What setting out is
Setting out is the reverse of a survey. A survey measures what is on the ground and draws it; setting out takes what is drawn and marks it on the ground, so the builders can work to it. Its products are pegs, nails, paint marks, profiles and level marks, each standing for a point in the design: a building corner, a grid line, a column centre, a floor level.
The international standard for it, ISO 4463-1:1989 (reviewed and confirmed by ISO in 2023), describes the work in three stages, and that structure is the clearest way to think about any building:
- Primary system. A network of control points covering the whole site, “connected to the official control system” (national or municipal coordinates), from which everything else is measured.
- Secondary system. The grid or main lines of each building, set out from the primary points.
- Position points. The marks for individual elements, “for instance columns and walls”.
Levels run alongside, from a benchmark carried to the site, and on multi-storey buildings points are transferred vertically from floor to floor. It is part of an engineering survey, and it depends on the same control as the survey the design was drawn on.
Before anyone goes to site
Most setting-out errors are made in the office. Before the first peg we check the design itself:
- Do the drawings close? Grid dimensions should add up to the overall dimensions, and coordinates (if given) should agree with the dimension strings. A 50 mm discrepancy between the architect’s and the structural engineer’s grid is common and should be settled on paper.
- Which drawing revision? Set out only from the current revision, and write its number on the setting-out record.
- Does the building fit the plot? The building lines must respect the setbacks the approved plan shows, which means the plot boundary must be right first. Where plot corners are missing or doubtful, they are re-established from the approved layout, as described in our guide to plot demarcation in an approved housing scheme.
- What is the level datum? Agree one benchmark and the design value of the plinth or ground floor against it. In Islamabad, plinth height is controlled against the front road level, so that level must be measured, not assumed.
- Units. Pakistani drawings often mix feet and metres. Decide the setting-out unit and convert once, in the office.
The steps, stage by stage
On site the order matters, because each stage is set from the one before. This is how we set out a typical framed building:
| Stage | What is set out | Set from | How it is marked |
|---|---|---|---|
| 1. Control | Three or more control points and at least one benchmark, outside the works | Official coordinates, or a site grid tied to the plot boundary | Concrete-set pins or nails, protected; described with sketches |
| 2. Boundary check | Plot corners and building lines | Control and the approved plan | Checked against corner pillars; differences reported before going on |
| 3. Main grid lines | Two main lines of the grid, at right angles | Control | Offset pegs or profiles (timber boards with nails on line) clear of the excavation |
| 4. Remaining grid | All other grid lines | The main lines | Nails on profiles; diagonals measured |
| 5. Excavation and foundations | Footing and pit outlines, bottom levels | Grid lines and benchmark | Pegs and level marks, re-set as excavation removes them |
| 6. Plinth | Column centres, wall lines and plinth level | Grid lines and benchmark | Marks on the foundation or plinth beam; level marks |
| 7. Each floor | Grid and column positions on each slab; floor level | Points transferred vertically from below, and the benchmark | Marks on the slab; level transferred up a column or by instrument |
Two habits make the sequence work. Control and benchmarks go where construction will not disturb them, and are checked against each other at every visit; ISO 4463-1 advises positioning benchmarks so that “sight lengths do not exceed 40 m” and change points are few. And the main lines are carried on offset marks outside the dig, because pegs inside it do not survive the first machine.
The checks that make it reliable
A set-out point that has not been checked is a guess. ISO 4463-1 separates two kinds of measurement: a “compliance measurement” verifies that a completed stage is within its permitted deviation, and a “check measurement” is an independent measurement “to check the correctness and accuracy of a previous measurement”. Caltrans’s surveys manual, written for highway structures, asks surveyors to verify set-up points “by making check measurements from other control points” before using them, and to check every staked position against its computed position, keeping the results.
| What is checked | How | When (hold point) |
|---|---|---|
| Control points | Measure between them and compare with their coordinates; re-observe from a second point | Every visit, before setting out |
| Benchmark | Level to a second benchmark and back; closure within the agreed limit | Every visit that sets levels |
| Instrument | Level collimation (two-peg) test; total station check on a known distance | Start of the job and after any knock; Toronto’s standard limits collimation to 0.1 mm per metre |
| Building and grid lines | Diagonals of each rectangle; measure back to control; distances to the boundary | Before excavation |
| Column and wall positions | Tape between adjacent points; check from a second station | Before foundation concrete and at plinth |
| Levels | Close each level run on the benchmark | Before each pour |
| Upper floors | Compare transferred points with points set independently from control; check plumb of columns | Before each slab is cast |
The check must be independent: a different station, a different method or a different person. Re-measuring the same distance with the same tape from the same point only proves the arithmetic.
Tolerances: where the numbers come from
The tolerance for setting out is a number in the house construction contract, and it should be written there before work starts. No Pakistani building regulation we have read sets one. The usual sources are a named standard or a published specification, and it helps to see how they are expressed:
| Source | What it gives | Example |
|---|---|---|
| ISO 4463-1:1989 | Permitted deviations for primary points, secondary points, position points, vertical transfer and levelling, with “consequences of non-compliance” | Values are in the paid text; cite the standard and its clauses |
| Caltrans Surveys Manual, chapter 12 (2012) | Setting tolerances for each type of construction stake | Major structures, ground: 0.03 ft (about 9 mm) horizontally, 0.02 ft (about 6 mm) vertically; superstructure: 0.02 ft either way; minor structures such as sign and lighting foundations: 0.03 ft horizontally |
| RICS, Measured surveys (3rd edition) | Accuracy bands the survey must achieve | Bands A to C list setting out among their uses: plus or minus 2, 4 and 5 mm at 1 sigma |
Keep two ideas apart. The setting-out tolerance is how close the mark must be to its design position. The construction tolerance is how close the finished wall or column must be, and it is usually larger, because the builder needs room to work. A setting-out tolerance that uses up the whole construction tolerance leaves the builder none.
Islamabad: Form-D at plinth and every slab
Islamabad builds a formal check into the regulations. Under regulation 5.5 of the ICT Building Control Regulations, as amended by S.R.O. 1074(I)/2023, when the foundations reach plinth (damp-proof course) level and the boundary wall is up at least at the corners, the owner submits Form-D through the licensed architect. The architect certifies “the plinth, the plot size and the building lines” and issues a provisional certificate; a copy goes to CDA’s Land Survey Division “for verification of Plot lines, Plinth level, Plot size and the building lines”, which it does within 15 days. If a discrepancy is found, the construction is corrected before the final certificate; if not, “the violated portion may be demolished”. The regulation adds that Form-D is submitted again “at all slabs levels (before pouring the concrete)”.
That makes good setting out a regulatory matter as well as a quality one. A building line set from a misplaced boundary wall, or a plinth set from the wrong road level, is found at plinth stage, when it is cheapest to fix. We measure the plot lines, building lines and plinth level by instrument before the architect certifies them, so the Form-D reflects what is on the ground. We found no equivalent published form for Rawalpindi; ask RDA or the scheme’s management what inspection applies to your plot.
The setting-out record
Every visit should leave a record, signed on site. Ours contains:
- date, site, drawing numbers and revisions used;
- control points and benchmark occupied, and the check made on them;
- each point set: its name, coordinates or offsets, and how it was marked;
- the independent check on each point and its result;
- anything that did not fit the drawings, and who was told;
- names and signatures of the surveyor and the contractor’s representative.
The contractor and the supervisor see the same sheet, which is why it settles most disputes before they start. It also becomes the start of the as-built survey at the end of the job, and the evidence that project supervision needs at each hold point of a house build.
Mistakes we see most
- Measuring from the boundary wall. Walls are rarely on the plot line. Set from the corner pillars or the approved plan, then check the wall.
- Two benchmarks in use. The contractor uses one level, the plumber another. One benchmark, written on every drawing.
- Pegs inside the dig. Lost at the first excavation. Use offset marks outside the works.
- No diagonals. A rectangle with correct sides can still be a parallelogram.
- Points carried up without a check. Small errors in vertical transfer add up floor by floor; check upper floors against control.
- Feet and metres mixed on site. Convert in the office, once.
If you are tendering the work rather than doing it, the scope items that make setting out checkable (control, accuracy, records and acceptance) are set out in our guide to specifying an engineering survey for a tender. To book setting out or an independent check of someone else’s, send the drawings and the plot details through our contact page.