
- The specifications
For a house, that becomes: the signed agreement; the conditions you have agreed; the priced schedule or bill of quantities; the approved building plan (see CDA building plan approval or RDA building plan approval) and the structural, electrical and plumbing drawings; and a specification that names materials and grades (cement, steel grade and bar sizes, brick class, concrete mix, tiles, fittings). Attach them, sign every page, and list them in the agreement with their drawing numbers and revision dates.
Two code points belong on the structural drawings. Islamabad and Rawalpindi are Seismic Zone 2B, and in Islamabad clause 4.1.17 of CDA’s Building Control Regulations requires the Pakistan Building Code to be followed; our guide to the seismic zone of Islamabad and Rawalpindi explains what the drawings should state. And if the builder is to do any design himself, PEC’s clause 5 makes him submit it for comment and remain responsible for it; say in the contract exactly what he designs, if anything.
Scope: name every item in or out
No regulation, code or PEC document we have read defines “grey structure”. Builders use it for the frame and brickwork without finishes, but the edges move from one quotation to the next. A per-square-foot rate with an undefined scope is the commonest source of “extra” bills. Write each item into the contract.
| Item | Why it causes disputes | Write in the contract |
|---|---|---|
| Setting out and levels | A plot set out a little wrong breaks setbacks or the plinth level the authority checks | Who sets out, from which survey points, checked by whom |
| Excavation, backfill, disposal | Rock, water or extra depth are often charged as extra | Depth allowed in the price; rate for extra depth or rock |
| Anti-termite, damp proof course | Sometimes omitted silently | In or out, and the product |
| Internal and external plaster | Included by some, excluded by others | In or out, and ceiling plaster separately |
| Roof waterproofing and insulation | Often left for “finishing” | In or out, with the system named |
| Mumty, parapet, stair cover | Extra floor area that may not be in the covered-area figure | In or out, and whether it counts in covered area |
| Water tanks, septic tank, soakage pit | Large items, often quoted separately | Each one in or out, with sizes |
| Boundary wall, gate pillars, ramp | Frequently outside the building rate | In or out, with length and height |
| Conduits, sleeves, drainage pipes in slabs | Missed sleeves mean breaking new concrete | In, laid to the services drawings before each pour |
| Door and window frames | Some builders fix them, some leave them | In or out, and the material |
| Water and electricity for the works, curing, scaffolding | Hidden running costs | Who provides and pays |
| Material tests, cube tests, steel tests | Skipped unless written | Which tests, how often, who pays |
| Authority fees, utility connections, soil investigation | Owner’s costs, but sometimes assumed by the builder | Owner or builder, named |
If the price is per square foot, also write how covered area is measured: which floors, whether the mumty, porch, balconies and stairs count, and whether walls are measured to the outside face.
How the price is fixed
PEC’s Contract Data (clause 11.1(b)) makes the employer choose how the works are valued: a lump sum; a lump sum with a schedule of rates; a lump sum with a bill of quantities; remeasurement against estimated quantities; or cost reimbursable. For a house the practical choices are:
- Lump sum with a bill of quantities: one price for the drawings, with item rates used to value changes. Needs complete drawings before signing.
- Rate per square foot: simple, but only as good as the scope table above.
- Labour only: the owner buys materials. Cheaper on paper, but the owner carries ordering, wastage, quality and theft, and the contract must say who measures material use and what happens when work stops for lack of material.
Whatever the choice, keep the quantities and rates in a schedule attached to the contract, because PEC’s clause 10.2 values changes from the contract rates first, and new rates only where none apply.
Stage payments tied to inspections
Payments should follow work that has been checked, not time on site. PEC’s model (Contract Data 11.1(a)) pays 10% as an advance against a bank guarantee, 75% through monthly statements of work done, 10% when the certificate of completion is issued and the last 5% after the defects period, and marks every figure “Employer to amend as appropriate”. It also allows payment for materials delivered to site (80%) and plant (90%) in its model data. Under clause 11.3 the engineer verifies a statement within 7 days of its submission, and the employer pays the verified sum, less retention, within 30 days of that submission.
For a house, a stage schedule might look like this. The percentages are yours and the builder’s to agree; the checks are what protect you, and our house construction supervision checklist sets out what to look at in each one.
| Stage | Check before paying | Record |
|---|---|---|
| Setting out | Building lines and setbacks match the approved plan; levels taken from an agreed site datum | Setting-out sheet signed by both sides |
| Foundations | Excavation depth and base; steel, cover and levels before concrete (for a basement in Islamabad, check the walls and waterproofing against CDA’s basement rules) | Photos and a signed pour check |
| Plinth and damp proof course | Plinth level against the approved maximum; damp proofing laid | Level record |
| Each slab | Steel, laps, cover, sleeves and shuttering levels before the pour | Pour check per slab; cube test results |
| Brickwork and roof | Lintels, bands and openings to the drawings; roof slab cured | Stage report |
| Completion | Snag list agreed; works match the drawings; as-built drawings handed over | Certificate of completion |
| Retention release | Defects period over; notified defects fixed | Final account |
Our construction service works this way: our own surveyors set out the building from the design coordinates and check levels as it rises, and each stage is inspected and recorded before it is covered. If another builder is on site, independent project supervision can do the checks in the table for you.
Retention, defects and delay
Three clauses protect the owner after the builder says he has finished.
Retention. PEC’s model holds back 5% of each interim payment (Contract Data 11.3) and releases it 14 days after the defects period ends, or after notified defects and outstanding work are completed, whichever is later (clause 11.4).
Defects period. For the period stated in the contract data, the builder repairs at his own cost any defect caused by poor work or below-specification material that the owner notifies in writing (clause 9.1). PEC leaves the length blank: agree it in writing. At the end a maintenance certificate closes the builder’s obligations. The owner may also order work uncovered and tested; if it complies, the uncovering is paid as a variation, and if it does not, the builder bears it (clause 9.2).
Delay damages. If the builder misses the completion date, his liability under clause 7.4 is a stated amount per day of delay. PEC’s contract data caps it at 10% of the contract sum and notes that such damages are usually set between 0.05% and 0.10% of the sum per day. The builder is entitled to more time for causes the form puts on the owner, such as late handover of the site, late drawings or anomalies in them (clauses 6.1 and 7.3), so the drawings must be ready before the start date.
Taking over is time-bound too: within 14 days of the builder’s notice of completion, the owner either issues a completion certificate, with any outstanding items listed, or gives reasons for refusing (clause 8.2). That is the contract’s certificate; in Islamabad CDA’s own completion certificate for a house is a separate permission to occupy. From that certificate, care of the house passes to the owner (clause 13.1).
Changes, extra work and price rises
Changes are where most house contracts break down. PEC’s clause 10 is a good model:
- Changes are ordered in writing (10.1). If an instruction is given verbally, the builder confirms it in writing, and if the owner does not deny it within 7 days, it becomes a variation.
- Changes are valued first at an agreed lump sum or the contract rates, then at new agreed rates, or at daywork rates if the owner instructs (10.2).
- The builder must give early warning of anything that may delay the work or lead to a claim, and loses entitlement to the extent he fails to (10.3).
- Claims are submitted itemised within 28 days of the instruction or event (10.5).
If the contract allows the price to rise with material costs, say which materials, which published index or invoice basis, and from what base date. An escalation clause with no basis is not a clause.
If it goes wrong: notices, termination and disputes
Write down how the contract can end before anyone needs it. Under PEC’s clause 12.1, if the builder abandons the work, ignores valid instructions or fails to proceed, the owner gives a notice naming the default; if it is not remedied within 14 days, the owner may terminate by a second notice within a further 21 days. The builder has a mirror right if the owner fails to pay: suspend after 14 days, terminate after 28 (clause 12.2). Clause 12.4 then settles payment, including a sum equal to 20% of the unexecuted work in the owner’s favour when the builder was at fault.
Two more clauses are worth copying. The builder insures the works (PEC’s model: the contract sum plus 15%), his equipment and third-party injury (clause 14). And disputes go first to the engineer or the owner’s named representative for a decision within 28 days, then to arbitration under the Arbitration Act 1940 if either side gives notice of dissatisfaction within 14 days (clause 15).
A checklist before you sign
- Approved drawings, structural drawings and specification attached, numbered and listed in order of priority.
- Scope table filled in, item by item, with the covered-area rule if priced per square foot.
- Price basis chosen, with a priced schedule for valuing changes.
- Start date, time for completion and a programme within 14 days of starting (PEC’s model).
- Stage payments tied to signed inspection records.
- Retention percentage and defects period written in.
- Delay damages per day, with a cap.
- Changes only in writing; the 7-day confirmation rule.
- Insurance, termination notices and the dispute route.
- As-built drawings at completion. Our guide to as-built drawings explains what they should show.
If you want the drawings, scope and stages prepared before you invite prices, our architecture and consultancy teams can do that, and the engineering survey gives the site datum the setting out depends on. Send your plot details and any drawings you have through our contact page to discuss a contract you can build from.