High-tension lines, nullahs and water channels on housing scheme land: what the survey shows and how the layout handles them

Published · 12 min read · RN Tech Associates · in Land records and land use

Short answer

A high-tension line, nullah or water channel crossing housing scheme land stays inside the scheme and must be planned around, not over. The survey records it exactly; the Punjab rules then require a green strip under the line and, outside development authority areas, transfer of that strip free to the local government. Flooding is checked by the Irrigation Department in Punjab and by a flood study within 500 m of a main stream in Islamabad.

High-tension lines, nullahs and water channels on housing scheme land: what the survey shows and how the layout handles them

Key points

  • The power company holds a right to run and maintain the line, not the land under it, so the strip stays in your scheme area and needs a use the rules allow.
  • Punjab's 2021 rules ask for a green strip under high tension lines as the electricity agency requires; the 2022 rules add that it is transferred free as a prohibited area.
  • No Pakistani rule found gives one corridor width for every line; NGC's own 2025 project statements give 30 m and 50 m for its 500 kV and 220 kV lines, and nothing public covers 132 kV.
  • The 2022 rules ask for an Irrigation Department NOC on flooding and on the public waterways inside the scheme; CDA asks for a flood study within 500 m of a main stream.
  • A survey that shows towers, conductor heights, banks, beds and watercourse outlets lets the planner fix the layout once instead of after a return.

Why these features decide the layout

A high-tension line, a nullah or a water channel crossing your land does not leave the housing scheme. It stays inside the scheme boundary, it is counted in the scheme area, and the layout plan has to give it a use the rules allow. That is why the survey must show it exactly, and why the planner needs it before drawing a single plot.

The power line is the case people most often get wrong. Many sponsors assume the land under a line belongs to the power company. It usually does not. The national grid company’s own resettlement plan for a 220 kV line, prepared for the Asian Development Bank in 2014, explains the law: under the Telegraph Act 1885, the line owner may enter private land and build and maintain poles and lines “without the need to acquire the land affected” (sections 10 and 11), and pays for damage it causes (section 16). The land stays on the owner’s khasra. The line company gets the right to keep its line there; you keep the land and the restrictions that come with it.

Nullahs (natural drainage channels, often dry for most of the year) and water channels (a khal, the irrigation watercourse fed from a canal outlet) work the same way in practice. They carry water that someone downstream depends on, and both Punjab rule books and CDA’s regulation check them. A layout that draws plots across them will come back.

What the rules say, by authority

The rules that apply depend on where the land is, as for every other part of a housing scheme file. Our housing scheme survey page sets out the three instruments; this table shows what each says about lines, flooding and waterways.

Item Punjab, development authority areas (2021 rules) Punjab, local governments (2022 rules) Islamabad, CDA (2023 regulation, clause 8-C)
High-tension lines Rule 10, other requirements (e): “green strip under high tension electricity lines as per requirements of the concerned Department or Agency” Rule 10(1)(b): green strip as the electricity agency requires, “transferred to the local government free of cost as prohibited area”, exclusive of parks, with 75% relaxed against the open space requirement Survey plan must show “physical features such as high-tension lines, water channels, etc.”
Flooding Rule 7(2)(a)(ii): the site “is not prone to flooding” Rule 6(3): NOC from the Irrigation Department “certifying that the proposed area of the housing scheme is not prone to flooding and the details of public water ways falling within the proposed area”; rule 7 checks it “as certified by the Irrigation Department” Item (ix): flood study report “if the proposed scheme falls within 500 meters of main water stream”, vetted by a hydrological expert registered with PEC and enlisted with CDA
Water channels and paths Not named in the survey rule Form-B transfer deed counts “the area under revenue paths and water courses” Named on the survey plan
Where it shows Layout plan with khasra boundaries (rule 9) Layout plan, AutoCAD and geo-referenced soft copy (rule 6(3)) Survey plan at not more than 1:1200, aks shajra on the contour plan, layout on the topography plan

Two points are easy to miss. First, the 2021 rules also list canals and distributaries as “physical barriers” (rule 7(2)(b)(i)) that can make a small parcel “locked” for a land sub-division, so a channel can change which category your land falls into. Second, the 2022 rules want the Irrigation Department’s certificate at the application stage, not after approval; where it sits in the full file is in our housing scheme approval documents checklist.

The 2021 rules were amended by a notification of 8 July 2026, published in the Punjab Gazette on 15 July 2026. We have read it: it changes the access road condition, moves applications to a “centralized digital approval system” and sends electricity designs to a company holding a NEPRA distribution licence (rule 14(b)), but it leaves the flooding condition and the green strip under high tension lines as they were. Amendments to the 2022 rules were reported in 2026; we have not seen their gazette text, so confirm the lines above with the local government before the layout is finalised.

How wide is the corridor under a power line?

No Pakistani rule we could find sets one corridor width for every high-tension line. The housing scheme rules hand the question to “the concerned Department or Agency”, which means the line’s owner: the National Grid Company of Pakistan (NGC, the name NTDC took on 20 March 2025) for its 500 kV and 220 kV lines, and the distribution company (IESCO around Rawalpindi and Islamabad) for the lines it runs.

The clearest public figures are NGC’s own statements in a project document it prepared in September 2025 for a 500 kV line to Islamabad West grid station:

NGC statement (IEE, September 2025) Figure
Corridor “clear of all obstructions” for 500 kV and 220 kV lines (section 2.3), half either side of the centreline Minimum 30 m
NGC policy for 500 kV lines (chapter 3, public safety): 25 m either side of the centreline 50 m
Residential structures kept out from the plumb line of the outer conductor (section 2.3) 12 m
Conductor clearance over “building part” and over private property (table 3-2) 8.00 m
Conductor clearance over rivers and major canals at high flood level (table 3-2) 9.14 m

The same section says no residential or public buildings are permitted inside the corridor, that tube wells and pumps are not permitted under high-voltage conductors, and that general farming and low trees may stay. NTDC’s 2014 resettlement plan for a 220 kV line in D.I. Khan used a 50 m right of way, 25 m each side, for compensation.

Read these as what one owner states for its own lines, not as a national table. The two NGC figures differ by section and voltage, and nothing comparable is published for 132 kV or 11 kV lines. The figures that circulate online for “distance from a 132 kV line” come from Indian rules and do not apply in Pakistan. So the practical rule is simple: get the corridor for your line from its owner, in writing, before the layout is drawn, and quote the line name and the tower numbers your survey recorded.

What the survey must record

The survey turns each feature into lines and levels the planner can design against. CDA names high-tension lines and water channels on the survey plan; the Punjab rules do not list survey features, but the green strip, the flood certificate and the waterway details all depend on them. What the rest of the scheme survey must contain is in our guide to the topographic survey a housing scheme approval file needs. For these three features, we record:

Feature What we record Why the planner needs it
Transmission towers Centre and legs of each tower, tower number from its plate, line name if posted Fixes the line on the ground and identifies it for the owner
Conductors Plan position of the outer conductors; heights at the lowest point between towers, with the date, time and air temperature (conductors sag more when hot) The corridor is measured from the conductors, and clearance under them varies along the span
Poles of lower-voltage lines Each pole, line direction, any transformers Distribution lines are often diverted or put underground inside the scheme; the owner needs their position
Nullah Top of bank both sides, toe, bed levels along the channel, cross-sections, culverts and bridges with their openings The channel’s real width and capacity, and the levels the drainage design must meet
Flood evidence High-water marks, debris lines, eroded banks, anything residents point out Supports or questions the “not prone to flooding” condition
Watercourse (khal) Centreline, lined or earthen, bed and bank levels, the canal outlet (mogha), where it enters and leaves the land Downstream fields depend on it; the Irrigation Department asks for public waterways inside the scheme
Revenue paths and channels on the record The strips the aks shajra shows as paths or watercourses, overlaid on what is on the ground Form-B counts them; a mismatch between record and ground is better found now

Two habits make this work. We survey on real coordinates (WGS-84 / UTM), so the line, the channel and the khasra overlay sit together without stretching. And we put each corridor on its own drawing layer, labelled with where its width came from (owner’s letter, or “awaiting owner”), so nobody later mistakes an assumption for a rule. Reading the record correctly is covered in our guide to the khasra plan and aks shajra.

Nullahs, flood and the Irrigation NOC

Flooding is a condition of approval, not a design detail. Rule 7(2)(a)(ii) of the 2021 rules lets a development authority approve only a site that “is not prone to flooding”. The 2022 rules make the Irrigation Department the judge, through an NOC filed with the application that also lists the public waterways inside the scheme. In Islamabad, clause 8-C(ix) asks for a flood study if the scheme is within 500 metres of a main water stream, prepared by a hydrological expert and vetted by a third party; how that fits CDA’s stages is in our guide to CDA layout plan approval.

What the survey gives the hydrologist and the Irrigation Department:

  • the catchment’s edge where it crosses the 1,000 foot survey margin, and where water enters the land;
  • the channel’s sections at regular steps and at every change in shape, with bed levels, so the capacity can be worked out;
  • every culvert, bridge and pipe crossing, with its opening size and invert (the same levels later feed the drainage design, as our guide to service designs for a Punjab housing scheme explains);
  • the levels of the land beside the channel, so the planner can set plot levels above it.

The cost of ignoring a nullah is on public record. In Islamabad’s E-11, Dawn reported in August 2021 that a housing society had narrowed a nullah “from 40ft to 18ft” with CDA permission, that the narrowed nullah flooded E-11/2 the month before with loss of life, and that the government announced buildings on the nullah’s right of way would be razed. A layout that keeps the channel’s full width, with a road or green belt along it, avoids that.

Water channels and revenue paths

A watercourse or a revenue path through the land is not yours to close. The fields beyond it depend on it, and the revenue record shows it. The 2022 rules’ transfer deed (Form-B) recites the scheme land “including the area under revenue paths and water courses”, and the Irrigation NOC asks for “the details of public water ways falling within the proposed area”.

In the layout this usually means one of three things: the channel stays in place inside a green belt or road reserve; it is realigned along a road, if the Irrigation Department agrees and the farmers downstream still get their water; or it is piped, again only with that agreement. The survey has to show the channel as it runs today, with its levels, so whichever option is chosen can be designed. Settle it before the layout goes in; a realignment drawn without agreement is a reason for a return.

How these features change the layout and the saleable area

Every metre of corridor is land you own but cannot sell as plots. The arithmetic is simple, and worth doing before the land price is agreed. This table is geometry, not a rule: a line crossing the land in a straight run, with the two NGC corridor figures above, converted at the revenue kanal of 5,445 square feet (about 505.9 m²).

Length of line across the land 30 m corridor 50 m corridor
300 m 9,000 m², about 17.8 kanal 15,000 m², about 29.7 kanal
600 m 18,000 m², about 35.6 kanal 30,000 m², about 59.3 kanal
1,000 m 30,000 m², about 59.3 kanal 50,000 m², about 98.8 kanal

How the strip is then counted depends on the rule book. The 2022 rules keep the strip separate from parks but let 75% of it be set against the open space requirement; where that would be more than half the required open space (the rule’s example is the 7% figure), the sponsor still provides 3.5% as open space. The wording is hard to read, so agree the calculation with the local government before the area statement is fixed. How this sits with the other rule 10 requirements is in our guide to planning standards for housing schemes in Punjab, and what it does to the sellable land is worked through in saleable area in a Punjab housing scheme.

Good layouts turn the constraint into structure. A corridor or a nullah reserve can carry a road, a linear park or a green belt, and plots can face it rather than back onto it. Two placements to avoid: the scheme’s tube well or pumping station under the conductors (NGC’s statement does not permit tube wells and pumps there), and plots whose rear lines fall inside the corridor, which buyers discover at the building plan stage.

Before you plan or buy

Five questions settle most of this before money is spent:

  1. Which lines cross or touch the land, and who owns each? The survey gives tower numbers and line names; the owner gives the corridor in writing.
  2. Is any nullah, drain or watercourse on the land or within the survey margin? If so, get the sections surveyed and start the Irrigation Department or flood study conversation early. The other checks to run before buying scheme land, from access road to title, are in our guide to checking land before you buy it for a housing scheme.
  3. What does the revenue record show? Paths and watercourses on the aks shajra stay public unless lawfully dealt with.
  4. How much area do the corridors and reserves take? Do the arithmetic above with real widths before agreeing a land price.
  5. For a buyer: where is your plot against the corridor? Check the plot against the approved layout and the survey, not the brochure. The worked example in our khasra plan guide shows how a boundary on paper is tied to the ground, and our guide to checking a plot before you buy in Pakistan covers the papers and approval checks that go with it.

We survey these features as part of every housing scheme survey, on the same control the layout and the services designs will use. To scope a survey for land with a line or a channel across it, send the khasra numbers and a map pin through our contact page, and tell us which lines and channels you already know about.

Want RN Tech Associates to handle this for your site?

Send the location and what the work is for. We reply with the questions that decide scope and price.

Questions

Common questions

01Can you build a house under a high tension line in a housing scheme?

Not on a planned plot. The Punjab rules ask for a green strip under high tension lines, and the grid company's own safety statements keep residential buildings out of its corridors: NGC's 2025 statement keeps residential structures 12 m from the plumb line of the outer conductor of its line. The layout should place plots outside the corridor the line's owner gives in writing.

02What is the safe distance from a 132 kV line for a house?

We found no published Pakistani rule that states one for 132 kV lines. The figures that circulate online come from Indian rules and do not apply here. Ask the line's owner (NGC, or the distribution company, which around Rawalpindi and Islamabad is IESCO) for the corridor and clearance in writing, quoting the line name and tower numbers from your survey.

03Can a high tension line on our land be moved or put underground?

Only the line's owner can decide that, after an application from you; nothing in the housing scheme rules lets a sponsor move it. Until a diversion is approved and built, plan the layout around the line where it stands and show the corridor on the survey and the layout plan.

04Does the land under a high tension line count as park in a housing scheme?

Under the 2022 local government rules the strip is transferred free as a prohibited area and is kept separate from parks, but 75% of it may be set against the open space requirement, with at least 3.5% of the scheme still provided as open space where the strip would cover more than half of it. The 2021 rules for development authority areas say only that a green strip is provided as the agency requires.

05Can a nullah inside a housing scheme be filled or narrowed?

Not without the authority's approval and, in Punjab, the Irrigation Department's view on flooding. Narrowing a nullah has gone badly: in Islamabad's E-11, a nullah narrowed from 40 feet to 18 feet flooded in July 2021, and the government announced that buildings on its right of way would be razed. Design the layout around the channel's full width.

06Why are plots near high tension wires cheaper?

Buyers avoid them, and a plot that sits partly inside a corridor may not be buildable to its full size. Before you buy, check the plot against the approved layout plan and see where the corridor runs on the survey, not only on the sales map.

Sources

  1. Punjab Development Authorities Private Housing Schemes Rules 2021, Punjab Gazette (Extraordinary), 7 December 2021, rules 7, 9, 10 and 24 (copy hosted by FDA)
  2. Punjab Private Housing Schemes Rules 2022, Notification No. SOR(LG)8-5/2022, rules 6, 7 and 10 and Form-B (LG&CDD compendium)
  3. CDA letter of 6 March 2026 quoting clause 8-C of the 2023 ICT private housing scheme regulation (S.R.O. 886(I)/2023)
  4. Amendments to the Punjab Development Authorities Private Housing Schemes Rules 2021, Notification No. SO(H-II)2-5/2015 of 8 July 2026, Punjab Gazette (Extraordinary) 15 July 2026 (RDA copy)
  5. National Grid Company of Pakistan (formerly NTDC), Initial Environmental Examination for a 500 kV line to Islamabad West, September 2025, section 2.3 and chapter 3 (ADB 59002-001)
  6. NTDC Land Acquisition and Resettlement Plan, 220 kV D.I. Khan grid station and line, August 2014, sections 1 and 4.1 (ADB 37192-044)
  7. Dawn, 25 August 2021: buildings on right of way of nullahs in E-11 to be razed (news report)

Rules and fees change. Check the current notification with the authority before you file; we do this on every job.

→Request a survey

Tell us about the site

Location, rough size and what you need it for. We reply with the questions that decide the scope and the price.

Town, area or a Google Maps link.

Rough size, purpose, deadline. Drawings can follow by email or WhatsApp.