Three land use rule books, and which one is yours
Whether land can carry a housing scheme is decided by its land use status in the plan that covers it, and Punjab has more than one set of land use rules. The housing scheme rules then say which statuses a scheme may use. Start by working out which pair applies to your land.
| Where the land is | Land use rules | Housing scheme rules | Who answers the status request |
|---|---|---|---|
| Inside a development authority’s area (RDA, FDA, GDA, MDA and others) | Punjab Development Authorities Land Use (Classification, Reclassification and Redevelopment) Rules 2021, made under section 43 of the Punjab Development of Cities Act 1976 | Punjab Development Authorities Private Housing Schemes Rules 2021 | The development authority |
| Punjab, outside development authority limits | Punjab Local Governments Land Use Plan (Classification, Reclassification and Redevelopment) Rules 2020 | Punjab Private Housing Schemes Rules 2022 | The local government |
| Lahore, LDA’s area | LDA’s own land use rules (reported as the LDA Land Use Rules 2020) | LDA’s own rules | LDA |
Two notes on the sources. The development authority land use rules we read are the copy hosted by the Faisalabad Development Authority: a scan of a March 2021 notification with its number left blank, so confirm the current text with your authority. The 2020 local government rules were made under the Punjab Local Government Act 2019; the 2022 housing scheme rules still refer to them by name, so they remain the instrument outside development authority areas until replaced. We have not found an official copy of LDA’s land use rules online, so for Lahore, ask LDA.
The line between the first two rows is legal: under rule 4 of the 2021 housing scheme rules, a local government may not approve a scheme in a development authority’s notified area. The approval stages that follow are in our guide to private housing scheme approval in Punjab.
What the housing scheme rules allow
The housing scheme rules turn land use into a yes or no.
- Development authority areas. Rule 44 of the 2021 rules lets the authority allow a housing scheme “in the area declared residential or peri-urban in the master plan, outline development plan, agro-ville development plan, peri-urban structure plan and other allied plans”. A land sub-division is allowed only in an area earmarked as a settlement in the master plan, of at least 500 kanal, which the authority’s governing body has declared for sub-division cases. Rule 7(2)(a)(iv) adds that the proposal must conform to the approved plans.
- Local government areas. Rule 5(1) of the 2022 rules allows a scheme only “in the area declared as residential area in site development zone, structure plan or master plan or outline development plan or peri-urban structure plan”. Rule 7 asks for conformity with the approved plans; where no such plans exist, the local government and the District Planning and Design Committee must “exercise due diligence”, looking at infrastructure and growth potential.
Note the difference: peri-urban land qualifies directly inside a development authority area, but outside one the 2022 rules ask for land declared residential.
Land use classes compared
The two sets of land use rules divide land differently, and the class on the map decides what can be built.
| Development authority rules 2021, rule 3 | Local government rules 2020, rule 3 |
|---|---|
| Residential | Residential |
| Commercial | Commercial (including institutional) |
| Industrial | Industrial |
| Institutional | (part of commercial) |
| Mixed use | No separate class |
| Open space and recreational | No separate class |
| Peri-urban | No class; site development zones instead (rules 19 to 26) |
| Special development zone | No separate class |
| Agricultural | Agricultural |
| Notified area | Notified area |
Each class has permitted uses, permissible uses (allowed with the committee’s approval and, in development authority areas, a fee) and prohibited uses: anything neither permitted nor permissible.
Peri-urban, agricultural and the site development zone
Most new schemes are proposed on farmland at the edge of a town, so three terms decide most cases.
Peri-urban (development authority areas). The 2021 land use rules define it as the area between contiguous urban development and the rural countryside, with low population density, mostly farmed and “likely to be urbanized in the next twenty years”. Rule 10(3) says peri-urban land “shall be considered residential until the land use is specified”, and rule 10(4) makes any conversion subject to the conversion fee.
Agricultural (development authority areas). Rule 12 has the authority notify the land outside the peri-urban area as agriculture area. Its permitted uses include crops, orchards, livestock farms, tube wells and a farm house within a farm of at least four kanal, but not a housing scheme.
Site development zone (local government areas). A local government may notify a site development zone for future development and prepare a structure plan for it, with proposed roads, blocks and land uses for the next twenty years (rules 19 to 22). Rule 20(2) is the trap: land in the zone “shall be deemed to be agricultural area unless it is converted into proposed land use upon payment of conversion fee”. Rule 20(3) adds that a private housing scheme “can only be established in residential land use of an approved site development zone structure plan”. A residential colour on the structure plan is the start of the process, not the end.
The land status request
You do not have to read the plans alone: the authority will state the status in writing. Under rule 5 of both housing scheme rule books, apply with:
- a valid CNIC;
- the khasra numbers marked on a satellite image (under the 2022 rules, certified by the Assistant Commissioner);
- proof of the Rs 1,000 processing fee.
The 2022 rules require the local government to reply within two weeks. The reply is valid for six months under both rule books, and the 2021 rules say it does not commit the authority not to change the land use later. Ask before you buy land, and file the scheme application while the letter is still valid. The request is the first item of the approval file in our housing scheme approval documents checklist; the other checks that belong before purchase (size, access road, flood and title) are in checking land before you buy it for a housing scheme.
Notified maps can also be read directly. Under the 2020 local government rules, the notified land use classification map, the site development zone structure plan and the land use plan are kept on the notice board, published on the local government’s website, and sold as certified copies (rules 18, 26 and 28). In District Rawalpindi, RDA publishes tehsil maps and plans (read map by map here), and the approval route is described in our guide to housing scheme approval in Rawalpindi.
Conversion and its fee
Where land is not yet in a use that allows a scheme, it must be converted, and the fee depends on which rules apply. Both housing scheme rule books make the conversion fee a condition of approval (2021 rule 26; 2022 rules 21 and 27).
| Rule | Conversion | Fee |
|---|---|---|
| 2021 housing scheme rules, rule 36 (development authorities) | Peri-urban area to a housing scheme | 5% of the residential value in the valuation table; if none, 5% of the average sale price of residential land nearby over the preceding twelve months |
| 2021 land use rules, rule 30(1)(c) (development authorities) | On declaration of a peri-urban area: agricultural to residential | 20% of the residential value of the total area of ownership in the valuation table |
| 2021 land use rules, rule 30(1)(c) | On declaration of a peri-urban area: agricultural to commercial, or to industrial, institutional or intercity services | 10% of the commercial value |
| 2020 local government rules, rule 50(1)(c) | Site development zone (agricultural) to residential, after the committee’s clearance | 2% of the agricultural value in the valuation table; if none, 2% of the twelve-month average sale price set by the district price assessment committee |
The fee is a share of a value, so it scales with the land. For a 200 kanal scheme under rule 36, it is 5% of 200 times the valuation table’s residential rate per kanal for that mouza; look the rate up before you price the land. When the 2021 housing scheme rule and the 2021 land use rule both seem to fit, the authority’s demand decides which is charged: ask for it in writing before you commit.
The 2021 land use rules also set a scrutiny fee (Rs 5,000 up to 1 kanal, Rs 10,000 up to 2 kanal, Rs 20,000 above 2 kanal, Rs 50,000 for an area development project) and payment terms: 20% as a lump sum and the rest in seven equal instalments over two or three years, or the full fee within a year with a 5% rebate if paid within 45 days of the first demand, and a surcharge of 1.5% a month on late instalments (rule 30).
One document is often confused with these. RDA’s checklist for “change of land use”, with a processing fee of Rs 5,000 to Rs 20,000 by plot size and a conversion fee of 10% of the DC valuation table, is for individual plots and buildings, not for converting land to a housing scheme.
What cannot be reclassified
Some land is locked whatever a buyer is told. Under rule 39 of the 2020 local government rules, a local government may not reclassify the land use in an approved scheme or industrial estate for twenty years from its approval, may not turn commercial or residential land to industrial use, and may not reclassify plots reserved for schools, health facilities, police stations, post offices, places of worship, graveyards, public parks and open space in an approved scheme. The plans themselves can be revised, but not earlier than four years after notification (rule 29).
The order of checks
Before land is bought or a layout drawn, work through the status in this order:
| Step | Question | Where the answer comes from |
|---|---|---|
| 1 | Which authority and which rule books? | The development authority’s notified limits, mouza by mouza |
| 2 | What class or zone is the land in? | Notified classification map, structure plan or master plan |
| 3 | Does that class allow a scheme? | Rule 44 (2021) or rule 5(1) (2022) |
| 4 | Is conversion needed, and at what rate? | Rule 36 (2021 housing rules), rule 30 (2021 land use rules) or rule 50 (2020 rules) |
| 5 | What does the authority say in writing? | Land status reply under rule 5, valid six months |
| 6 | Does the layout follow the plan’s roads? | Roads proposed in the master plan must be accommodated (rule 10 of both housing rule books) |
Step 6 is where planning starts. A large site that will be developed over years needs its own plan that fits the official one: main roads where the master plan puts them, land uses that match the zones. That is the work of our master planning service, and the approval itself is covered on our housing scheme approval page. The fees that follow approval are in housing scheme approval costs in Punjab. To check the status of a particular piece of land, send the khasra numbers and the mouza through our contact page or on WhatsApp.