Engineering surveys and utilities

Setting out a building: the steps, the checks and the tolerances

Published · 8 min read · RN Tech Associates · in Engineering surveys and utilities

Short answer

Setting out is the survey that transfers a building's design from the drawings to the ground: control points first, then the building and grid lines, then the position of each foundation, column and wall, with levels from a fixed benchmark. Every stage is checked independently before the next is built on it. In Islamabad, CDA also verifies the plot lines, building lines and plinth level at plinth stage on Form-D, and again before every slab.

Setting out a building: the steps, the checks and the tolerances

Key points

  • Set out in three stages, as ISO 4463-1 does: control tied to official coordinates, a building grid, then position points for columns and walls.
  • A point that has not been checked by an independent measurement is not set out; build the check into the programme as a hold point.
  • Tolerances come from the contract or a named standard; ISO 4463-1 holds values in its paid text, and published manuals such as Caltrans's show how they are written.
  • In Islamabad, Form-D at plinth level puts plot lines, building lines and plinth level before CDA's Land Survey Division, and Form-D is filed again before each slab is poured.
  • Keep a setting-out record for every visit: what was set, from which control, how it was checked, and who signed.

What setting out is

Setting out is the reverse of a survey. A survey measures what is on the ground and draws it; setting out takes what is drawn and marks it on the ground, so the builders can work to it. Its products are pegs, nails, paint marks, profiles and level marks, each standing for a point in the design: a building corner, a grid line, a column centre, a floor level.

The international standard for it, ISO 4463-1:1989 (reviewed and confirmed by ISO in 2023), describes the work in three stages, and that structure is the clearest way to think about any building:

  1. Primary system. A network of control points covering the whole site, “connected to the official control system” (national or municipal coordinates), from which everything else is measured.
  2. Secondary system. The grid or main lines of each building, set out from the primary points.
  3. Position points. The marks for individual elements, “for instance columns and walls”.

Levels run alongside, from a benchmark carried to the site, and on multi-storey buildings points are transferred vertically from floor to floor. It is part of an engineering survey, and it depends on the same control as the survey the design was drawn on.

Before anyone goes to site

Most setting-out errors are made in the office. Before the first peg we check the design itself:

  • Do the drawings close? Grid dimensions should add up to the overall dimensions, and coordinates (if given) should agree with the dimension strings. A 50 mm discrepancy between the architect’s and the structural engineer’s grid is common and should be settled on paper.
  • Which drawing revision? Set out only from the current revision, and write its number on the setting-out record.
  • Does the building fit the plot? The building lines must respect the setbacks the approved plan shows, which means the plot boundary must be right first. Where plot corners are missing or doubtful, they are re-established from the approved layout, as described in our guide to plot demarcation in an approved housing scheme.
  • What is the level datum? Agree one benchmark and the design value of the plinth or ground floor against it. In Islamabad, plinth height is controlled against the front road level, so that level must be measured, not assumed.
  • Units. Pakistani drawings often mix feet and metres. Decide the setting-out unit and convert once, in the office.

The steps, stage by stage

On site the order matters, because each stage is set from the one before. This is how we set out a typical framed building:

Stage What is set out Set from How it is marked
1. Control Three or more control points and at least one benchmark, outside the works Official coordinates, or a site grid tied to the plot boundary Concrete-set pins or nails, protected; described with sketches
2. Boundary check Plot corners and building lines Control and the approved plan Checked against corner pillars; differences reported before going on
3. Main grid lines Two main lines of the grid, at right angles Control Offset pegs or profiles (timber boards with nails on line) clear of the excavation
4. Remaining grid All other grid lines The main lines Nails on profiles; diagonals measured
5. Excavation and foundations Footing and pit outlines, bottom levels Grid lines and benchmark Pegs and level marks, re-set as excavation removes them
6. Plinth Column centres, wall lines and plinth level Grid lines and benchmark Marks on the foundation or plinth beam; level marks
7. Each floor Grid and column positions on each slab; floor level Points transferred vertically from below, and the benchmark Marks on the slab; level transferred up a column or by instrument

Two habits make the sequence work. Control and benchmarks go where construction will not disturb them, and are checked against each other at every visit; ISO 4463-1 advises positioning benchmarks so that “sight lengths do not exceed 40 m” and change points are few. And the main lines are carried on offset marks outside the dig, because pegs inside it do not survive the first machine.

The checks that make it reliable

A set-out point that has not been checked is a guess. ISO 4463-1 separates two kinds of measurement: a “compliance measurement” verifies that a completed stage is within its permitted deviation, and a “check measurement” is an independent measurement “to check the correctness and accuracy of a previous measurement”. Caltrans’s surveys manual, written for highway structures, asks surveyors to verify set-up points “by making check measurements from other control points” before using them, and to check every staked position against its computed position, keeping the results.

What is checked How When (hold point)
Control points Measure between them and compare with their coordinates; re-observe from a second point Every visit, before setting out
Benchmark Level to a second benchmark and back; closure within the agreed limit Every visit that sets levels
Instrument Level collimation (two-peg) test; total station check on a known distance Start of the job and after any knock; Toronto’s standard limits collimation to 0.1 mm per metre
Building and grid lines Diagonals of each rectangle; measure back to control; distances to the boundary Before excavation
Column and wall positions Tape between adjacent points; check from a second station Before foundation concrete and at plinth
Levels Close each level run on the benchmark Before each pour
Upper floors Compare transferred points with points set independently from control; check plumb of columns Before each slab is cast

The check must be independent: a different station, a different method or a different person. Re-measuring the same distance with the same tape from the same point only proves the arithmetic.

Tolerances: where the numbers come from

The tolerance for setting out is a number in the house construction contract, and it should be written there before work starts. No Pakistani building regulation we have read sets one. The usual sources are a named standard or a published specification, and it helps to see how they are expressed:

Source What it gives Example
ISO 4463-1:1989 Permitted deviations for primary points, secondary points, position points, vertical transfer and levelling, with “consequences of non-compliance” Values are in the paid text; cite the standard and its clauses
Caltrans Surveys Manual, chapter 12 (2012) Setting tolerances for each type of construction stake Major structures, ground: 0.03 ft (about 9 mm) horizontally, 0.02 ft (about 6 mm) vertically; superstructure: 0.02 ft either way; minor structures such as sign and lighting foundations: 0.03 ft horizontally
RICS, Measured surveys (3rd edition) Accuracy bands the survey must achieve Bands A to C list setting out among their uses: plus or minus 2, 4 and 5 mm at 1 sigma

Keep two ideas apart. The setting-out tolerance is how close the mark must be to its design position. The construction tolerance is how close the finished wall or column must be, and it is usually larger, because the builder needs room to work. A setting-out tolerance that uses up the whole construction tolerance leaves the builder none.

Islamabad: Form-D at plinth and every slab

Islamabad builds a formal check into the regulations. Under regulation 5.5 of the ICT Building Control Regulations, as amended by S.R.O. 1074(I)/2023, when the foundations reach plinth (damp-proof course) level and the boundary wall is up at least at the corners, the owner submits Form-D through the licensed architect. The architect certifies “the plinth, the plot size and the building lines” and issues a provisional certificate; a copy goes to CDA’s Land Survey Division “for verification of Plot lines, Plinth level, Plot size and the building lines”, which it does within 15 days. If a discrepancy is found, the construction is corrected before the final certificate; if not, “the violated portion may be demolished”. The regulation adds that Form-D is submitted again “at all slabs levels (before pouring the concrete)”.

That makes good setting out a regulatory matter as well as a quality one. A building line set from a misplaced boundary wall, or a plinth set from the wrong road level, is found at plinth stage, when it is cheapest to fix. We measure the plot lines, building lines and plinth level by instrument before the architect certifies them, so the Form-D reflects what is on the ground. We found no equivalent published form for Rawalpindi; ask RDA or the scheme’s management what inspection applies to your plot.

The setting-out record

Every visit should leave a record, signed on site. Ours contains:

  • date, site, drawing numbers and revisions used;
  • control points and benchmark occupied, and the check made on them;
  • each point set: its name, coordinates or offsets, and how it was marked;
  • the independent check on each point and its result;
  • anything that did not fit the drawings, and who was told;
  • names and signatures of the surveyor and the contractor’s representative.

The contractor and the supervisor see the same sheet, which is why it settles most disputes before they start. It also becomes the start of the as-built survey at the end of the job, and the evidence that project supervision needs at each hold point of a house build.

Mistakes we see most

  1. Measuring from the boundary wall. Walls are rarely on the plot line. Set from the corner pillars or the approved plan, then check the wall.
  2. Two benchmarks in use. The contractor uses one level, the plumber another. One benchmark, written on every drawing.
  3. Pegs inside the dig. Lost at the first excavation. Use offset marks outside the works.
  4. No diagonals. A rectangle with correct sides can still be a parallelogram.
  5. Points carried up without a check. Small errors in vertical transfer add up floor by floor; check upper floors against control.
  6. Feet and metres mixed on site. Convert in the office, once.

If you are tendering the work rather than doing it, the scope items that make setting out checkable (control, accuracy, records and acceptance) are set out in our guide to specifying an engineering survey for a tender. To book setting out or an independent check of someone else’s, send the drawings and the plot details through our contact page.

Want RN Tech Associates to handle this for your site?

Send the location and what the work is for. We reply with the questions that decide scope and price.

Questions

Common questions

01What is a setting out survey?

It is the survey that marks a design on the ground so it can be built: the building corners, grid lines, foundation and column positions and the levels. It works from control points and a benchmark fixed before construction, and each mark is checked before it is used.

02Who is responsible for setting out a building?

The contract decides. Usually the contractor sets out from reference points and drawings the client or engineer provides, and the engineer or supervisor checks. The contract should say who sets out, who checks, and which control and benchmark everyone uses, so a dispute can be settled from the records.

03How accurate does setting out need to be?

As accurate as the specification says, and that should be stated before work starts. ISO 4463-1 gives permitted deviations for each stage in its paid text. As a published example, Caltrans's surveys manual sets stakes for major structures within 0.03 ft (about 9 mm) horizontally and 0.02 ft (about 6 mm) vertically of their computed position.

04What is a setting out survey report?

It is the record of a setting-out visit: date, drawings and revision used, control points and benchmark occupied, points set with their coordinates or offsets, the check made on each and its result, and the signatures of the surveyor and the person receiving the marks. It is what settles an argument later.

05How is a column grid set out?

The two main grid lines are set from control and marked on offset pegs or profiles outside the excavation, then checked by measuring the diagonals and closing back on control. The remaining grid lines are measured from them, and each column position is set from the grid at foundation level and again at plinth and every floor.

06Does CDA check setting out in Islamabad?

Yes, at plinth level. Under regulation 5.5 of the ICT Building Control Regulations, as amended in 2023, the architect certifies the plinth, plot size and building lines on Form-D, and CDA's Land Survey Division verifies plot lines, plinth level, plot size and building lines within 15 days. Form-D is filed again at every slab level before the concrete is poured.

→Request a survey

Tell us about the site

Location, rough size and what you need it for. We reply with the questions that decide the scope and the price.

Town, area or a Google Maps link.

Rough size, purpose, deadline. Drawings can follow by email or WhatsApp.