Cut and fill calculator: earthwork volume

Cut and fill is the volume between the existing ground and the design level: subtract the design level from each existing level, then take the average depth times the area for each grid square, or the average of two section areas times their distance apart.

Work out cut and fill

Method

The four corner levels of each square, separated by spaces or commas. Cut is where the ground is above the design level.

Cut 97.5 m³, fill 57.5 m³: 40 m³ more cut than fill.

  • Cut97.5 m³Dig out, 3,443 ft³
  • Fill57.5 m³Build up, 2,031 ft³
  • Net40 m³ surplus cutCut minus fill
  • Area covered300 m²From what you entered
Line by line
PartWorkingVolume
Square 1depths 0.8, 1.2, 1, 0.6cut 90 m³
Square 2depths -0.4, -0.2, -0.6, -0.8fill 50 m³
Square 3depths 0.4, -0.2, 0.2, -0.4cut 7.5, fill 7.5 m³

Also know

  • 1 square crosses the design level (cut and fill corners together) and was split in proportion to the corner depths.
  • Each square is 10 by 10 m (100 m²). Volumes are in place, before digging and before compaction.

How the calculator works

Cut and fill compares two surfaces: the ground as it is and the ground as designed. Where the existing level is above the design level the difference is cut, and where it is below, fill. This calculator turns your levels into those depths and their volumes with plain arithmetic, shows every line of the working, and applies no rate, soil factor or allowance of its own.

Grid of levels

Divide the site into squares and take the existing level at each corner. The depth at a corner is the existing level minus the design level. A square whose corners are all cut holds its area times the average of its four depths, which is area × (sum of the four depths) / 4, and a square of all fill works the same way. When the design level passes through a square, the calculator takes the cut as area × (sum of the cut depths)² / (4 × sum of all depths without signs), and the fill the same way with the fill depths. For a sloping surface that is exact; for a warped square it is an approximation, so use smaller squares where the ground changes quickly. Enter one square a line, as in the worked example, which levels three 10 m squares to 100.00 m.

Cross-sections

For a road, canal, drain or pipeline, take sections at regular distances and work out the cut area and fill area of each. The volume between two sections is the distance between them times the average of their two areas, L × (A1 + A2) / 2, the average end area method. The calculator does this for each interval and adds them. In the worked example the first interval holds 20 × (0 + 40) / 2 = 400 m³ of cut. That method overstates a volume that tapers to nothing, so take sections closer where the shape changes quickly. Our guide to where the methods disagree works a 400 m³ against 266.7 m³ case.

Area times depth

A rough check is always available: area times the average depth. The same sum gives these:

AreaAverage depthVolume
10 m by 10 m0.5 m50 m³
1,000 m²0.1 m100 m³
1 hectare0.05 m500 m³
5,440 sq ft (1 kanal at 272 sq ft a marla)1 ft5,440 ft³ (154.04 m³)

To turn marla and kanal into square feet or square metres first, use the land area converter; the marla size you choose changes the area. A cubic foot is exactly 0.028316846592 cubic metres, from the foot's exact 0.3048 m definition.

What the calculator does not cover

  • Swell and compaction. Volumes are in place, as the ground lies before digging. A fill of 100 m³ compacted needs more than 100 m³ of loose soil, by a factor you must measure for your soil.
  • Topsoil stripping, haulage distance, disposal and import, which are separate items in a contract. Net surplus is a figure to start from, not a bill.
  • Sloping sides of an excavation, trenches and ramps, unless you enter them as squares or sections.
  • Wrong levels. The answer is only as good as the survey: a 1 cm error in every level over one hectare is 100 m³, and two surveys on different datums can disagree by far more. See why two surveys of one site disagree.

For a quantity that will be paid or disputed, the original ground is surveyed jointly before work starts, and the sections or surfaces come from that record. That is the engineering survey service, and our guide on how earthwork quantities are measured and checked explains what to put in the contract. For a plot or housing scheme, the topographic survey gives the existing levels this calculator needs. All our calculators are on the free tools page.

Need the levels surveyed?

Send the location, the area and what the work is for. We reply with the questions that decide scope and price.

Questions

Common questions

01How do you calculate cut and fill?

Take the existing level and the design level at the same points, subtract to get a depth at each point (existing minus design: positive is cut, negative is fill), and multiply the average depth by the area it represents. This calculator does that for a grid of squares or, from cross-section areas, between sections. Cut and fill are shown separately because a site can balance to zero net and still move thousands of cubic metres.

02What is the grid method of cut and fill?

The site is divided into squares, and the existing level is taken at each corner. A square whose corners all lie above the design level holds its area times the average of its four corner depths. In the worked example a 10 m square with corner depths 0.8, 1.2, 1.0 and 0.6 m holds 100 × 3.6 / 4 = 90 m³. Where the design level cuts through a square, the calculator splits it in proportion to the corner depths.

03What is the average end area method?

For two cross-sections a distance L apart with areas A1 and A2, the volume between them is L × (A1 + A2) / 2. Do it for cut areas and fill areas separately and add the intervals. It is simple to check by hand, but it overstates a volume that tapers to nothing: a cut growing from 0 to 40 m² over 20 m is 400 m³ by this method and 266.7 m³ by the prismoidal formula.

04Does the result allow for swell or compaction?

No. The volumes are in place (bank) measure, from the surfaces alone. Soil swells when dug and compacts when placed, by amounts that depend on the soil and should be measured on the job, so the calculator applies no factor. Our guide on earthwork quantities explains which state a contract should say each item is measured in.

05Can I use feet instead of metres?

Yes. Choose feet and enter levels, grid sides and chainages in feet and section areas in square feet; volumes come out in cubic feet, with the cubic metre figure beside each total. A foot is exactly 0.3048 metres, so a cubic foot is 0.028316846592 cubic metres.

06Is this accurate enough to pay a contractor on?

It is accurate to the levels you enter and the method you choose, and no better. A 1 cm error in every level over one hectare is 100 m³. For a quantity that will be paid, the original ground should be surveyed jointly before work starts, which is what an engineering survey provides.

→Request a survey

Tell us about the site

Location, rough size and what you need it for. We reply with the questions that decide the scope and the price.

Town, area or a Google Maps link.

Rough size, purpose, deadline. Drawings can follow by email or WhatsApp.