Demarcating plots in an approved housing scheme: from layout plan to pegs on the ground

Updated · 12 min read · RN Tech Associates · in Land records and land use

Short answer

Plot demarcation is marking on the ground, with survey instruments, the roads, plots and public sites of a housing scheme exactly as the approved layout plan shows them. It starts from control points on the same grid as the plan, sets out road centrelines and right of way, then block and plot corners, and checks every plot's sides and diagonals against the plot schedule. In Punjab the pegs must match the approved plan: deviations are barred.

Demarcating plots in an approved housing scheme: from layout plan to pegs on the ground

Key points

  • Demarcation sets out an approved plan on the ground; it is not the revenue department's demarcation of khasra boundaries.
  • The rules bind the pegs to the approved layout: no deviation, no plots beyond the approved number, no change of an allotted plot's number without consent.
  • Work from the authority-stamped plan and the geo-referenced CAD file, on the same grid as the survey it was drawn on.
  • Roads first, then blocks, then plots: every block is closed and every plot checked on its sides and diagonals.
  • No Pakistani rule sets a setting-out tolerance, so write one into the contract.
  • Where the ground and the plan disagree, stop and revise the plan formally; never absorb the difference into plots on site.

What plot demarcation means

Plot demarcation is the survey work that turns an approved layout plan into marks on the ground: every road edge, block corner, plot corner and public site, pegged where the plan puts it. It is the last stage before plots are handed over, and the one buyers see. On our scheme development page it is the final step of the journey, after the land check, survey, layout and approval.

Two kinds of “demarcation” are often confused:

Revenue demarcation Plot demarcation in a scheme
What it fixes Boundaries of khasra numbers in the land record Roads, blocks, plots and public sites inside an approved scheme
Done by Revenue staff, on an application Surveyors engaged by the sponsor
Works from The revenue map (aks shajra) and record The approved layout plan and its CAD file
Matters for The scheme’s outer boundary, title disputes Allotment, possession, building plans, handover

This guide covers the second. The outer boundary still has to agree with the revenue map, which is why the scheme survey ties the khasra boundaries in first; how that is read is in our guide to the khasra plan and aks shajra.

If you own or are buying one plot

Most people who search “plot demarcation meaning” have one plot and one worry: is the land I am paying for the land I will get? In plain words, demarcation means finding your boundary on the ground and marking it with pillars, so you and your neighbours can see where it runs. Which route you take depends on where the plot is.

Your plot is Who marks the boundary What the mark rests on
In an approved housing scheme The scheme’s sponsor, from the approved layout plan (the rest of this guide) The authority-stamped plan and its plot schedule
Agricultural or village land with a khasra number A Revenue Officer, on an application The revenue map (aks shajra) and the record of rights
In a scheme, but the marks are missing or disputed Ask the sponsor to re-peg it from the plan; a private survey can check it The same approved plan

Revenue demarcation. Section 117 of the Punjab Land Revenue Act 1967 lets a Revenue Officer, “on the application of any person interested”, define the limits of an estate, a holding or a field, and require boundary marks to be put up or repaired. Section 121 lets the Board of Revenue make rules on how boundaries are demarcated and what the marks are made of. Once a boundary is settled this way, section 122 says the settlement decides where the line and the marks are, and the rights of the owners on either side. So a revenue demarcation is the one that settles a dispute between neighbours; a private survey, however accurate, does not.

Why you should not do it yourself. Section 134 lets a Revenue Officer fine anyone who wilfully destroys, injures or removes a lawful boundary mark. If a mark has gone, ask for it to be restored. Do not set your own.

What a private survey adds. A surveyor can measure your plot against the papers before you pay, and show the gap in figures: the sides and area in the deed or the plan against what is on the ground, and whether a neighbour’s wall or a road edge has moved into it. That is evidence for your talks with the seller, the society or the revenue office. It does not replace the Revenue Officer’s order. Our guides on checking land before you buy and on checking a plot against the approved layout show what to compare, and checking a plot before you buy in Pakistan sets the papers, the approval and the ground side by side.

What to bring to the office. The registered deed, the fard (record of rights), the khasra number, a certified copy of the village map, and your CNIC. We found no published fee or form for a demarcation application, so ask the tehsil in writing before you pay anyone. The Act leaves the detail to the Board of Revenue’s rules, which we did not find online.

Before you build: the society’s demarcation for your house

A second meaning is the one most owners in an existing society mean. Once your building plan is approved, the society’s building control office marks your plot for you before any digging starts. This is a permission step on your own plot. It is not the sponsor’s pegging of the whole scheme, and it is not a revenue demarcation. Rules and forms are set by each society, so treat the steps below as one worked example and ask your own office for its current list.

DHA Lahore’s building control page (read on 15 November 2026) is a good example because it is published in full. It says demarcation “is required before construction” and comes after the drawing is approved. The owner, or the society’s authorised special power of attorney holder, submits a signed set to the main office, and gets an acknowledgement slip with the date to collect the demarcation papers. The page lists:

Item What DHA Lahore asks for
Dues A no-objection certificate (NOC) that dues are cleared
Form The demarcation and inspection booklet, filled in by the owner or the authorised power of attorney holder
Undertaking A stamp-paper undertaking, attested by an Oath Commissioner, for stacking material and a temporary hut
Approval A photocopy of the drawing approval letter
Possession The paid challan for possession charges
Basements only A method statement, an earth-moving machinery undertaking and a refundable security challan

The same page gives a timeline of 7 days and shows no charge for the demarcation. Three conditions matter more than the paperwork:

  • It expires. Demarcation is valid for one month only if construction has not started. If you are not ready to break ground, do not collect it early.
  • Site arrangements come first. A septic tank and a temporary lavatory must be built inside the plot as the approved drawing shows, before the field staff visit.
  • It is a gate for later steps. Temporary sewerage, water and sewerage connections and the completion certificate each depend on field inspections that check the build against the approved drawing.

Other societies, development authorities and local governments run their own versions, with different forms, fees and timelines. Ask for the written list before you pay anyone. Whatever the office calls it, two checks are yours to make. First, that the plot number and sides on the demarcation paper match your deed and the approved layout plan. Second, that the pegs on the ground match the paper. A surveyor can check the second against the plan (see setting out a building: steps and checks). The building plan itself comes first: see our guide to RDA building plan approval in Rawalpindi.

The approved plan is the only drawing that counts

In Punjab, plot demarcation reproduces the approved layout plan, and the rules leave little room to do anything else.

  • No deviation. The authority “shall ensure that there is no deviation” from the approved plan, and may visit without notice to check (2021 rules, rule 50; 2022 rules, rule 35).
  • No extra plots. The 2022 approval letter (Form D) makes “sale or commitment of plots over and above the total number of plots provided in the approved scheme” an offence.
  • Numbers are fixed. Plot numbers follow the form set by the rules (Form G under the 2021 rules, Form F under the 2022 rules), and the allotment agreement must say the allotted number will not change without the allottee’s written consent (2021 rule 47(2)(a); 2022 rule 32(2)(a)).
  • Public land is handed over by the plan. Roads, parks, open spaces and the graveyard are transferred to the authority by a deed tied to the approved plan, and the 2022 approval letter requires the sponsor to hand over possession of those areas.
  • Disputes do not move the plan. Since July 2026, rule 27 of the 2021 rules says that if litigation over the land starts after development or sale of plots, “no change in the approved layout plan shall be permitted”.

The rules also ask for what demarcation makes visible: a guide map at the entrance and a board at the corner of each road showing plot numbers and block names (2021 rule 10, other requirements, item (d); 2022 rule 10(1)(b)). What the layout sheet itself must carry, including plot numbering and chamfers, is set out in our guide to what a housing scheme layout plan must show.

Before the first peg

Most demarcation errors are made in the office, not on site. Before anyone goes out:

  1. Get the right drawing. Use the plan with the authority’s seal and signature, and the geo-referenced soft copy the sponsor filed with it (2021 rule 24(1)(b)(ii); 2022 rule 6(3)). Check that the CAD file and the stamped sheet agree: same plot dimensions, same road widths, same plot count as the area statement.
  2. Check the grid. The CAD file must be on the coordinate system of the topographic survey it was drawn on. A file drawn on a different grid, or never tied to one, will place the plots metres away from where they belong.
  3. Recover or rebuild control. Find the survey’s control points on site and check them against each other before trusting any. Lost points are re-established from the surviving ones and checked again.
  4. Read the plot schedule. Every plot’s sides, and the chamfer on corner plots (5 x 5 ft up to one kanal and 10 x 10 ft above, under rule 9 of each rule book), are set out from it.

Step by step on site

Demarcation runs from the large to the small, so that errors show up early and do not pile into the last plots.

  1. Scheme boundary. Mark the corners of the approved boundary and compare them with the khasra boundaries found on the ground. Any land excluded during approval, for example disputed land cut out after the public notice, stays outside.
  2. Road centrelines. Set out the centreline of each road, starting with the main roads, then mark the right of way on both sides. Right of way is the width between the two opposite properties, so these lines are also the front lines of the plots.
  3. Block corners and closure. Mark the corners of each block between roads and measure the block’s sides and diagonals. A block that does not close to its design dimensions is fixed now, before any plot is pegged inside it.
  4. Plot corners. Set out the plot corners from the block lines, with the chamfer on each corner plot.
  5. Public sites. Mark the parks, open spaces, graveyard, public building sites and service sites (tube well, overhead tank, disposal), which go to the authority by the transfer deed.
  6. Independent check. Re-measure a sample of plots, or all of them, from a different set-up or by tape: each plot’s frontage, depth and diagonals against the schedule.
  7. Number on the ground. Put each plot’s number on its marker, in the sequence of the approved plan.

What gets marked, and how it is checked

Item Taken from Checked by
Scheme boundary corners Approved boundary dimensions; geo-referenced file Comparison with the khasra boundary on the ground
Road centreline and right of way Road widths on the approved plan Width measured property line to property line
Block corners Block dimensions in the CAD file Sides and diagonals close to the design
Plot corners Plot schedule (size and dimension of each plot) Frontage, depth and both diagonals
Corner chamfers 5 x 5 ft or 10 x 10 ft by plot size (rule 9) Measured on each corner plot
Public and service sites Area statement and approved plan Area and position against the plan
Plot numbers Approved numbering (Form F or G) Read-through against the plan, block by block

Accuracy and markers

No Pakistani rule we have found states how close a plot corner must be to its design position. The international standard for building setting-out, ISO 4463-1:1989, gives values for permissible deviations, but they sit in the paid text, so we do not quote them. Agree a number in the demarcation contract instead: how far a corner may be from its design position, and how far a plot’s measured sides may differ from the schedule. A stated number lets both sides check the work.

The rules do not say what a marker must be. Choose markers for the life of the job: corner pegs placed before road and sewer works are often lost when trenches are cut, so set offset or reference marks clear of the works that let a lost corner be put back exactly. During construction, our engineering survey work re-marks lost corners and sets out roads and services from the same control, so the pegs and the infrastructure stay on one grid. How the works are inspected and how mortgaged plots are released as they are completed is in development periods and release of mortgaged plots.

When the ground and the plan disagree

Sometimes the plan does not fit: a road clashes with an existing structure, the boundary is short on one side, or a block will not close to its design. The temptation is to absorb the difference into a few plots. Do not: those plots no longer match the approved schedule, their buyers’ agreements or the plan the authority will check against.

Stop, measure the problem exactly, and take it to the authority as a formal change. Both rule books allow revision of an approved scheme, and the 2021 rules allow a one-time partial revision of up to 10% of the scheme’s area. Since July 2026 that partial revision needs a valid development period, may not reduce road widths, and its time counts against the development period. What can and cannot move is covered in our guide to revising an approved layout plan.

The record you keep

Demarcation should leave a record, not just pegs. At the end of the job the sponsor should hold:

  • a coordinate list of every peg as set, on the scheme’s grid;
  • the check measurements for each block and plot, against the schedule;
  • a drawing of the as-pegged plots, signed off against the approved plan;
  • a note of every lost and re-set corner, with the date.

That record answers an allottee’s question about a boundary in minutes, and it is becoming part of the transfer system. In development authority areas, the July 2026 amendment requires booking agreements and the property ownership certificate to go through the Housing Society Management System developed by the Board of Revenue (rules 47 and 48); in Lahore, the property certificate already links each plot to digital maps, as our guide to Lahore’s property certificate and HSMS explains. A scheme whose plots were set out on the approved grid, and recorded, is ready for that.

We demarcate plots from the approved layout plan, on the grid of our housing scheme survey, and hand over the coordinate record with the pegs. To plan demarcation for an approved scheme, send the approved plan and the CAD file through our contact page or on WhatsApp.

Want RN Tech Associates to handle this for your site?

Send the location and what the work is for. We reply with the questions that decide scope and price.

Questions

Common questions

01What is plot demarcation?

It is the survey work that marks a plot's corners and boundaries on the ground, with pegs or pillars, at the positions the approved layout plan gives. In a housing scheme it covers every road, block, plot and public site, so that what is sold, built and handed over matches what was approved.

02What is the difference between demarcation and possession of a plot?

Demarcation is the marking of the plot on the ground; possession is the handover of that marked plot to the allottee. The Punjab rules make the possession date a term of the allotment agreement and require the sponsor to pay 2% a month of the amount paid if possession is late, so demarcation has to be done and checked before possession can be given.

03Who demarcates plots in a housing society?

The sponsor is responsible, and the work is done by surveyors working from the approved layout plan. The authority does not peg plots, but it can inspect the scheme at any time without notice and act against any deviation from the approved plan.

04Can a housing society change my plot number?

Not on its own. Both Punjab rule books require the allotment agreement to say that the number of the allotted property shall not be changed without the allottee's prior written consent. Plot numbers are fixed on the approved layout plan in the form the rules set.

05What happens if my plot on the ground is smaller than on the plan?

The approved plan and plot schedule are the reference, so ask for the plot to be re-measured against them, side by side and corner to corner. If the scheme cannot fit the approved plots on the ground, the fix is a formal revision of the layout plan through the authority, not a quiet cut to some plots.

06Is plot demarcation the same as a demarcation survey by the patwari?

No. Revenue demarcation fixes the boundaries of khasra numbers in the land record, which matters for the scheme's outer boundary and for disputes. Plot demarcation sets out the inside of an approved scheme from its layout plan. A scheme usually needs both: the outer boundary agreed against the revenue map, then the plots set out within it.

07What does plot demarcation mean in simple words?

It means finding the edges of a plot on the ground and marking them with pegs or pillars. In the revenue record that is done by a Revenue Officer on application. Inside a housing scheme it is done by surveyors from the approved layout plan.

08How do I get my own plot demarcated in Punjab?

For village or agricultural land, apply to the revenue office. Section 117 of the Punjab Land Revenue Act 1967 lets a Revenue Officer define a field's limits on the application of a person interested and require boundary marks. For a plot in a scheme, ask the sponsor to re-peg it from the approved plan. We found no published fee, so ask in writing.

09Is a private survey accepted instead of revenue demarcation?

Not to settle a boundary. Under section 122 a boundary settled by the revenue procedure decides the line and the neighbours' rights. A private survey is useful evidence of what is on the ground, and a good way to check before you buy.

10Do I need plot demarcation before I build a house in a society?

Usually yes. Societies such as DHA Lahore require it after the building plan is approved and before construction starts, and issue it through their building control office. DHA Lahore's page lists a 7 day timeline and says the demarcation is valid for one month only if construction has not started. Other societies set their own forms and timelines, so ask yours for the current list.

Sources

  1. Punjab Development Authorities Private Housing Schemes Rules 2021, rules 9, 10, 24, 27, 43, 47 and 50, Punjab Gazette (Extraordinary), 7 December 2021 (FDA copy, read from the kept copy fetched 2 November 2026)
  2. Amendments to the Punjab Development Authorities Private Housing Schemes Rules 2021, Punjab Gazette (Extraordinary), 15 July 2026: rules 27, 43(8), 47 and 48 (copy in RDA downloads)
  3. Punjab Private Housing Schemes Rules 2022, Notification No. SOR(LG)8-5/2022: rules 6, 9, 10, 32, 35 and 43, Forms D and F (LG&CDD compendium)
  4. Punjab Land Revenue Act 1967 (Act XVII of 1967), sections 117, 121, 122 and 134 (Board of Revenue Punjab copy; read from the kept copy, fetched 4 November 2026)
  5. ISO 4463-1:1989, Measurement methods for building: setting-out and measurement, Part 1 (catalogue entry; deviation values are in the paid text)
  6. DHA Lahore, Building Control: demarcation, plan approval and completion certificate (DHA Lahore website, read 15 November 2026; one society's procedure, used as an example)

Rules and fees change. Check the current notification with the authority before you file; we do this on every job.

→Request a survey

Tell us about the site

Location, rough size and what you need it for. We reply with the questions that decide the scope and the price.

Town, area or a Google Maps link.

Rough size, purpose, deadline. Drawings can follow by email or WhatsApp.