Why two survey quotes are rarely for the same job
Two quotes for “a topographic survey” of the same land usually price two different jobs. Survey firm pages in Pakistan rarely say what they will deliver: the ones we read state no extent, no contour interval, no coordinate system, no accuracy and no list of drawings. So each firm prices its own assumptions, and the buyer compares numbers that describe different work.
The fix is on the buyer’s side and costs nothing: write the scope down once and send the same brief to every firm. The UK’s Geospatial Survey Association puts the trade-off in one line: “over-specifying wastes money but under-specifying creates risk”. A brief that matches the purpose avoids both.
Three items move the size of the job more than all the others together:
- How far the survey reaches. A house plot plus the road in front is one job (what it must cover is in our guide to surveying a plot before house design). A Punjab housing scheme surveyed 1,000 feet beyond its boundary is many times the area of the scheme itself on a small site.
- How closely the ground is described. Contours at 0.5 m need more levels, and better levels, than contours at 1 m, which is why the contour interval is chosen from purpose and slope.
- How accurate it must be, and how that is proved. A survey tested against independent checkpoints, with the result reported, is more work than one that is not.
The brief, item by item
These are the decisions a surveyor needs before a price means anything. Write an answer to each, even if the answer is “please advise”.
| Item | What to write in the brief | How it changes the job | If you leave it out |
|---|---|---|---|
| Purpose | What the survey is for and who receives it: architect, engineer, CDA, RDA, a Punjab development authority, a local government | Sets everything below | The firm guesses, and a design survey may not satisfy an authority file |
| Extent | The boundary to survey and any margin: the road, neighbours’ levels, a drain the site discharges into, or the 1,000 ft band for a Punjab scheme | Area to walk or fly, access to other people’s land | A quote for your land only, when the file needs more |
| Contour interval | 0.25 m, 0.5 m, 1 m, or “to suit the slope”; CDA asks 0.5 m or 2 ft for scheme survey plans | Number of levels and their accuracy | Contours too coarse to show where water runs |
| Drawing scale | 1:200 or 1:500 for a plot; not smaller than 1:1200 for a CDA scheme survey plan | Detail picked up, sheet count | Sheets that do not meet the authority’s scale |
| Accuracy | A number, tested at checkpoints, horizontal and vertical (see below) | Method, control, checking time | “Accurate” with nothing to hold anyone to |
| Grid and datum | WGS-84 on UTM zone 43N (Rawalpindi, Islamabad, Lahore), or the project grid; heights tied to a stated benchmark or a stated assumed level | Control work and ties to existing marks | A drawing that will not overlay a khasra plan, a satellite image or a later survey |
| Control left on site | How many permanent control points, and a schedule with coordinates and descriptions | Pillars or pins set and protected | Setting out and as-built checks start from scratch |
| Features | Buildings, walls, gates, roads and kerbs, trees (from what girth), poles and overhead lines, manholes and valve covers, water channels, graves, wells, tube wells | Field time, especially in built-up or wooded areas | A drawing missing what the designer needs |
| Spot levels | Grid spacing on open ground, plus levels on every feature, floor and road edge that matters | Number of points | Levels too sparse at the place a ramp or drain goes |
| Boundary | Whether to compare the walls with the revenue record or an approved layout, as a separate line | Revenue papers, overlay work | A belief that the survey “confirmed” the boundary |
| Buried services | Visible covers only, or a separate utility survey | Locating equipment, a different team | Pipes and cables assumed absent because none were drawn |
| Deliverables | AutoCAD DWG on named layers, PDF sheets, coordinate list (CSV), surface model on request, survey report | Office time | A flattened PDF that cannot be designed on |
| Access and timing | Gates, keys, guards, crops, neighbours’ permission, any drone flight restriction | Days on site | Delays charged as extras |
Two of these need a word of explanation. The height datum is the zero that levels are measured from. On a single plot an assumed level can work if the report states it; when a design must meet a road, a sewer or an authority’s levels, tie the survey to a known benchmark and say which. The boundary is covered further down, because it is the commonest misunderstanding in survey quotes.
What the authority already fixes for you
For a housing scheme, part of the brief is set by the rules of the authority the file goes to, and the brief should quote them.
| Item | Punjab, development authority areas (2021 rules) | Punjab, local government areas (2022 rules) | Islamabad, CDA (2023 regulation) |
|---|---|---|---|
| Extent | 1,000 ft around the scheme; a land sub-division is surveyed to its own boundary (rule 6(2)(j)) | 1,000 ft around the scheme (rule 6(3)) | The site; surroundings within half a kilometre go on a separate 1:10,000 site plan (clause 8-C(i)) |
| Copies | Triplicate | Triplicate | Three |
| Contour interval | Not set | Not set | 0.5 m or 2 ft (clause 8-C(ii)) |
| Scale | Not set for the survey; scheme plan 1:1200 to 1:2400, location plan 1:4800 (rule 9) | Same scales (rule 9) | Survey plan not more than 1:1200 |
| Content named | Khasra plan and layout overlays elsewhere in the file | Layout plan geo-referenced “with the appropriate coordinate system” | Khasra numbers, spot levels, high-tension lines, water channels; aks shajra on the contour plan |
None of these instruments names an instrument or a tolerance, and the 2022 rules contain no word about contours, levels or accuracy at all. That gap is why the accuracy line in your brief matters. The full rule-by-rule reading is in our guide to the topographic survey a housing scheme approval file needs, and the effect of the 1,000 ft band on the size of the job is worked out there in a table on why the margin drives the size of the job. For a scheme, the job to ask for is a housing scheme survey drawn to that authority’s specification.
Asking for accuracy as a number
“Accurate” is not a specification. A number is, if it says how it was measured. The ASPRS Positional Accuracy Standards for Digital Geospatial Data (Edition 2, 2023), a published American standard for mapping data, express accuracy as RMSE (root mean square error, a typical error size) in centimetres, horizontal and vertical, found by comparing the finished survey with independent checkpoints.
Three of its rules are worth copying into a brief:
- Checkpoints must be better than the product. Section 7.12: checkpoints “shall be at least two times more accurate than the required accuracy of the geospatial product being evaluated”.
- Enough checkpoints. The standard calls for at least 30 for a fully compliant assessment; with fewer, the report must say so.
- A plain statement of the result. The data is reported as “tested to meet” a stated accuracy class, with the RMSE actually found.
The same standard says it “does not endorse the use of GSD, map scale, or contour interval to express product accuracy”, but its Table B.8 gives the old equivalences for buyers who think in contours. Under the 1947 National Map Accuracy Standard, the equivalent contour interval is about 3.29 times the vertical RMSE. Read the other way:
| Contour interval you need | Vertical RMSE to ask for (about) | Table B.8 class that supports it |
|---|---|---|
| 0.25 m | 7.6 cm | 5-cm class (equivalent contour 16.45 cm); the 10-cm class (32.90 cm) is too coarse |
| 0.5 m (CDA scheme survey plans) | 15.2 cm | 15-cm class (equivalent contour 49.35 cm) |
| 2 ft (0.61 m) | 18.5 cm | 15-cm class; the 20-cm class (65.80 cm) is slightly too coarse |
| 1 m | 30.4 cm | 20-cm class (65.80 cm); the 33.3-cm class (109.55 cm) is too coarse |
A simpler test for contour plans, that 90% of checked levels fall within half the interval, is explained in our comparison of drone, total station and GNSS accuracy. Either way, the point for the brief is the same: name the interval, ask for the accuracy that supports it, and ask how it will be checked. A drone-only price for land under an orchard is a quote you should question, because the ground under trees is where drone accuracy falls away.
Two example briefs
A brief does not need to be long. These two show the level of detail that lets several firms quote the same job.
A house plot in Rawalpindi, for an architect. Purpose: house design and building plan drawings. Extent: the plot, the full width of the road in front, and the levels of both neighbouring plots along the shared walls. Interval: 0.25 m. Scale: 1:200. Grid: WGS-84, UTM zone 43N; heights to the nearest known benchmark if within reach, else an assumed level stated in the report. Control: two pins left on site. Features: walls with tops and bottoms, gate, trees, poles, manholes with cover levels, road crown and edges, the drain at the front with its invert where visible. Deliverables: DWG on named layers, PDF, CSV, short report. Boundary: walls as found; no comparison with the allotment plan unless priced separately. Access: plot empty, key with owner.
A 150 kanal scheme in a Punjab development authority area. Purpose: approval file under the 2021 rules. Extent: the khasra boundary plus 1,000 ft all round; neighbours’ access to be arranged by the sponsor. Interval: 0.5 m. Scale: plotted at 1:1200, in sheets with a key plan. Grid: WGS-84, UTM zone 43N. Accuracy: vertical RMSE of 15 cm or better on open ground, tested at independent checkpoints, with the result stated. Features: everything on the ground, with water channels, nullahs, high-tension lines, graves, tube wells and the access road’s right of way, property line to property line. Boundary: khasra plan overlay as a separate line. Copies: three sets plus DWG. Drone flights only where cleared.
The second brief shows why the khasra numbers matter at quote stage: the overlay of the revenue map on the survey is described in our guide to reading a khasra plan and aks shajra, and a firm cannot scope it without them.
Reading the quotes side by side
Put the quotes in one table against your brief, line by line. A firm that answers every line has quoted your job. These are the gaps that make a low price look lower than it is:
- No extent stated. The quote says “X kanal” with no margin, when your file needs the road or the 1,000 ft band.
- “Contours” with no interval, or an interval coarser than you asked for.
- “GPS survey” with no control. No permanent points, no schedule, no tie to a stated grid.
- No datum named, or a local grid that will not sit on a satellite image or a geo-referenced layout.
- No accuracy figure, or a maker’s instrument specification offered as if it were the survey’s tested accuracy.
- PDF only. A designer needs layered CAD and the point list.
- No report. Nothing that states method, control, checks and what could not be measured. What a complete report holds is in our survey drawing and report checklist.
- Drone only, over trees or a built-up block, with no ground work where the camera cannot see.
- “Demarcation included” in a topographic quote. Marking legal corners is a different job (below).
- Extras left open. Revisits, extra copies, neighbours’ access, waiting time.
Ask each firm to confirm its scope in writing against your brief. A firm that pushes back on an item with a reason (for example, that 0.25 m contours add nothing on a steep plot) is usually the one that has read it.
What a survey quote will not cover
Two things are often assumed to come with a topographic survey and do not.
The legal boundary. A topographic survey records the walls, fences, pillars and edges that exist on the ground. Whether they sit on the line in the revenue record or an approved layout is a separate question, and in Punjab the legal answer belongs to the revenue office. A survey can show where the record and the ground disagree; it cannot settle it. Price any boundary comparison as its own line.
Buried services. A topographic survey shows manholes, valve chambers and marker posts that can be seen, and draws pipes only where they can be traced from them. If anyone will dig, ask separately for an underground utility survey and say which quality level each area needs.
Authority fees, copies stamped by others and later changes to the design are also outside a survey quote unless the brief names them.
We quote every topographic survey against a written scope like the ones above, and we will help you write it if you are not sure what the job needs. How we check and report is set out on our standards page. To get a quote, send the location, the boundary as you know it and what the survey is for through our contact page or on WhatsApp, and we will come back with the scope in writing before the price.
